Within 7 days of receipt of a claim for payment, the Superintendent shall:
(a) issue to the Principal and to the contractor a payment certificate stating the opinion of the Superintendent:
(i) the value of the work carried out by the Contractor in the performance of he Contract at the time for a claim for payment.
(ii) any moneys due to the Contractor under any provisions of the Contract.
(iii) amounts which the Principal is entitled to deduct for retention moneys, and
(b) Refer to the Principal
(i) claims for breach of Contract and interest on overdue payments, and
(ii) the matter of any moneys due from the Contractor to the Principal as setoffs.
together with such advice in respect of (a) and (b) as the Superintendent deems appropriate.
If the contractor fails to make a claim for payment, the Superintendent may nevertheless issue a payment certificate.
Within 28 days from the end of the month after receipt by the Superintendent of a claim for payment from the Contractor the Principal shall pay to the Contractor the amount due to the Contractor and shall provide written particulars of how the amount due was calculated.
The Principal's liability is to pay the amount due ascertained in accordance with Clause 42.2. In the calculation of the amount due to the Contractor, the Principal shall be bound to accept the amounts shown on the certificate of the Superintendent in respect of (a) (i), (ii) and (iii) above except in the case of manifest error.
Payment of moneys shall not be evidence of the value of work or an admission of liability or evidence that work has been executed satisfactorily but shall be a payment on account only, except as provided by Clause 42.8.
Notwithstanding Clause 42.4, the Principal shall be obliged to pay for any item of unfixed plant and materials where the item is -
(i) to be imported into Australia, provided the Contractor has given the Principal a clean on board bill of lading or its equivalent, drawn or endorsed to the order of the Principal and, where appropriate, a custom's invoice for the item; or
(ii) listed in the Annexure and which is not an item to be imported into Australia, provided the Contractor establishes to the satisfaction of the Superintendent that the Contractor has paid for the item, and the item is properly stored, labelled the property of the Principal and adequately protected.
Upon payment to the Contractor of the amount which includes the value of the item, the item shall be the property of the Principal free of any lien or charge.
Except as provided in the contract, the Principal shall not be obliged to pay for any item of unfixed plant and materials which is not incorporated into the Works."
16 The difference between the parties in respect of the construction of this clause is whether the clause provides for progress claims on a monthly basis on the 15th day of the month or the nearest working day after the 15th day, which is what is set out in the annexure, up until the issue of a certificate of practical completion or whether there exists a right to issue progress claims for the subsequent months after the certificate of practical completion up until the expiration of the defects liability period 12 months thereafter. The plaintiff suggests that the contractual ability to make progress claims continues after practical completion whilst the defendant contends that the proper construction of the clause provides that the right to issue monthly claims only continues up until the issue of a certificate of practical completion.
17 In the present case progress claims 12 and 13 are in respect of dates and work in part performed subsequent to practical completion. According to the defendant's submissions, therefore, none of these progress claims was a progress claim made under the contract, as there is no due date for such claims.
18 After adding in the annexure referred to the words at the commencement of clause 42.1 provide that claims may be made:
"Monthly on the fifteenth day of the month or the nearest working day after the fifteenth day and upon issue of a certificate of a practical completion and within the time prescribed clause 42.7".
19 Of importance in understanding the meaning of 'payment claim' are the terms of s 42.7 which are as follows:
"42.7 Final payment claim
Within 20 days after the expiration of the defects liability period, or where there is more than one, the last to expire, the contractor shall lodge with the superintendent a final payment claim and endorse it 'final payment claim'."
20 Thus one has a clause dealing with payments which includes payment claims in general and a final payment claim. On the face of the clauses there is nothing in them to give any indication that a payment claim may not be issued after the issue a certificate of practical completion. On the ordinary meaning of the words payment claims can continue on the dates provided for in the clause.
21 Although the plaintiff's argument was not expressed as claim for an implied term one would almost need an implied term in order to justify such a reading of the contract. The defendant sought to justify its reading of the contract in this way by reference to, inter alia, the effect of practical completion. It pointed to the fact that it was the builder that nominated practical completion on this occasion and referred to the definition of practical completion in the general conditions which, inter alia, required the works to be complete except for minor omissions and minor defects. The defendant also pointed to the fact that there might be on the plaintiff's construction two payments in one particular month, for example in the month of practical completion. The date of practical completion and the time for the final payment are natural times for a payment claim and may not necessarily occur on the fifteenth day of the relevant month. It is probably for this reason that they are specified as additional times.
22 It is to be noted that clause 40 of the special condition deals with variations which may be directed by the superintendent. Clause 40.1, in dealing with variation to the work, provides, inter alia:
"The contractor shall not be bound to execute a variation directed after practical completion unless the variation is in respect of rectification work referred to in clause 37."
23 Clause 37 is the clause giving power to the superintendent to direct rectifications in respect of defects or omission which exist at practical completion. It is thus clear that there is a power for the direction of a variation in connection with rectification work during the defects liability period. The other thing to notice about clause 40.1 is that it is expressed in terms of the contractor not being bound to execute a variation. It is always open, of course, for a contractor to waive that protection and agree to a variation. From a practical point of view there may well be circumstances in many projects where after the project is handed over by the builder the proprietor sees that it is desirable to carry out some changes to the work. Such work in these circumstances would fall under the terms of the contract.
24 The defendant's construction, which would seek to imply a term to the effect that no payment claim could be made between the date of practical completion and the final payment claim under 42.7, on the face of the contract contradicts the express terms to which I have referred. I would not have thought that it is so obvious that it goes without saying and the contract is quite effective without the implied term.
25 The plaintiff also supported this position on the basis that the defendant had, in fact, issued a progress certificate number 12 on 26 June 2003. This, it said, was a clear recognition of the fact that there was a right to make progress certificates between practical completion and the end of the defects liability period. The answer to this, from the defendant, is simply that the plaintiff is not asserting payment under a contractual right but under its statutory right under the Act. It points to the fact that there has been no variation of the contract alleged or that there has been some estoppel alleged.
26 In my view the construction contended for by the defendant on this aspect of the contract is untenable and accordingly I would not see it as giving rise to a triable issue.
Whether Progress Claims 12 and 13 were supported by the evidence and information required by the contract and the Act
27 Clause 42.1 of the contract provides that progress claims shall be "supported by evidence of the amount due to the contractor and such information as the superintendent may reasonably require". Relying upon Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 56 NSWLR 576, [2003] NSWCA 4; the defendant submits that there was no compliance with the condition precedent.
28 It relied upon evidence of Mr Tucker, a quantity surveyor who was responsible for assessing matters for the defendant, that he was unable to assess the progress claims without a detailed discussion with representatives of the plaintiff in order to understand the claims made in the progress claims.
29 The plaintiff's argument sought to distinguish the case relied upon by the defendant, both upon the terms of the contract and the legislation. It also submitted that if the contract had not provided a due date s 11(b) of the Act applied making the payment payable within 10 days after the claim was made.
30 In Brewarrina Shire Council v Beckhaus Civil Pty Ltd the Court of Appeal held by a majority that the obligation of the superintendent to issue a payment certificate in regard a progress claim under the contract is subject to the condition precedent that the contractor support that claim with evidence of the amount due to it and with such information as the superintendent might reasonably require. The relevant judgment of the majority was that given by Ipp JA.
31 One of the arguments in Beckhaus was that the condition precedent contended for by the Council was inconsistent with the clause in that case namely that if no payment certificate has been issued then the principal shall pay the amount of the contractors claim. This was referred to at paragraph 14 of the judgment of Ipp JA in these terms:
"14 I do not agree, with respect, that the condition precedent contended for by the Council would be inconsistent with the provision that "if no payment certificate has been issued, the principal shall pay the amount of the Contractor's claim". The obligation to pay the amount of the contractor's claim when no payment certificate has been issued is, by the third paragraph of cl 42.1, expressed to be "subject to the provisions of the contract". This express qualification (that is, that the obligation to pay be subject to the terms of the contract) means that no inconsistency arises."
32 The submissions of the plaintiff were that the relevant parts of the clause in Beckhaus and in the present case were different and in particular the fourth paragraph of the clause in the present case did not contain the words "subject to the provisions of the contract". It was these words, according to the submissions, that allowed the condition precedent to apply because there was no inconsistency.
33 It is to be noted that it is the fourth and fifth paragraphs of the clause in the present case, quoted at paragraph 15 above, which are important and which are quite different to the provisions of the contract in Beckhaus, which appears at paragraph 4 in the judgment of Ipp JA. Although the relevant words have been deleted, it is apparent that the issue of a certificate is still required because in the fifth paragraph, in the present case, if payment is to be made the principal is bound to accept the certificate of the superintendent in respect of certain items. This would tend to suggest that the principal's liability to pay is thus also conditioned upon the issue of a certificate. In these circumstances an inconsistency does not arise. Accordingly, it would seem to me, that the principles in Beckhaus equally apply having regard to the contract in the present case.
34 The plaintiff also submitted that it would be an unusual condition for a payment claim to exist under the Act that does not fall due for payment because of non-compliance with a condition precedent. It referred to amendments to the Act in March 2003 which included: