(2) Others at workplace An employer must ensure that people (other than the employees of the employer) are not exposed to risks to their health or safety arising from the conduct of the employer's undertaking while they are at the employer's place of work.
4 The allegation with respect to GPCC is that it failed to provide and maintain a system of work, with respect to the installation of pre-caste concrete panels, which was safe and without risks to the health, safety and welfare of its employees and it failed to ensure that adequate fall prevention measures were taken to prevent the employee Mr Roth from being at risk of falling from the leading edge of level 9 of the building under construction.
5 The particulars of the offence with which JML was charged is that it failed to ensure that a system of work with respect to the installation of pre-caste concrete panels at the site was provided and maintained which was safe and without risks to health, safety and welfare of persons who were not its employees and it failed to ensure that adequate fall prevention measures were taken so as to prevent persons not its employees from being at risk of falling from the leading edge of level 9 of that building.
6 GPCC had entered a plea of guilty from an early stage in the proceedings. JML entered a plea of guilty just prior to the time fixed for the hearing of those proceedings. This judgment, accordingly, deals only with the question of penalty.
7 Set out below is the agreed statement of facts tendered in the proceedings against JML. Those facts in all material respects that pertain to the circumstances surrounding the events that occurred on 20 April 2004 were common also to and became evidence in the proceedings against GPCC.
"1. The Prosecutor is and was at all material times:
(a) an Inspector duly appointed under Division 4 of Part 3 of the Occupational Health and Safety Act 1983 (NSW) ("the 1983 Act");
(b) taken to be appointed as an Inspector under the Occupational Health and Safety Act 2000 ("the 2000 Act") by virtue of Clause 11 of Schedule 3 to the 2000 Act; and
(c) empowered under s.106 of the 2000 Act, as extended by Clause 13 of Schedule 3 to that Act to institute proceedings in the within matter.
2. JML Group Pty Ltd (ACN: 003 969 622) ("the Defendant"), is and, at all material times, was a company duly incorporated with a registered office located at Corner Creek and Minmi Roads, Wallsend 2287 in the State of New South Wales.
3. At all material times, the Defendant was the principal contractor with respect to construction of a multi-storey apartment building at 489 Hunter Street, Newcastle in the State of New South Wales ("the site").
4. The building under construction at the site consisted of concrete floors with pre-cast concrete panels forming the exterior "curtain" walls of the building.
5. At all material times the Defendant's undertaking included the installation of the pre-cast concrete wall panels.
6. At all material times, the site was the Defendant's place of work.
7. At all material times, the Defendant was an employer.
8. At all material times, GPCC Pty Ltd (ACN 094 719 785) ("GPCC") was engaged by the Defendant on a subcontract basis, to install pre-cast concrete panels at the site.
9. At all material times, GPCC employed Anthony Roth ("Roth") as a leading hand, and Timothy Hyeronimus ("Hyeronimus") as a labourer, to work at the site.
10. Roth had been working as a construction team co-ordinator organising semi-trailers, cranes, men, erection of panels and "post direction work" for the previous 5 years with Girotto Precast. For 13 years prior to that, he had worked up from a labourer to a supervisor with another company. During these periods Roth had worked principally on single storey warehouse style constructions.
11. At all material times Roth was certified as a rigger (basic and intermediate) and as a crane driver.
12. Roth commenced employment with GPCC on 19 April 2004 and commenced work at the site on the day.
13. Prior to 19 April 2004, Hyeronimous' work involved mainly caulking, grouting and sometimes assisting in the installing of concrete panels. Prior to commencing work at the site, Hyeronimous had not worked on high rise.
14. On 19 April 2004, the GPCC workers were provided with safety harnesses, the eyelets, the block and lanyards to hook onto .
15. On 20 April 2004 ("the incident date"), Roth and Hyeronimus were undertaking tasks relating to the installation of pre-cast concrete panels on the south west corner level 9 of the building at the site.
16. GPCC 's installation procedure required Roth and Hyeronimus to work in close proximity to the leading edge of the building as the pre-cast concrete wall panels were fitted to the outside of the building, sitting one on top of the other.
17. First, the pre-cast concrete wall panels were to be lifted by a crane to the level of the building to which they were to be fitted. Once at the level of the building to which it was to be attached, each panel was to be located, manually, by Roth and Hyeronimus.
18. Secondly, the pre-cast concrete wall panels were cast with holes in the base and in the top of each panel so that the panels could be secured with threaded dowel. Once each panel was manually guided to a point above the position in which it was to be fitted, the holes in the top of the existing panel and the base of the panel were grouted and a threaded dowel was screwed into each of the holes in the base of the panel. Roth and Hyeronimus then manually guided the panel so that the threaded dowel(s) located into the existing pre-cast panel(s) below the panel being fitted.
19. Before a panel could be craned to the level and guided into position for fixing, GPCC's installation procedure called for the removal of perimeter fencing on the leading edge of the building where the panel was to be fitted.
20. On 19 April 2004, the day prior to the incident date, Roth removed the perimeter fencing from across the back and the south west corner of level 9 of the building in order to prepare for the installation of the pre-cast concrete panels.
21. However, no barrier, such as scaffolding or other edge protection was installed prior to the removal of the perimeter fencing; nor were any warning signs installed to alert workers to the risk of falling from the leading edge of level 9 of the building.
22. The fall from the leading edge on level 9 of the building to the ground below was approximately twenty (20) metres.
23. On 19 April 2004 Inspector Sandall attended at the site. Whilst present at the site on 19 April 2004, Inspector Sandall met briefly with JML site staff and GPCC employees on the stairs between level 8 and level 9. In the course of that meeting Inspector Sandall informed Roth and Hyeronimus and JML site staff that fall protection was to be maintained at all times, including the wearing of safety harnesses, and that barricading was to be put in place to stop other workers coming into the GPCC work area.
24. On 20 April 2004 barricading was put in place on level 9 of the site to prevent other workers from entering the area in which Roth and Hyeronimous were installing pre-cast panels.
25. At approximately 3.15pm on the incident date, Roth and Hyeronimus were involved in installing a pre-cast concrete panel to the leading edge on the south western side of level 9 of the building. Roth was working in close proximity to that leading edge of the building on that side of the building fitting the threaded dowel and manually locating a panel prior to it being lowered into place. Roth was not wearing a safety harness whilst performing this task in circumstances where there were no other methods of fall protection in place.
26. When interviewed after the incident both Roth and Hyeronimus stated that on 20 April 2004 they worked 'all day' with their harnesses on until the defendant's site foreman, Zaim Arabelovic, left level 9. Both Roth and Hyeronimus also stated when interviewed after the incident that Roth removed his harness, whilst positioning a pre-cast panel, just shortly before Inspector Sandall arrived on level 9 at about 3.15pm.
27. When interviewed after the event, Zaim Arabelovic stated that:
"Well every time I was up there, I was up there basically all day, one of us representatives were there ensuring that they maintained the harness on and the site, the exclusion zone was maintained and no other staff was up there….I can't explain why he took it (the harness) off. He had it on when I left to go downstairs and by the time I got back with Gary (Inspector Sandall) he had it off."
28. Prior to and as at the date of the incident, GPCC had in place a Safe Work Method Statement ("SWMS") for the Installation of Precast Panels. Annexed hereto and marked "A" is a copy of this SWMS.
29. After the incident, GPCC was required to revise their SWMS and to provide training to Roth and Hyeronimus in accordance with the revised SWMS. Annexed hereto and marked "B" is a copy of the revised SWMS.
30. The Defendant's Project Safety Plan, dated 12 December 2003, required GPCC to prepare and submit a work method statement to the Defendant's Project Manager for review prior to work on the installation of the pre-cast panels commenced at the site. Annexed hereto and marked with the letter "C" is a copy of the Defendant's Project Safety Plan for the site.
31. Further, the Defendant's Project Safety Plan included "Guidelines to Producing a Work Method Statement" against which SWMS, including GPCC's initial SMWS, were to be assessed. The initial SWMS did not comply with the Defendant's guidelines with respect to the production of safe work method statements for use on the Defendant's sites in that the initial safe work method statement for the installation of the pre-cast wall panels did not:-
· note the name, qualifications and experience of the supervisor required to carry out supervision of the task;
· note specific training required by personnel carrying out the task;
· detail the methods to be used to isolate the task.
32. Further, after the subject incident the Defendant put in place a "Work Method Statement - Amendment" with respect to its oversight of the installation of the pre-cast concrete wall panels, together with a "Precast Panel Erection Checklist (DRAFT)". Attached marked with the letters "D" and "E", respectively, are copies of the Work Method Statement - Amendment for Concrete Precast Panel Erector Contractor: GPCC and the draft "Precast Panel Erection Checklist".
33. After the incident, the Defendant had in place a system of supervision that required one of its supervisors to be present whenever GPCC was actually undertaking the installation of pre-cast wall panels.
34. The Defendant, being an employer at 489 Hunter Street, Newcastle in the State of New South Wales on 20 April 2004, DID FAIL, contrary to Section 8(2) of the Occupational Health & Safety Act 2000 (NSW) to ensure that people (other than employees of the Defendant), and in particular Anthony Roth, were not exposed to risks to their health or safety arising from the conduct of the Defendant's undertaking while they were at the Defendant's place of work, in that the Defendant:
(a) failed to ensure that a system of work with respect to the installation of pre-cast concrete panels at the site was provided and maintained which was safe and without risks to the health, safety and welfare of its non-employees;
(b) failed to ensure that adequate fall prevention measures were taken so as to prevent its non-employees from being at risk of falling from the leading edge of level 9 of the building under construction at the site."
8 A further agreed statement of facts was also tendered in the proceedings against JML and it is set out below:
"1. When interviewed by Inspector Dall on 13 May, 2004, Mr Roth gave the following answers to the following questions:
Q260. Dall: Okay however you by your own admission had elected to take the harness off?
A: That's right yes.
Q261. Dall: Okay what then transpired?
A: This is when the Workcover guy came over to me and asked me what I was doing and why I was doing it in this manner and I just said I felt safer doing it this way without the lanyard getting caught on starter bars and things on the ground, it is a lot easier to trip when you come to a sudden halt or you lose control of the panel and it hits another panel. I felt safer."
9 In addition to the agreed statement of facts in each matter there was tendered into evidence on behalf of the defendant JML affidavits of Michael Thomas Lavis and Zaim Arabelovic. Mr Arabelovic was cross-examined on his affidavit. The evidence of Mr Arabelovic became evidence in the proceedings against GPCC. Certain of the documentation exhibited to the affidavit of Mr Lavis became evidence in the proceedings against GPCC.
10 For completeness, I set out hereunder the agreed statement of facts tendered in connection with the proceedings against GPCC, and it will be seen that there is a substantial body of overlap with the JML proceedings.
"1. At all material times the Prosecutor was:
(a) an Inspector duly appointed under Division 4 of Part 3 of the Occupational Health and Safety Act 1983 (NSW) ("the 1983 Act");
(b) taken to be appointed as an Inspector under the Occupational Health and Safety Act 2000 ("the 2000 Act") by virtue of Clause 11 of Schedule 3 to the 2000 Act; and
(c) empowered under s.106 of the 2000 Act, as extended by Clause 13 of Schedule 3 to that Act to institute proceedings in the within matter.
2. At all material times, GPCC Pty Ltd (ACN: 094 719 785) ("the Defendant"), was a company duly incorporated with a registered office located at Suite 1, 614 Hawthorne Road, Brighton East 3187 in the State of Victoria.
3. At all material times, JML Group Pty Ltd (ACN: 003 969 622) ("JML") was the principal contractor with respect to construction of a multi-storey apartment building at 489 Hunter Street, Newcastle in the State of New South Wales ("the site").
4. The building under construction at the site consisted of concrete floors with pre-cast concrete panels forming the exterior walls of the building.
5. At all material times JML's undertaking included the installation of the pre-cast concrete wall panels.
6. At all material times, the Defendant was engaged by JML, on a subcontract basis, to install pre-cast concrete panels at the site.
7. At all material times, the Defendant was an employer.
8. At all material times, the Defendant employed Anthony Roth ("Roth") as a leading hand, and Timothy Hyeronimus ("Hyeronimus") as a labourer, to work at the site.
9. On 20 April 2004 ("the incident date"), Roth and Hyeronimus were undertaking tasks relating to the installation of pre-cast concrete panels on the south west corner level 9 of the building at the site.
10. The Defendant's installation procedure required Roth and Hyeronimus to work in close proximity to the leading edge of the building as the pre-cast concrete wall panels fitted to the outside of the building, sitting one on top of the other.
11. First, the pre-cast concrete wall panels were to be lifted by crane to the level of the building to which they were to be fitted. Once at the level of the building to which it was to be attached, each panel was to be located, manually, by Roth and Hyeronimus.
12. Secondly, the pre-cast concrete wall panels were cast with holes in the base and in the top of each panel so that the panels could be secured with threaded dowel. Once each panel was manually guided to a point above the position in which it was to be fitted, the holes in the top of the existing panel and the base of the panel were grouted and a threaded dowel was screwed into each of the holes in the base of the panel. Roth and Hyeronimus then manually guided the panel so that the threaded dowel(s) located into the existing pre-cast panel(s) below the panel being fitted.
13. Before a panel could be craned to the level and guided into position for fixing, the Defendant's installation procedure called for the removal of perimeter fencing on the leading edge of the building where the panel was to be fitted.
14. On 19 April 2004, the day prior to the incident date, Roth removed the perimeter fencing in the south west corner of level 9 of the building in order to prepare for the installation of the pre-cast concrete panels.
15. However, no barrier, such as scaffolding or other edge protection was installed prior to the removal of the perimeter fencing; nor were any warning signs installed to alert workers to the risk of falling from the leading edge of level 9 of the building.
16. The fall from the leading edge on level 9 of the building to the ground below was approximately twenty (20) metres.
17. At approximately 3.15pm on the incident date, Roth and Hyeronimus were involved in installing a pre-cast concrete panel to the leading edge on the southern side of level 9 of the building. Roth was working in close proximity to that leading edge of the building on that side of the building fitting the threaded dowell and manually locating a panel prior to it being lowered into place. Roth was not wearing a safety harness whilst performing this task in circumstances where there were no other methods of fall protection in place.
18. Prior to and as at the date of the incident, the Defendant had in place a Safe Work Method Statement ("SWMS"), which failed to adequately address the risks associated with working at heights.
19. After the incident, the Defendant revised their SWMS and provided training to Roth and Hyeronimus in accordance with the revised SWMS.
20. It is alleged that the Defendant, on 20 April 2004, being an employer at the site, did fail, contrary to s.8(1) of the 2000 Act, to ensure the health, safety and welfare at work of all of the employees of the Defendant employer, and in particular Anthony Roth, in that the Defendant:
(a) failed to provide and maintain a system of work with respect to the installation of pre-cast concrete panels at the site which was safe and without risks to the health, safety and welfare of its employees;
(b) failed to ensure that adequate fall prevention measures were taken so as to prevent its employees from being at risk of falling from the leading edge of level 9 of the building under construction at the site."
11 A further agreed statement of facts was also tendered in the proceedings against GPCC and it is set out below:
"1. When interviewed by Inspector Dall on 13 May, 2004, Mr Roth gave the following answers to the following questions:
Q260. Dall: Okay however you by your own admission had elected to take the harness off?
A: That's right yes.
Q261. Dall: Okay what then transpired?
A: This is when the Workcover guy came over to me and asked me what I was doing and why I was doing it in this manner and I just said I felt safer doing it this way without the lanyard getting caught on starter bars and things on the ground, it is a lot easier to trip when you come to a sudden halt or you lose control of the panel and it hits another panel. I felt safer.
2. Roth had been working as a construction team co-ordinator organising semi-trailers, cranes, men, erection of panels and "post direction work" for the previous 5 years with Girotto Precast. For 13 years prior to that, he had worked up from a labourer to a supervisor with another company. During these periods Roth had worked principally on single storey warehouse style constructions.
3. At all material times Roth was certified as a rigger (basic and intermediate) and as a crane driver.
4. Roth commenced employment with GPCC on 19 April 2004 and commenced work at the site on the day.
5. Prior to 19 April 2004, Hyeronimous' work involved mainly caulking, grouting and sometimes assisting in the installing of concrete panels. Prior to commencing work at the site, Hyeronimous had not worked on high rise.
6. On 19 April 2004, the GPCC workers were provided with safety harnesses, the eyelets, the block and lanyards to hook onto .
7. On 19 April 2004 Inspector Sandall attended at the site. Whilst present at the site on 19 April 2004, Inspector Sandall met briefly with JML site staff and GPCC employees on the stairs between level 8 and level 9. In the course of that meeting Inspector Sandall informed Roth and Hyeronimus and JML site staff that fall protection was to be maintained at all times, including the wearing of safety harnesses, and that barricading was to be put in place to stop other workers coming into the GPCC work area.
8. When interviewed after the incident both Roth and Hyeronimus stated that on 20 April 2004 they worked 'all day' with their harnesses on until the defendant's site foreman, Zaim Arabelovic, left level 9. Both Roth and Hyeronimus also stated when interviewed after the incident that Roth removed his harness, whilst positioning a pre-cast panel, just shortly before Inspector Sandall arrived on level 9 at about 3.15pm.
9. When interviewed after the event, Zaim Arabelovic stated that:
'Well every time I was up there, I was up there basically all day, one of us representatives were there ensuring that they maintained the harness on and the site, the exclusion zone was maintained and no other staff was up there….I can't explain why he took it (the harness) off. He had it on when I left to go downstairs and by the time I got back with Gary (Inspector Sandall) he had it off.'"
12 Prior to the incident occurring, JML as head contractor created a "project safety plan" which dealt, among other things, with occupational health and safety measures to be taken at the site. That document required sub-contractors such as GPCC to prepare "Work Method Statements" which were to be submitted to the JML project manager for review prior to commencement. Those documents were intended to be reviewed regularly by sub-contractors. Furthermore, the project safety plan required the JML foreman to complete a sub-contractor safety performance data record on sub-contractors that the foreman believed "need to improve their safety performance" which was to be forwarded to the project manager.
13 JML documentation included guidelines for the production of work method statements by sub-contractors which sought specificity as to work areas, compliance with safety requirements, provision of personal protection equipment, the training and information to be afforded to persons carrying out the work, step by step procedures and the like.
14 GPCC created an "OHS site management plan" which incorporated a safety policy signed by directors on 1 July 2003. There was included a safety analysis which covered a range of activities. It is possible to read this documentation in such a way that it might not apply to the particular tasks being carried out at the time that this incident occurred. Nevertheless, there is a clear reference in the documentation to a danger being "fall from heights" and the necessity for "riggers to wear safety harness when moving around at heights." However, that documentation issued by GPCC was amended immediately after the incident to apply specifically to the work of installation of pre-caste concrete panels and which dealt in much greater detail with this particular work. That amended documentation was put into operation on 21 April 2004, the day after the incident and was specifically reviewed by Mr Tony Roth.
15 The prosecution in his submissions emphasised the generality of the GPCC documentation prior to the incident and the improvement brought about by the amendment after the incident as being indicative of culpability on the part of both JML and GPCC. I shall return to this aspect of the proceedings later in these reasons for judgment.
16 It is now necessary to refer to some of the other evidentiary material in describing what happened the day before the incident and in describing the events leading up to the incident.
17 The employees of GPCC, Anthony Roth and Timothy Hyeronimus commenced working on the site on 19 April 2004. Mr Roth was a certified rigger and had worked also as a crane driver. He had previously worked as a construction team co-ordinator organising the transport and erection of pre-caste concrete panels for a period of 5 years. For 13 years before that he had worked predominantly on single storey warehouse style constructions both as a labourer and as a supervisor.
18 Before commencing work on 19 April 2004, Messrs Roth and Hyeronimus had attended a toolbox meeting for about 15 minutes that was conducted by a director of GPCC. That meeting discussed a number of occupational health and safety matters including, specifically, "fall protection."
19 As a result of a complaint Inspector Sandall of the WorkCover Authority of New South Wales attended the site on 19 April 2004 and specifically told Mr Roth that fall protection was to be maintained at all times including the wearing of safety harnesses.
20 After this occurred Mr Zaim Arabelovic, one of the site supervisors employed by JML, had a conversation with Mr Roth in which he told him that he should wear his harness at all times when he was carrying out work involved in the fixing of the pre-caste panels. He said that Mr Roth remonstrated but that he repeated that safety harnesses had to be worn at all times. Mr Roth told him that he understood this direction.
21 As a result of this incident, JML determined that the GPCC employees would be closely watched whilst pre-caste concrete panels were being installed the next day. This supervision was carried out by Mr Arabelovic who supervised Mr Roth and Mr Hyeronimus substantially all of the working time on the next day, 20 April 2004. The only time when direct supervision did not occur was when Mr Arabelovic had to descend to the ground level to sign off for the delivery of the pre-caste concrete panels and to supervise their loading onto the crane. This occurred six or seven times that day. Mr Arabelovic was also absent briefly for toilet breaks. The evidence is that at all times during the performance of work on 20 April 2004 both Mr Roth and Mr Hyeronimus wore their safety harnesses until about 3pm, when Mr Arabelovic left the area to attend to the loading of the last concrete panel that day. Shortly after he left the site, Mr Roth decided that he would take off his safety harness. The reason for the removal of the safety harness given by Mr Roth was: "I felt safer doing it this way without the lanyard getting caught on starter bars and things on the ground, it is a lot easier to trip when you come to a sudden halt or you lose control of the panel and it hits another panel. I felt safer."
22 Despite this explanation, which Mr Roth gave to a WorkCover inspector when being questioned about the matter on 13 May 2004, Mr Roth did not at any stage on 19 or 20 April 2004 make any comment or complaint to Mr Arabelovic about any difficulty in performing his work whilst wearing the safety harness.
23 It must be concluded from this evidentiary material that the real and effective cause of the fact that Mr Roth was performing work at a height of about 20 metres above ground level near the edge of a building under construction, in circumstances where there was a clear risk that if he fell he would sustain serious injuries, was the blatant failure of Mr Roth to comply with instructions which had been explicitly and specifically given to him by a WorkCover Authority inspector and by the site supervisor, Mr Arabelovic, that he should wear a safety harness at all times whilst carrying out this work and in disregard of the matters discussed on 19 April 2004 at the toolbox meeting conducted by a director of GPCC. Each of JML and GPCC was compelled by the Act to ensure, in the sense of guaranteeing, that Mr Roth was not subjected to any risk of injury whilst performing his work. It was stressed on behalf of the prosecutor during the course of submissions that one way of ensuring that this occurred would have been the more rigid and greater attention to the documentation which was created by both defendants, to which I have earlier referred and which was the subject of amendment after the incident in a manner which I have described. Whether and to what extent the creation of more comprehensive and explicit documentation would have assisted either defendant in ensuring that Mr Roth wore a safety harness on the particular days is a matter of conjecture. Nevertheless, there were deficiencies in the documentation produced by both defendants which the prosecutor submitted should be taken into account in assessing the objective seriousness of this offence.
24 More pertinently, the prosecutor submitted, with respect to the defendant JML, that having been alerted on 19 April 2004 to the predisposition of Mr Roth to fail to adhere to instructions in the wearing of a safety harness, the supervision of Mr Roth, which was conducted on the following day, was inadequate. That is, it was asserted by the WorkCover Authority of New South Wales that Mr Roth should have been supervised by JML in order to comply with its obligations under the Act for all of the time that Mr Roth was carrying out his work. It was submitted that there were deficiencies in the supervisory process because Mr Arabelovic had to leave the particular site on six or seven occasions during the day to attend to the delivery and loading of concrete panels and during toilet breaks. That is, in order to comply with its obligations under the Act, the WorkCover Authority of New South Wales asserted that during such periods as Mr Arabelovic was absent that day, arrangements should have been made for someone else to have conducted the appropriate supervision.
25 It is well established that the Act creates absolute offences. That is, once there is a risk to the safety of a person performing work, this will result automatically in a breach unless the defendant can come within the defences created by s 28. Once Mr Roth had taken off his safety harness a risk to his safety was created and each defendant was in breach. The only means of preventing that breach would have been constant supervision, and in particular supervision at the time that Mr Roth removed his harness. It was this failure that put both JML and GPCC in breach of the Act.
26 In determining the appropriate penalty to be imposed in each case it is necessary to have regard to the objective seriousness of the offence. This requires, in my opinion, a consideration of the total situation which prevailed at the time that the breach occurred, the identification of the various matters by way of cause and effect which were in play at the time and an assessment of the nature and extent of the breach by reference to what occurred. The real and effective cause of what occurred was, in my opinion, the aberrant, deliberate and irresponsible conduct of Mr Roth in removing his harness. This was especially so given the breach by him of clear contrary directions given by a person in obvious supervisory authority, namely Mr Arabelovic, and given by a person with statutory authority, namely a WorkCover inspector. It must be problematic in these circumstances that no amount of attention to detail in the safety documentation of either defendant would have had any impact on Mr Roth and his compliance with directions to wear a safety harness. This is, therefore, a matter of less significance. However, it cannot be denied that constant supervision of Mr Roth by JML would have prevented him from removing his harness, he having worked for all of the time up until when the incident occurred on 20 April 2004 wearing his harness without apparent complaint.
27 Seen in this way, the breach by JML and, hence, by GPCC, was a failure to adequately supervise a person about whom it was previously known that he was disinclined to obey safety directions given to him by persons in authority. The objective seriousness of each of the offences with which each of the defendants is charged must be assessed in this way. Given that there was obvious danger in working at a height of about 20 metres unprotected and unrestrained in terms of a risk of falling and given that Mr Roth was known to be disobedient in complying with directions concerning his safety, the breach by each of the defendants must be regarded as a serious one. However, given that each defendant was dealing with a person who obviously had little or no regard for his own safety and no seeming intention of obeying directions, I do not regard each of the breaches as warranting the imposition of a penalty at the higher end of the scale. Indeed, the prosecutor so submitted.
28 During the course of submissions, counsel for JML commented that it was regrettable that no prosecution had been instituted by the WorkCover Authority of New South Wales against Mr Roth. I agree.
29 The Act imposes specific obligations on employees. S 20 is in the following terms:
20 Duties of employees