© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] WASCA 173
Court of Appeal (WA)
2019-11-07
Murphy JA
Original judgment source is linked above.
(1) Adopting a 'hindsight' approach which required J‑Corp to avoid the particular incident, rather than exercise reasonable care as a builder and occupier who was required to address a risk that was identified and articulated in general terms.
(2) Finding that J‑Corp ought to have known that the unfilled pier was too weak to support loads such as those applied by the feet of roof carpenters, when that finding was not supported by the evidence.
In our view, both of these contentions are established.
(1) The pier was an unfilled pier constructed of relatively light weight fast wall brick. Such a pier was very weak and not capable of withstanding relatively low horizontal forces. A relatively low horizontal force applied to the top of the pier would cause it to become laterally unstable. An unreinforced pier would give no warning of its failure.[12]
(2) Structural drawings for the pier required that a galvanised rod running up the cavity in the pier be cast into the cavity. This meant that the pier cavity should be filled with mortar, cement or broken bricks and mortar.[13] The pier was not constructed in accordance with the engineering design as the rod had not been cast into the pier.[14]
(3) The horizontal force required to topple a cracked hollow brick pier was 'approximately 22 kg and the failure would be sudden and without warning. The horizontal force required to topple a reinforced pier would be approximately 71 kg.'[15]
(5) If the pier cavity had been filled, the horizontal forces applied by Mr Thompson as he attempted to move back to the main wall of the house would not have been sufficient to cause the pier to fail.[18]
(6) Generally tradespeople would not be able to predict the destabilising force required to topple a brick pier.[19]
[I]t is fundamental that the question of whether [J-Corp] breached [its] duty to exercise reasonable care is approached prospectively, not retrospectively with the benefit of hindsight and without regard to the fact that the relevant risk materialised. (citations omitted)
The risk of harm alleged by Mr Thompson is the risk that a roof carpenter installing the roof would be injured as a result of the pier collapsing and suffer a not insignificant injury.
Mr Thompson says that the precaution [J-Corp] should have taken was to check the brickwork and ensure the cavity was filled.
(1) The unfilled pier was too weak to support loads such as those applied by the feet of roof carpenters and, as builder of the house, J‑Corp ought to have known this.[24]
(2) A reasonable person in J‑Corp's position should have foreseen that roof carpenters in the process of installing the roof to an isolated pier (including marking out the beams and wall plates) may at some stage walk or stand on an isolated brick pier and thereby apply horizontal forces sufficient to topple the pier.[25]
(3) It is reasonably foreseeable that in the process of performing the task of marking up the beams or wall plates to an isolated pier before the hip is installed, a roof carpenter may stand on and therefore step on and off the beams and/or pier and thereby apply horizontal forces sufficient to topple the pier.[26]
(4) The risk of a roof carpenter falling to the ground below if the pier collapsed whilst he was stepping on or off the pier in the process of marking up the beams or wall plates is clearly foreseeable, as is the risk of that fall resulting in injury.[27]
The trial Judge erred in finding that [J‑Corp] breached duties of care as builder and occupier:
1.1 He erred in law in finding that the relevant risk of harm was the risk of injury to a roof carpenter from standing or walking on an isolated pier and applying horizontal forces that were sufficient to topple the pier in that:
1.1.1 He formulated the risk of harm in broad terms in his finding that [J‑Corp's] duty was to use reasonable care when coordinating the activities of trades at the premises to avoid unnecessary risks of injury or minimise the risk of injury to those engaged in the activity it organised;
1.1.2 The finding of a secondary and more specific risk was not required and was derived from the application of knowledge of the particular pier, [Mr Thompson] and the incident and hindsight reasoning;
1.2 He erred in law and fact in making findings that were derived from hindsight reasoning and to the extent that each was a finding of fact it was not supported by the evidence:
1.2.1 There was a foreseeable risk and not insignificant risk, that [J‑Corp] knew or ought to have known, of injury to roof carpenters walking or standing on an isolated brick pier and applying horizontal force sufficient to topple the pier; and
1.2.3 In the exercise of reasonable care [J‑Corp] should have filled a cavity in the particular pier before roof carpenters embarked on their work;
The perception of the reasonable man's response calls for a consideration of the magnitude of the risk and the degree of the probability of its occurrence, along with the expense, difficulty and inconvenience of taking alleviating action and any other conflicting responsibilities which the defendant may have. It is only when these matters are balanced out that the tribunal of fact can confidently assert what is the standard of response to be ascribed to the reasonable man placed in the defendant's position.
If, instead of looking forward, the so called Shirt calculus is undertaken looking back on what is known to have happened, the tort of negligence becomes separated from standards of reasonableness. It becomes separated because, in every case where the cost of taking alleviating action at the particular place where the plaintiff was injured is markedly less than the consequences of a risk coming to pass, it is well nigh inevitable that the defendant would be found to have acted without reasonable care if alleviating action was not taken. And this would be so no matter how diffuse the risk was - diffuse in the sense that its occurrence was improbable or ... diffuse in the sense that the place or places where it may come to pass could not be confined within reasonable bounds.
Ought J-Corp to have known of the extent of the pier's weakness?
I find as a fact that the unfilled pier was too weak to support loads such as those applied by the feet of roof carpenters. As the builder of the house [J-Corp] ought to have known this. (emphasis added)
Now, for the purposes of this case, you have made a number of calculations and you've provided a number of drawings that - - -?---Yes.
- - - indicate what your calculations were?---Yes.
Now, that's not something that you would ever expect a person other than yourself, like an engineer, to do, prior to embarking upon a building job, would you?---No.
And you've said - why I ask that is, on this page, at paragraph 8, you've said:
In my experience, tradesmen will not be able to predict the destabilisation force required to topple such a brick pier.
?---Yes.
So you would not expect the ordinary person on the site, like either the ordinary tradesman like Mr Thompson or anybody of that nature who wasn't an engineer like you, with your experience, to be able to predict how much force was required to topple the pier?---I agree with that.
(1) There was a reasonably foreseeable and not insignificant risk that roof carpenters may be seriously injured by the structural failure of brickwork which they are standing on or near if the brickwork is not constructed to structural specifications.[67] The higher the brickwork, the greater the risk of injury to those working on or near it in the event of a structural failure of the brickwork.
(2) The probability that harm would occur if elevated brickwork failed because it was not constructed to structural specifications was relatively high, or at least not insignificant, and serious injury would be likely to result from the structural failure of such brickwork by or on which a roof carpenter was standing.[68]
(3) The burden of inspecting the brickwork and requiring the bricklayers to rectify structural defects was not great. It can be inferred that J‑Corp was contractually obligated to construct the house according to structural specifications in any event. J‑Corp had the contractual right, noted at [10] above, to inspect the bricklayer's work and require defects to b[69]rectified.69 J‑Corp employed [70]pervisors.70 Mr Tarry, a building supervisor called as a witness by J‑Corp, gave evidence that part of a supervisor's role was to inspect the work of a bricklayer after it was completed, including to see that piers had been completed in accordance with t[71] drawings.71
(4) The social utility of residential house construction would be advanced rather than impeded by checking to see that the house was constructed in accordance with structural specifications.[72]
Reinforcement rods built into brick piers are designed to:
Failed to inspect to see that the brickwork on the premises was constructed safely and/or in accordance with the plans before calling on TJO Roofing to commence work on the premises.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
Research Associate/Orderly to the Honourable Justice Mitchell
[1] Thompson v J-Corp Pty Ltd [2018] WADC 164 [1] (primary decision).
[2] Primary decision [22], [162] - [163].
[8] Primary decision [242] - [246], trial ts 290.
[13] Primary decision [82] - [83], [232].
[16] Primary decision [95], [303] - [304].
[20] Primary decision [284], [295].
[21] Primary decision [286] - [287].
[22] Primary decision [289] - [291].
[23] Primary decision [296] - [297].
[24] Primary decision [303] - [304].
[25] Primary decision [305], [325].
[28] Primary decision [340] - [343].
[32] Primary decision [349] - [350].
[33] Primary decision [352], [369].
[37] Primary decision [373] - [377].
[38] Primary decision [379] - [395].
[39] Primary decision [396] - [433].
[40] Primary decision [434] - [489].
[41] Paragraphs 1.2.2 and 1.3 were abandoned at the hearing of the appeal (appeal ts 94) and are not reproduced.
[42] Appellant's Submissions, par 11 (White AB 8).
[44] See primary decision [305], [325].
[47] Primary decision [287], [364], [369], [405].
[48] Wyong Shire Council v Shirt [1980] HCA 12; (1980) 146 CLR 40, 47 - 48.
[49] New South Wales v Fahy [2007] HCA 20; (2007) 232 CLR 486 [57].
[50] Vairy v Wyong Shire Council [2005] HCA 62; (2005) 223 CLR 422 [127].
[52] Roads and Traffic Authority of NSW v Dederer [2007] HCA 42; (2007) 234 CLR 330 [67]. Hayne J's judgment was also cited with approval in Fahy [58]. The passages in Vairy and/or Fahy have been further cited with approval in decisions of this court in Department of Housing and Works v Smith [No 2] [2010] WASCA 25; (2010) 41 WAR 217 [87] (which was in turn cited with approval in Taylor v Fisher [2018] WASCA 126 [58]); Davies v Tomkins [2009] WASCA 228 [72]; Jasmina Investments Pty Ltd v Vlahos [2009] WASCA 190 [14]; The Quadriplegic Centre Board of Management v McMurtrie [2009] WASCA 173 [83]; Hanna-Pauley v AMP Shopping Centres Pty Ltd [2007] WASCA 174 [41]; Alinta Gas Networks Pty Ltd v James [2007] WASCA 155 [39]; Fitzpatrick v Job [2007] WASCA 63 [203]; Shire of Toodyay v Walton [2007] WASCA 76 [29], [96].
[54] Adeels Palace Pty Ltd v Moubarak [2009] HCA 48; (2009) 239 CLR 420 [31]; CGU Insurance Ltd v Coote [2018] WASCA 117 [78]; Apostolic Church Australia Ltd v Dixon [2018] WASCA 146 [61].
[58] Primary decision [104], [111].
[59] Primary decision [393], [395].
[62] Stevens v Brodribb Sawmilling Co Pty Ltd [1986] HCA 1; (1986) 160 CLR 16, 47 - 48.
[63] Leighton Contractors Pty Ltd v Fox [2009] HCA 35; (2009) 240 CLR 1 [21].
[64] Primary decision [306] - [323].
[67] Section 5B(1)(a) and (b) of the Civil Liability Act.
[68] Section 5B(2)(a) and (b) of the Civil Liability Act.
[69] Section 5B(2)(c) of the Civil Liability Act.
[72] Section 5(2)(d) of the Civil Liability Act.
[73] Section 5(1)(c) of the Civil Liability Act.
[77] Appellant's Submissions, par 26.5 (White AB 13).
[79] Paragraph 9.3 of the Statement of Claim (See Blue AB 76, trial ts 302, 305 - 306 and appeal ts 37, 111 - 112).
(2010) 41 WAR 217
(1986) 160 CLR 16
(1980) 146 CLR 40
(2007) 232 CLR 486
(2005) 223 CLR 422
(2007) 234 CLR 330
(2009) 239 CLR 420
(2009) 240 CLR 1