1.7 The Defendant failed to identify or mark the existence of the penetration.
Factual background
3 The defendant supplies to, and erects formwork for, various industrial and commercial construction sites. At the time of the offence it employed about 105 employees, 20 of whom were labourers, 80 of whom were formwork carpenters and 5 of whom worked in the office and administration. The defendant contracted with Leighton Contractors to supply, erect and remove formwork at the ABC Sydney premises. Mr Kos was employed there by the defendant as a formwork labourer. On 16 July 2001 he was in the process of dismantling and clearing falsework and formwork in goods lift shaft No 5. Formwork is apparently plywood used as a mould into which concrete is poured. Falsework is the support system for the formwork. It is used typically to provide a platform upon which employees work. Lift shafts consist of both formwork and falsework. The latter is erected to provide the work platform from which the employees erect the formwork for the walls of the lift shaft. The work platforms in the lift shafts contain a section in the middle which is open in order for a ladder to be used by the workers when travelling from floor to floor.
4 At around 2.00pm during the course of his work on 16 July 2001 Mr Kos lifted a piece of plywood measuring approximately 1800mm x 1200mm that was covering an opening or penetration approximately 600mm x 600mm. He fell some 5.4 metres through the penetration. As a result of the fall he sustained a comminuted fracture to his left forearm and injuries to his vertebrae.
5 On the day of the offence a WorkCover Inspector, Inspector Neill Bourne, attended the premises and made a number of observations which were included in a document entitled "Factual Inspection". He observed that the piece of plywood which was removed by Mr Kos was not fixed or otherwise secured to the first floor level inside the shaft, and, that it had white paint around the edges. He also observed that the distance between the first floor deck on which Mr Kos had been working and the decking below was approximately 5.4 metres.
Prosecutor's evidence
6 At the sentence proceedings, the prosecutor represented by Mr Cahill of counsel tendered an agreed statement of facts which annexed a series of five photographs taken by Inspector Bourne on 16 July 2001 shortly after the accident and the Inspector's Factual Inspection document.
7 According to the agreed statement of facts, on the day of the offence, in addition to the facts recited above, there was no fencing or other means of securing for the safety of persons working at a height in excess of 1.8 metres. Nor was there any marking or signage which warned of the existence of the penetration. There was no adequate inspection of the lift shaft before the task of dismantling and clearing the formwork commenced, and, no adequate risk assessment that might have identified the penetration or might have ensured the integrity of penetration covers in the lift shaft prior to the commencement of the work. The defendant did not ensure a safe system of work for the dismantling and clearing of the formwork in the lift shaft. The head contractor, Leighton Contractors, required Dolso Constructions Pty Ltd to produce a work method statement, when the work was considered high risk. Anthony Baroni, the defendant's supervisor and foreman at the premises apparently considered that the task being undertaken by Mr Kos was low risk. Either as a consequence of this view or for some other reason no specific work method statement was generated for the dismantling and clearing of the formwork in the lift shaft. Mr Kos received site specific induction training but he is from a non-English speaking background and claimed that he did not understand the training. He completed an induction questionnaire containing nine questions but answered five of them incorrectly. No follow up action was taken to provide Mr Kos with adequate training. Mr Kos held no relevant certification of competency in relation to the work he performed. There was no system in place to ensure the integrity of penetration covers prior to the dismantling and clearing of formwork. The defendant did not adequately warn Mr Kos of the dangers posed by penetrations on the premises.
8 The Court was advised by Mr Cahill that the defendant has no prior convictions.
Defendant's evidence
9 The defendant represented by Mr Pearce of counsel relied on an affidavit of Laurie John Dolso sworn on 4 March 2005 in the sentence proceeding. Mr Dolso is the director of the defendant and was also a director of Dolso Constructions Pty Ltd. In his affidavit Mr Dolso explained that following the collapse of the insurance company HIH and after failing to receive assurances that his business would be insured he arranged for the defendant to take over the employment of most of the workers employed by Dolso constructions. These arrangements were commenced on 21 March 2001.
10 According to the affidavit the defendant as a member of a group of companies, the Dolso Fastform Group, had an occupational health and safety policy. The policy is dated 17 September 1997. Part 2 of the policy is headed OH&E Risk Assessment of the Works and Safe Working Practices. This section deals with the erection of frames, formwork decks, formwork stripping and the associated potential hazards and precautions required to be taken. In relation to the erection of formdecks there is a requirement in relation to covering penetrations expressed in the following terms: