Background
11A document outlining the factual background leading up to the alleged offences was provided to the Court for its assistance. I have cross-referenced the information set out in the document to the prosecution's brief of evidence and am satisfied that it accurately reproduces and otherwise conforms to the evidence contained in the brief. The document has been particularly helpful in providing background material and in clarifying the roles of the various entities involved in the Lane Cove Tunnel project (LCT project). Part of the material in the document (referred to as the Statement of Facts) is extracted below:
2. At all material times Pells Sullivan Meynink Pty Ltd [ACN 061 447 621] ("PSM") was a corporation whose registered office is situated at Blackwood Clarke, Suite 502A, Level 5, 282 Victoria Avenue, Chatswood, in the State of New South Wales ("the defendant") ( tab D20 ).
3. At all material times the defendant was an employer ( tab S24 Clark at Q20; tab S23 Bertuzzi at Q20; tab S26 Gilchrist at Q20). Philip Clark was employed by PSM as the Senior Rock Mechanic Engineer ( tab S26 Clark at Q12-Q14), Daryl Gilchrist was employed as a senior geologist, Robert Bertuzzi was employed as a Principal Engineer ...
4. The Roads and Traffic Authority ("RTA") engaged the Lane Cove Tunnel Company Pty Ltd, now known as Connector Motorways Pty Ltd, to design, construct, maintain and operate the Lane Cove Tunnel (LCT). The LCT and associated works were being constructed to link the M2 Motorway with the Gore Hill Freeway ( tab D1 ).
5. The Lane Cove Tunnel Company Pty Ltd contracted Thiess John Holland Joint Venture to design and construct the tunnel and associated works. The construction of the LCT commenced in 2004 ( tab D1 ).
6. The co signatories of the Thiess John Holland Joint Venture ("TJH") were Thiess Pty Ltd and John Holland Pty Ltd ( tab D1 ).
7. TJH engaged Parsons Brinckerhoff Australia Pty Ltd ("PB"), design consultants to design the project ( tab D2 ).
8. PSM, a company involved in design consultancy and supply of construction phase services such as geological inspection/mapping and monitoring, provided geologists and geotechnical staff to assist both PB in the design stage and TJH and PB in the construction phase. Staff worked with these two organisations at different stages of the project ( tab D3, D6, D7, D8 ).
9. In October 2004, TJH engaged PSM to provide a Senior Rock Mechanics Engineer and associated services (the "PSM Rock Mechanics Engineer Consultancy Agreement").
10. As at October 2004 and at all times subsequently, PSM was a specialist geological consultant with world renowned experience in geological conditions in the Sydney basin.
11. Under the PSM Rock Mechanics Engineer Consultancy Agreement, PSM was to provide the services of a specialist Rock Mechanics Engineer to overview the construction of the LCT and associated works with regard to the following points:
Interpret data received from tunnel and surface mounted ground monitoring instrumentation.
Analyse tunnel mapping by a geologist and compare that mapping to conditions described in design reports to ensure that support regimes nominated were appropriate and efficient.
Liaise with the Project designers to facilitate changes to the design to tailor it to conditions experienced based on the results of instrumentation and performance of previously installed support.
Liaise with construction engineers and supervisors regarding the design requirements.
Manage TJH's monitoring activities (specified by others) connected with the Project.
Co-ordinate geologists and engineers seconded to the monitoring team by PB, Coffey Geosciences and PSM.
Ensure that adequate records of monitoring activities were kept in an agreed format for use and consultation by TJH staff and designers.
Co-ordinate the TJH survey teams inputs into the monitoring activities.
Manage and co-ordinate the installation of monitoring equipment whether installed by TJH or subcontractors.
Provide geotechnical technicians to read all instruments installed as part of the construction of the works.
12. Under the PSM Rocks Mechanics Engineer Consultancy Agreement, PSM was obliged to exercise all the skill, care and diligence of a professional consultant experienced in providing the services and was obliged to carry out all responsibility in a thorough, skilful and professional manner ( tab D6 & D7 ).
13. URS Australia Pty Ltd ("URS") were appointed by the RTA as the Independent Verifier for the project.
14. In the period 27 October 2005 to 2 November 2005 the following people worked in the MCAA including in its intersection with MC5B: Laurence Grace ( tab S3 at Q60), Glynn Baker ( tab S1 ), Dave Shaw ( tab S8 at Q40-41), Stephen Swan ( tab S10 at Q36-37), John Labruyere ( tab S5 at Q33-37), Regan Findlay ( tab S2 at Q30-42), Craig Lightfoot ( tab S6 at Q51), Bryan Greenfield ( tab S4 at Q41-48), Jason Tyler ( tab S13 at Q29), Hamish Studholme ( tab S9 at Q31), Noel Makene ( tab S7 at Q30-37), Mark Watson ( tab S11 at Q29-36), Christopher McKervey ( tab S12 at Q32-34), John Wilson ( tab S16 at Q45), Sam Jones ( tab S14 at Q66), Phil Lloyd ( tab S20 at Q40, Q60).
15. In the period 27 October 2005 to 2 November 2005 the following people lived in the home units located at 11-13 Longueville Road, Lane Cove which was above the area where the incident occurred: Anna Sayyadi ( tab S30 ), Laura McWhinnie ( tab S31 ), Robert Colquhoun ( tab S29 ) and Carlos Baccan ( tab S28 ).
Incident
16. On Wednesday, 2 November 2005 TJH employees were carrying out excavation works at the junction of two tunnels, the Marden Street ventilation tunnel and the Pacific Highway exit ramp. At approximately 1:40am a large section of the tunnel roof collapsed in the area underneath the Longueville Road off-ramp to the Pacific Highway at Lane Cove. The employees working within the tunnel evacuated the tunnel as the section of tunnel roof collapsed narrowly escaping injury ( tab S5 John Labruyere at Q33-36; tab S4 Craig Greenfield at Q41-48; tab S7 Noel Makene at Q30-37).
17. The collapse led to a significant ground subsidence that affected the stability of a block of home units situated at 11-13 Longueville Road, Lane Cove. There were also concerns relating to a retaining wall that supported the Pacific Highway off-ramp. The incident caused the off-ramp and Longueville Road to be closed and residents of the home units to be evacuated (see the residents' statements at tab S28 to S31 ).
The Occurrence
18. The incident occurred at the junction of two tunnels: the Marden Street ventilation tunnel (referred to as MC5B) and the Pacific Highway exit ramp excavation (referred to as MCAA) (see, for example, tab S5 Labruyere at Q33). Over the previous weeks MC5B had been advancing towards the line of MCAA and reached the intersection point with MCAA around 17 October 2005 ( tab D10 & tab D12 ). Once this point was reached MCAA was excavated first to the east (referred to as the "up" or "upper" drive), and then to the west (referred to as the "back", "lower" or "down" drive). Work was continuing on this western excavation at the time of the collapse ( tab D12 ).
19. On the evening prior to the incident, 1 November 2005, the night tunnelling crew ("crew B") commenced their shift at 1900 hrs. The crew was comprised of four workers: John Labruyere, the leading hand, Noel Makene, the road header operator, Bryan Greenfield, the loader operator and Mark Watson, the driver of the dump truck. The crew were all employed by TJH (see Tab S4 Greenfield, tab S5 Labruyere, tab S7 Makene and tab S11 Watson).
20. The crew on the preceding day shift ("crew A"), according to shift reports, had installed and grouted five rock bolts on the MCAA down left, installed but not grouted five rock bolts on the MCAA down left, installed and grouted 2 rock bolts on the MCAA down right, and had installed some shotcrete (see tab D12 ). The shift report for this shift does not indicate what chainage the excavation of the lower drive of MCAA was at the conclusion of the day shift. Ground Support Classification and Ground support determination reports indicate that the down drive of the MCAA was at chainage 467 when inspected near the start of the day shift (see tab D10 ). Crew A consisted of Craig Lightfoot, Steve Swain, Glynn Barker and Lawrence Grace.
21. Crew B on the night shift on 1 November 2005/2 November 2005 had cut approximately one metre into the left side of MCAA down drive and had commenced loading out and "mucking out" spillage from the front of the road header when, at about 1:40 am, the rock collapse commenced. Mr Labruyere, described what happened:
I was standing on top of the road header next to the operators cab talking to the operator ... We were just doing a bit of mucking out waiting for the shotcreters, ...and I noticed the whole roof, from the centre to right side of MCAA coming down as a whole mass and back towards us, and we were out of there. I can't remember from that point, when we turned around there was stuff falling on our lid and from that point I have a gap in my memory until I reached the truck. One comment from the truck driver was he heard a banging and crashing and got out of his cab, and saw the road header cab was almost completely covered ( tab S5 Labruyere, Q36).
22. Once the fall commenced, it increased rapidly when it reached an area where a dolerite dyke was situated. The crew, under instructions from the leading hand, retreated from the area, back to the entrance of MC5B, which was then secured (taped off).
23. The acting shift boss, Craig Bennett, who was operating with another crew in tunnel MC1A East, was then notified of the incident and travelled to the scene of the collapse with the leading hand of crew B. After observing that the area was still unstable, the evacuation alarm was activated and all tunnels in the Marden Street area were evacuated (see tab S17 Bennett).
24. At approximately 2:00am, a hole was observed off the exit ramp in front of the "Kerslake" apartment block (11-13 Longueville Road). It also appeared that the subsidence had fractured a water pipe, causing a substantial inrush of water into the collapse.
25. Once the tunnels were evacuated and all workers accounted for, management representatives, geologists and engineers were progressively contacted and requested to attend the site. Subsequently, inspections were carried out both underground at the scene of the collapse and on the surface. At approximately 2.30am the hole was observed to be about 4 or 5m diameter on the surface and had undermined approximately 1-2m under the road.
26. Staff considered that the collapsed debris required strengthening before any surface activity could occur. It was proposed to place large diameter hammered rock to form a bridging layer to lessen any pressure on the pile of collapsed debris. However, they needed to remove an electrical sub-station and a dust scrubber from the area before the rock could be placed up against the debris pile delayed this action. This strategy was discarded as observation of the hole at approximately 5:30am revealed the hole had expanded in size. At about 6:00am loud noises were heard to be coming from the hole and it was observed that a substantial secondary collapse had occurred under the existing Longueville Rd exit ramp and a number of piles with the collapsed area of the tunnel were observed to have been undermined by the collapse. The hole at that stage was observed to be around 8-9m diameter.
27. It was at this stage that the decision was made by TJH to commence filling the hole with concrete to mitigate any further collapse. Concrete pumping commenced with one pump at approximately 8am. Two further concrete pumps arrived shortly after and also commenced pouring, the initial pour ceasing at around 3:00pm, having reached a height of 2 metres above the top of the pile. This amount of concrete had been determined as the maximum that could be placed initially without putting pressure on the exit ramp retaining wall. Longueville Road had been closed to traffic at approximately 6:45am.
28. After waiting for the first lot of concrete to cure a second pour was commenced at approximately 9:30pm on 2 November 2005 and completed at around 12:30am the following morning. The third and final concrete pour, which was to reach the level of the top of the retaining wall, was commenced at 6:30am on 3 November 2005 and completed mid-morning. Over the next couple of days, grout was pumped into identified void areas around the collapse to complete the stabilisation works. In total, approximately 2750 cubic metres of concrete and grout was pumped into the collapsed area (see tab D21 and tab D14 Golder report pages 19-22 for further detail of the incident).
Geological Conditions at the Site
Low Strength Shale
29. The bedrock at the site consisted of Ashfield Shale. In the area of the MC5B/MCAA intersection, the bedrock in the crown of the tunnel had been documented by the Project Geologist as Ground Class LCTG7 and LCTG8, that is, shale of low to very low strength (see tab D10 , GSD dated 1 November 2005, see tab S20 Lloyd at Q37). Previous investigations and assessments in the area had also indicated that the strength of the shale further decreased closer to the ground surface, in turn passing up to residual soil and/or some overlying fill. This material thus comprised a low strength sequence, from the crown of the tunnel up to the surface infrastructure (see tab D15 Kotze report at page 11).
The Presence of the Dyke
30. The MC5B/MCAA intersection was transected in a southeast to northwest direction by an igneous (doleritic) dyke. The dyke comprised a subvertical, through-going intrusion, generally ranging in true thickness from between 600 and 700mm. Dyke intersections had been encountered previously in MC5B as well as in the main line tunnels and the occurrence of the dyke in or near the MC5B/MCAA intersection was anticipated by site personnel ( tab S26 Gilchrist at Q112-116, tab D15 Kotze report at page 11).
31. In previous encounters the dyke was predominantly orange in colour, highly to extremely weathered and of low to very low strength. These conditions are understood to have prevailed through the MC5B/MCAA intersection. The dyke comprises a persistent low strength feature, both laterally and vertically, and its side boundaries constitute low strength defect planes (see tab D15 Kotze report at page 11).
Rock Mass Joints and Faults
32. Mapping documentation completed by the Project Geologist confirmed that the rock mass into which the MC5B/MCAA intersection had been excavated was relatively highly fractured. The shale in this area was characterised by structures comprising bedding plane partings, joint plane defects and localised faults (see tab D15 Kotze report at page 11).
33. Bedding plane partings are subhorizontal to locally dipping defects of variable vertical spacing. They are intersected by inclined to subvertical joint plane fractures. Mapping confirmed the presence of three (3) intersecting joint plane sets, one of which was parallel to the dyke, whilst the other two were both normal and more acutely angled to it. These subvertical fracture sets are locally continuous upwards and spaced as closely as 200 mm apart. They effectively divide the rock mass into a series of vertical columns, which can in turn be subdivided into blocks by intersecting with sub horizontal bedding planes (see tab D15 Kotze report at page 11 & 12).
34. The rock mass in the MC5B/MCAA intersection was further fractured by localised inclined fault structures that were mapped by the Project Geologist. In combination with the bedding plan partings and joint plane fractures described above, the localised faults further fragmented the rock mass into variously shaped and sized blocks and wedges (see tab D15 Kotze report at page 12).
Large Span Width of Tunnel Intersection
35. Both the ventilation tunnel (MC5B) and the Pacific Highway Exit Ramp (MCAA) were "Two Lane" tunnels within the Lane Cove Tunnel Project, with spans or widths of approximately 9 metres. At the intersection of the two tunnels however, the width of the underground opening was locally greater. The diagonal width of the MC5B/MCAA intersection was up to 22m (see tab D15 Kotze report at page 7). This is a relatively large effective span width to support, particularly when the roof strata were comprised of low strength and fractured shale. Furthermore, the above described weathered and low strength dyke passed through the intersection as a zone of weakness, aligned closely with the line of maximum span (see tab D15 Kotze report at page 12).
Tunnel Roof Support Installations
36. The roof support adopted at any tunnel location on the project was dependant on the assessed "Ground Classification", which in turn related to a "Ground Support Determination". As mentioned above the assessed ground classes in the area of the MC5B/MCAA intersection were LCTG7, LCTG7/G8 and LCTG8. Early project documents relate a ground class of LCTG7 (for a 2 lane/9m tunnel width) to a support system comprising an array of 3m long rock bolts on a 1250mm spacing both ways, with an initial 50mm lining of shotcrete and a second/final 75mm lining of shotcrete. Ground class LCTG8 required Steel Sets or Lattice Girders, with an initial 75mm lining of shotcrete and a final 200 mm lining (see tab D15 Kotze report at page 7 & 8).
37. The amount of rock bolts to be installed and the thickness of the shotcrete varies depending on the ground support determination ("GSD") (based on the ground classification determined by the geologist) in the design documents. If the "as found" conditions vary significantly from what was expected, a "Request Further Information" form was referred back to the tunnel designers who would consider the new information and, if required, issue a revised set of drawings. Any design revisions would be submitted to the independent verifier for approval.
38. As the project advanced and poor ground conditions associated with low strength fractured shale and dyke intersections were encountered, the LCTG7 ground support system was upgraded to 4m long rock bolts on 1000mm x 1250mm spacings with two (2) cyclic 100mm applications of shotcrete (Mar VII Support Type). The original LCTG8 requirement for Steel Sets or Lattice Girders in poorer ground conditions however, was also modified, to a less conservative rock bolt and shotcrete application (see tab D15 Kotze report page 8).
39. When the doleritic dyke was encountered in the MC5B drive in September 2005, geological predictions were that it would be encountered again in the vicinity of the intersection of MC5B and MCAA and a revised drawing for the intersection was issued. This new design was not verified by URS prior to it being adopted for construction ( tab S26 Gilchrist at Q76).
40. In the area of the MC5B/MCAA intersection, a modified Mar VII 4m rock bolt and shotcrete support type was employed, with a supplementary 5m long rock bolt pattern in the centre of the intersection including the southern and eastern transitions. Shotcrete was to be applied in two layers of 100mm. One layer prior to bolting and the second layer to be sprayed after the bolts had been installed. The shotcrete was to form a complete arch from floor to floor ( tab S26 Gilchrist at Q69-70) (see tab D15 Kotze report page 8).
41. Beyond the transition zones, the modified Mar VII support type only was installed, that is, without the supplementary 5m rock bolts. It is understood that the MCAA up drive should have been installed with 4m long rock bolts on a 1m x 1m grid pattern, with two shotcrete applications comprising a 125mm thickness. It is understood that the MCAA down drive had been partially installed (on the northern side) with 4 m long rock bolts on a 1m x 1m grid pattern, with an initial application of shotcrete of unknown thickness (see tab D15 Kotze report page 8).
42. Instructions and information about the method of excavation work to be carried out on the LCT project were provided to the crew by induction into Job Safety and Environment Analyses ("JSEA"). These JSEA included procedures for road header excavation, loader operation, dump truck operation, rock bolting, ventilation and the use of compressed air equipment. Directions on the sequence of construction in particular areas were issued in the form of site instructions that were communicated to the crews by the shift boss and/or leading hand. The site instructions were then usually affixed in the cabin of the road header.
43. The site instruction issued for the construction sequence in the intersection of MC5B and MCAA required the crew to cut a prescribed minimum distance (about 1-1.5m) and stop. The road header would then be pulled back and the newly excavated area shotcreted. The crew would then leave the shotcrete for approximately an hour for it to cure, and then install an amount of rock bolts as determined by the design documents. This process involves drilling a hole, inserting and tensioning the bolts and finally pumping in grout to complete the installation. The support was to be installed to the full face of the advancing tunnel. Full implementation of the design was considered essential for it to be effective. The shotcrete role is significantly greater given the poor geological conditions as under those conditions the shotcrete can be expected to be directly loaded by the shale and is required to perform as a structural shell. The sequence of application of the shotcrete and the completion of shotcrete in accordance with the design becomes of more significance than in more favourable ground conditions (see tab D9 and tab D15 Kotze report page 18).
Ground support determination and monitoring
44. Although this support regime was generally considered to be robust by the design team, it was considered necessary to draw the constructor's attention to the need to have a geotechnical engineer monitor the "as found" ground conditions as construction progressed as the design may need to be reviewed or adapted. The geotechnical engineer and/or the geologist was also to direct the installation of spot bolts in the tunnel walls should that be considered necessary.
45. The system of ground mapping and ground support determination is defined in TJH Work Method Statement Geotechnical Mapping and Ground Support Determination No TJH-WMS-TU-CON-016 ( tab D5 ). Essentially the procedure for ground mapping and support determination was that a Geologist, Daryl Gilchrist (PSM) would attend, inspect and map the face of tunnels under construction, and produced a Ground Support Determination Sheet (GSD) ( tab S26 Gilchrist at Q132-137). On occasion and if needed he would consult with the Geotechnical Engineer, Phil Lloyd (PB's Design Representative) who often attended the face, on the ground support determination (GSD's) made. Daryl Gilchrist would then provide the GSD to the TJH Senior Engineer, Sam Jones for confirmation. Sam Jones would then distribute the GSD information and recommendations to the superintendent and shift bosses for implementation. The responsibility for ensuring the procedure was carried out in accordance with the guidelines was delegated down the line by the Construction Manager Tunnels (Steve Wille) to the Project Manager (Duncan Shires) down to the Senior Project Engineer (Sam Jones) and Superintendent (John Wilson).