The statutory regime
14 The scheme for payment of payment claims under the Act is set out in ss 8, 13, 14(4) and 15. They provide that on and from each reference dated under a construction contract a person who had undertaken to carry out construction work under the construction contract is entitled to a progress payment - s 8.
15 A person referred to in s 8(1) who is or who claims to be entitled to a progress payment may serve a payment claim on the person who under the construction contract concerned is or may be liable to make the payment - s 13. The payment claim can be served up to 12 months after the construction work was carried out - s 13(4).
16 If a claimant serves a payment claim on a respondent and the respondent does not provide a payment schedule to the claimant within the time required by the construction contract or within 10 business days after the payment claim is served, whichever time expires earlier, the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claims relates - s 14(4).
17 If a respondent becomes liable to pay the claimed amount to the claimant under s 14(4) as a consequence of having failed to provide a payment schedule within the time allowed by that section and fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates (s 15(1)) then the claimant may recover the unpaid portion of the claimed amount from the respondent as a debt due to the claimant in any court of competent jurisdiction - s 15(2)(a)(i).
18 If a claimant commences proceedings under s 15(2)(a)(i) to recover the unpaid portion of the claimed amount from the respondent as a debt the respondent is not in those proceedings entitled to bring any cross-claim against the claimant or to raise any defence in relation to those matters arising under the construction contract - s 15(4).
19 Einstein J stated in Isis Projects Pty Ltd v Clarence Street Limited [2004] NSWSC 222 at para 33:
"Hence it is clearly necessary in order that a claimant prove that a respondent's liability has accrued under section 15 (1) (a) [to satisfy the precondition to be found in subsection (4) (a)], that the claimant prove that a valid payment claim has been served and also clearly prove what is the due date for the progress payment. There will of course always be a due date for a progress payment under a construction contract because the Act [s 11] provides for such a date as being either:
· the date on which the payment becomes due and payable in accordance with the terms of the contract; or
· if the contract makes no express provision with respect to the matter, the date occurring 10 business days after a payment claim is made in relation to the payment."
20 Bell's submission before the Magistrate was that the plaintiff's entitlement to a progress payment could only arise if it issued progress payments in 3 equal intervals in 3 equal amounts of $6,216.00 during construction, but Kann did not issue the progress claims in accordance with the construction contract. According to Bell, Kann is not a person entitled to a progress payment and therefore may not serve a payment claim pursuant to s 13 of the Act.
21 Five tax invoices were in evidence before the Magistrate. They represented three instalments and two extra amounts. There were three reference dates for the first three payment claims as per contract (email dated 21 November 2002). The contract provided that the fee was $18,650.00 to be invoiced over three equal intervals commencing when construction began. If the proposed construction period was six weeks long, three payments of $6,216.00 each at week two, week four and week six were expected. The first three tax invoices were issued on a fortnightly basis (week 2, week 4 and week 6). The works commenced on 10 March 2003. The due dates or reference dates for the progress payments were 24 March 2003, 7 and 21 April 2003. In respect of the extra works, there were some carried out in April 2003. Thus for the extra payments pursuant to s 11, the relevant reference dated would be the end of the month, being 30 April 2003. In respect of the July works, the reference date is 31 July 2003. The passage set out in Isis has been complied with. This argument is hopeless.
22 Bell's second submission to the Magistrate was that s 13 of the Act provides that a payment claim must identify the construction work or the related goods or services to which the progress payment relates. According to Bell, payment claims 1, 3 and 4 identify the same work performed and it is not possible for the Kann in respect of each payment claim to identify what additional work if any was done by Bell in the periods referred to. Payment claims 3 and 4 are in respect of periods which overlap in contravention of s 13(5). Further Bell submitted that progress claim 4 is also defective because, contrary to s 8(2)(b) it does not identify a reference date which is the end of the month during which the relevant work was carried out. The Magistrate was correct to hold that these submissions were hopeless.
23 Finally Bell submitted that it is arguable that the services identified in progress claim 1 do not come within the definitions of "construction work" or "related goods and services" as those terms are defined by the Act. The Magistrate held that the work was described as provide design systems and this work fell within the definition of related goods and services. The Magistrate was entitled to do so. This work clearly falls within the definition of related goods and services. There is no error of law.