"Within 28 days after the expiration of the Defects Liability Period, or where there is more than one, the last to expire, the Contractor shall lodge with the Superintendent a final payment claim and endorse it 'Final Payment Claim'…"
37 The real question, which arises on the Appeal, is as to whether the Master is shown to have committed an appellable error on the approach which he took to this construction issue in the environment of a summary judgment application.
38 In my view, for the reasons given below, the answer to this question is in the affirmative.
General Steel and the construction issue
39 Before dealing with the construction issue it is necessary and appropriate to examine the extent to which the General Steel test remains applicable to the subject field of discourse.
40 The appellant has submitted that for the very reason that the legislative scheme preserves ultimate final rights [cf section 32] this is an environment in which the General Steel test should not be strictly applied. The submission is that the underpinning for that test concerns preserving the rights of a party to its day in court for the purpose only of determination of its ultimate rights at law.
41 I do not see the matter in this way. Notwithstanding the fast track legislative scheme aimed at ensuring quick adjudication of disputed progress claims, the fact remains that the pre-conditions stipulated for by the Act as requiring to be satisfied in order to permit a claimant to procure a judgment do require to be strictly complied with.
42 Where established, the entitlement of a claimant to enter judgment under the Act is likely to have very real consequences to the respondent in any given case. A respondent may be forced into liquidation by reason of the effect of the judgment or otherwise dramatically affected by the financial effect of the immediate requirement to pay the judgment debt. This is not an occasion for moving one jot outside of the General Steel principles.
43 Returning to the question of construction the following may be said:
· The approach taken by the Master was to regard the respondent's construction as seeking "to imply a term to the effect that no payment claim could be made between the date of practical completion and the final payment claim under 42.7, on the face of the contract contradicts the express terms [of the contract]".
· The Master expressed the view that he would not have thought that such an implied term was so obvious that it went without saying and that the contract was quite effective without the implied term.
· In my view this is not the territory of implication. It is rather the territory of contractual construction requiring to be determined in accordance with well-established principles in that regard.
· I do accept that there is clearly something to be said in favour of the proposition that the respondents construction does not take into account the possibility that prior to the expiration of the Defects Liability Period, the Superintendent may direct the Contractor to rectify any omission or defect in the work under the Contract existing at the date of practical completion or which becomes apparent prior to the expiration of the Defects Liability Period [clause 37]. Further and as the Master noted, clause 40.1 permits the Superintendent to direct the Contractor to execute variations within the general scope of the Contract although it also provides that the Contractor is not to be bound to execute a variation directed after Practical Completion unless the variation is in respect of rectification work referred to in clause 37.
· However, in my view the approach taken by the respondent cannot be said to be so obviously untenable that it cannot possibly succeed", "manifestly groundless", "so manifestly faulty that it does not admit of argument", one which "the court is satisfied cannot succeed".
· The respondent has thrown up an area where there is a real issue to be tried and for that reason the summary judgment application required is to be dismissed.
44 The respondent having thrown up an area where there is a real issue to be tried, the Master's approach having been shown to fail on General Steel bases to accept this as a triable issue, the summary judgment application was appropriate to be dismissed on this basis. It has been unnecessary in this regard to consider any particular aspect of the dates of the instant progress claims [both of which were served well after the date of practical completion and many many months prior to the expiration of the Defects Liability Period].
45 Further in my view the appellant is incorrect in its 'outflanking' submission that on this particular issue the respondent is debarred by section 15 (4) (b) (ii) from raising a defence in relation to this as a matter arising under the construction contract. The holding is that section 15 only applies if subsections (1) (a) and (b) are satisfied and that the claimant must affirmatively establish what [within the meaning of section 14 (4)] was the due date for the progress payment to which the payment claim related.
The point reached on the Appeal
46 The Court has now held that:
· grounds 2 and 3 of the Notice of Appeal require to be dismissed;
· there was a triable issue on the construction matter which was put to the Master who failed to uphold the respondent's argument.
47 It is unnecessary to go further and to deal with any of the other matters which were the subject of submissions on the Appeal and/or notice of contention. In particular it is not necessary to treat with the holding [at [40]] following the reasons given [at [27]-[39]] where the Master did uphold the respondents claim that there was a triable issue in relation to another matter. Nor is it necessary to deal with the motion seeking leave to withdraw the concession made to the Master.
48 The appellant did submit that this was a circumstance in which the Court should proceed to finally determine the question of construction. That course is not available on the appeal.
Short minutes of order
49 The parties are to bring in short minutes of order when costs may be argued.
I certify that paragraphs 1-49
are a true copy of the reasons
for judgment herein of
the Hon. Justice Einstein
given on 29 March 2004