Prosecutor's evidence
7Mr C Magee of counsel, who appeared for the prosecutor, tendered an agreed statement of facts. There remains some facts in dispute between the parties. These are identified in the statement of facts with the prosecutor's version of the facts identified by the letter "A" and the defendants' version of the facts identified by the letter "B". The agreed statement of facts provided:
...
The parties
2. At all material times Stratabuild Pty Ltd ("Stratabuild") was a corporation operating as a painting company.
3. At all material times Carlos Acevedo was the sole director and owner of Stratabuild. Mr Acevedo was employed by Stratabuild.
Background
4. Stratabuild was registered on 7 July 2006. It primarily undertakes painting and minor building repair work in the building and construction industry.
5. Stratabuild was contracted by Paint & Technical Services Pty Ltd on behalf of the owners of Strata Plan 60294, to carry out re-tiling of balconies, minor repair work and painting of the outside of buildings, including balconies and courtyards called "The Landings', the "Tors" and the "Tors Annex", which were part of an apartment complex known as the "Balmain Cove Complex" at 3 Wulumay Close, Rozelle ("Site").
6. The contract to perform the work at the Site commenced on approximately 1 October 2007 and was due for completion on 1 March 2008. The contract price was the sum of $531,930.00 plus prime cost items. The work to be undertaken under the contract included painting the balconies and pergolas on the balconies. Stratabuild was the principal contractor on the Site. (Vol 2, Tab 7.12 - Contract for Building Repairs and Painting with Stratbuild dated 1 October 2007).
7. Stratabuild supplied all materials and equipment for the work to be performed under the contract at the Site. This included paints, scaffolding, ladders and other equipment.
8. Stratabuild also had available for use approximately 5 safety harnesses and lanyards. (Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A122) .
9. Stratabuild also utilised a swing stage for areas that could not be reached using ladders or scaffolding. (Vol 1, Tab 6.3 - Witness statement of Christopher Vega dated January 2011 at [14]) .
10. Mr Acevedo managed the business of Stratabuild. He also performed painting and other related tasks for Stratabuild, including the erection scaffolding and supervision of workers.
11. Mr Acevedo played a significant role in the development of the systems of work that were utilised by Stratabuild both generally and at the Site.
12. Mr Acevedo held a Certificate of Competency in scaffolding. He undertook scaffolding work on the Site. He also provided training to other employees in erecting and dismantling scaffold at the Site.
13. On the day of the Incident, Mr Acevedo was performing work at the Site.
14. On the day of the Incident, Mr Acevedo's role in relation to the work being performed at the Site included directing other workers of Stratabuild as to the tasks that they should undertake. (Vol 1, Tab 6.3 - Witness statement of Gustavo Asciutto dated 11 February 2011 at [14]; (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008 at Q&A39) .
15. Mr Acevedo was on Site at the time of the Incident and was performing work in relation to the erection of scaffolding on the north elevation of the building called the Landings, near to where Mr Vega was performing work.
16. Mr Acevedo held a Certificate of Competency in scaffolding. He undertook scaffolding work on the Site. He also provided training to other employees in erecting and dismantling scaffold at the Site.
17. Mr Acevedo played a significant role in the development of the systems of work that were utilised by Stratabuild both generally and at the Site.
18. On 19 March 2008, Stratabuild had employed or engaged approximately seven people to perform work on the painting and repair of the building.
19. As at 19 March 2008, Ivan Vega was employed by Stratabuild as a painter.
20. Ivan Vega commenced work for Stratabuild at the Site in or about October 2007 (Vol 2, Tab 7.10 - Records of Hours worked; Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A62) .
21. Ivan Vega had worked for Stratabuild since approximately March 2007. This had included performing work at other sites.
21-B. Ivan Vega held the OHS General Induction for Construction Work in NSW - OHS Construction Induction Training Certificate (formerly Green Card). Ivan Vega held Card Number W044317607 .
22. In February 2006, Ivan Vega obtained qualifications to operate a Scissor Lift.
22B. The assessment included questions about fall arrest harnesses as did the demonstration he had to complete to get his card.
23. In February 2008, while contracted by Everest Contracting Pty Ltd, Ivan Vega completed the Rail Industry Safety Induction.
23B. In February 2008, while Stratabuild Pty Ltd was subcontracted by Everest Contracting Pty Ltd, Ivan Vega completed the Rail Industry Safety Induction Course with an accredited course provider at the request and expense of Stratabuild Pty Ltd. He was deemed competent in Rail Safety Induction as he displayed an acceptable level of understanding and awareness of Rail Safety Induction procedures to comply with the requirements of RailCorp and the NSW Rail Regulator. There were modules on Risk Management, Safe Work Practices and Key Safety Categories which included Working at Heights which specifically made reference to working safely with ladders, including the 1:4 rule for ladders and the need to maintain three points of contact with the ladder (Defendant's Documents Additional Documents II Rail Safety Course (b) Railcorp Working Safely Handbook issue date 12/12/2007 at pages 31- 33).
24. On 9 February 2008, while contracted by Everest Contracting Pty Ltd, Ivan Vega signed a SWMS/JSA relating to painting work being conducted a Coledale Train Station and a Daily Hazard Assessment.
25. On 10 February 2008, while contracted by Everest Contracting Pty Ltd, Ivan Vega signed a SWMS/JSA relating to painting work being conducted a Como Train Station and two Daily Hazard Assessments on different days.
26. Victor Galvez was employed or engaged as Stratabuild's Site Supervisor/Foreman. He had been engaged by Stratabuild for approximately 4 months at the date of the Incident. Prior to this date he had been engaged from April 2007 by another company of which Mr Acevedo was a director. Mr Galvez reported to Mr Acevedo and was supervised by Mr Acevedo. Mr Galvez had been a supervisor for Stratabuild for 2 months at the date of the Incident.
27. Mr Galvez holds the following qualifications:
(a) Certificate of Proficiency - Painting & Decorating, apprenticeship completed 29 April 2002;
(b) Certificate III in Painting and Decorating , December 2000;
(c) Certificate IV in Building Studies, Residential, July 2005;
(d) Contractor Licence, Painting and Decorating, 159502C;
(e) First Aid - Apply First Aid, issued 3 June 2009
(f) First Aid - Perform CPR, issued 18 June 2010
(g) Rail Industry Safety Induction Certificate, issued 22 February 2008;
(h) Occupational Health and Safety General Induction for Construction Work in NSW, OHS Construction Induction Training Certificate, issued 10 October 2005.
28. Gustavo Asciutto was employed or engaged as a painter by Stratabuild. He had been engaged by Stratabuild for approximately 2 weeks at the date of the Incident.
29. Roberto Navarro was employed or engaged as a painter and labourer by Stratabuild. He had been engaged by Stratabuild for approximately 15 months at the date of the Incident.
30. Mario Torres was employed as a painter by Stratabuild. He had been engaged by Stratabuild on or about 22 February 2008, and had worked at the Site for approximately 1 month at the date of the Incident.
31. Christopher Vega (son of the deceased) was employed as a labourer by Stratabuild in or about October 2007. He had been employed by Stratabuild for approximately 4 months at the date of the Incident.
32. Stratabuild paid Mr Vega, Mr Galvez, Mr Asciutto and others who performed work at the Site (Vol 2, Tab 7.11). Stratabuild paid superannuation contributions for Mr Vega, Mr Galvez, Mr Asciutto and others at the site.
33. For about 1 month prior to 19 March 2008, Stratabuild workers were performing work on the building known as the Landings. In the week before 19 March 2008, this work involved work on the northern elevation or 'waterfront' side of the apartments. The Landings was primarily a 4 storey building with a small component being 3 storeys in height. (Vol 1, Tab 7.1 - Photo 3 of Photographs taken by Vince Castro on 19 March 2008).
34. This work generally included the painting of the exterior surfaces of the front of the apartments, including the courtyards and balconies of the buildings.
System of work in relation to accessing work areas at heights and working at height
35B. Stratabuild's system for the works to be performed by its workers at the site included inter alia an initial informal site induction. This site induction involved looking around the Site for hazards and discussing matters such as working at heights, scaffolding, toilets and places to keep equipment. (Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A56 - 58).
35. After the initial induction, consultation in relation to safety primarily involved Mr Acevedo talking to workers about safety during lunch breaks or when he saw someone doing something unsafe. Mr Galvez, in his role of Supervisor, would also raise safety concerns that he saw with workers.
The Incident
36A. On 19 March 2008, Mr Vega and Mr Asciutto had been directed by Mr Acevedo to continue to undertake painting work on the exterior surfaces of the apartments and the courtyards on the ground level and first floor of the northern elevation or 'waterfront' side of the Landings. (Police statement between Gustavo Alejandro Asciutto and Constable Chris Fraser dated 19 March 2008 at [4]).
36 B. On 19 March 2008, Mr Vega commenced work at approximately 7 am.
On the day of the Incident, Mr Vega and Mr Asciutto were directed by Mr Acevedo to continue performing the work that they had been performing the day before. This involved painting the outside surfaces of the ground floor apartments on the front side of the building called 'The Landings'. ( Police statement between Gustavo Alejandro Asciutto and Constable Chris Fraser dated 19 March 2008 at [4]).
36. On 19 March 2008, Mr Acevedo and other workers were moving scaffolding components to the northern elevation of the Landings to commence erecting scaffold at the front of the Landings. (Vol 1, Tab 7.1 - Photo 4 of Photographs taken by Vince Castro on 19 March 2008).
This scaffolding was being constructed so that the painters and tilers could commence work. The Tiler were to undertake waterproofing and tiling of balconies including on apartment No. 15, which was on the fourth floor of the Landings. The scaffolding was also to be used to paint the upper levels of the northern elevation of the Landings, once the tilers had completed their work. (Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A45; Witness statement of Victor Galvez dated 1 June 2011; Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A117; Vol 1, Vol 1, Tab 6.9 - Witness statement of Thomas Winston Muter dated 13 January 2011 at [22] -[25]; Witness statement of Mario Torres dated 31 January 2011 at [40] - [41]).
37. At approximately 7.10 am, Mr Vega and Mr Asciutto commenced to undertake painting the outside surfaces of the ground floor apartments on the front side of the building called 'The Landings'.
37-B . Stratabuild had an arrangement with the Owners Corporation to obtain access to balconies when needed. The point of contact on site was the Caretaker, Tom. Galvez was walking towards Tom to make his way to third floor and on the way and saw Ivan and Gustavo painting one of the ground floor units. He noticed that the colour was incorrect. At that stage they appear to have completed one unit and were walking to the next unit. There is no clear vision between the courtyards because they are obscured by hedges and walls. Galvez noticed the incorrect colour by looking at the upper section of the ground floor.
38. At approximately 7.40 am, Mr Galvez came to the area where Mr Vega and Mr Asciutto, were undertaking painting work. Mr Galvez noted that they were utilising the wrong colour paint to undertake the work. They were using 'Summer Straw' when they should have been using 'Grand Canyon'. Mr Galvez informed Mr Vega and Mr Asciutto that the colour they were using was for the higher balconies. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A36; Police statement of Victor Galvez dated 19 March 2008 at [6]; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [26]).
39. Mr Galvez directed that Mr Vega and Mr Asciutto pack up the colour that they were using and to commence to paint the building with the correct colour. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A36; Police statement of Victor Galvez dated 19 March 2008 at [6]; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [26]).
40-A. Ivan Vega responded to Mr Galvez that it would take him and Mr Asciutto half an hour to clean the brushes and rollers and get the paint to re-paint the area, and that they had already wasted half an hour. Ivan Vega proposed that he and Mr Asciutto continue to use that colour and paint some of the balconies of the apartments that required that colour. Mr Asciutto agreed that that was a good idea. ( Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [27]).
The other part of the building that Mr Vega proposed that they commence painting was on the waterfront northern aspect of the Landings, but involved the balconies on the second floor of the Landing.
Mr Vega' proposal meant that he and Mr Asciutto did not need to clean the brushes and rollers and get the new paint and they could remain the area where they were and finish using the colour paint that they had started to paint with. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A39-40; Police statement of Victor Galvez dated 19 March 2008 at [6]; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [27]-[30]).
A further discussion then occurred between Mr Galvez, Ivan Vega and Mr Asciutto as to the merits of this proposal.
Mr Galvez agreed to this proposal. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A39-40; Police statement of Victor Galvez dated 19 March 2008 at [6]).
40-B. Mr Galvez had the following conversation with Ivan in Spanish:
VG : "You dumb ass. Can't you see that that's the wrong colour - you're using Summer Straw when it should be Grand Canyon. Go and put the paint and tools away and come back with the right colour"
Ivan: "I don't want to walk all the way to the site shed and clean the tools can't we use this colour on the other balconies?"
Me: "No. We have to first finish the ground floor balconies and fix your fuck up, after that when the scaffolding is erected we will paint the upper balconies."
The ground floor area where Vega was working was prepared and primed. The second floor and above had no preparation or primer applied at this time. For the second floor and above to be painted the area would first have to be prepared. Preparation involves water blasting of surfaces, scraping, sanding, rendering or filling of surfaces. Then the ceiling would have to be painted first. They could not start painting the walls when the ceilings had not been painted yet. This was common practise. For these reasons I did not and could not tell Ivan and Gus that they were allowed to paint above the ground floor with the finish paint. (Galvez statement June 2011 paragraph 28.)
41. Subsequently, Mr Galvez left the area where Mr Ascuitto and Mr Vega had been painting and went to locate the caretaker of the Landings, Thomas Muter, to assist moving furniture from the balcony of apartment No. 15, which was on the fourth floor of the Landings. This apartment was due to have its tiles replaced on the balcony.
42. Subsequently, Mr Vega and Mr Asciutto commenced preparations to paint the second-floor balcony of apartment number 22. This balcony was two floors directly above the courtyard of apartment number 16. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A39-40; Police statement of Victor Galvez dated 19 March 2008 at [6]; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [26]).
43. Mr Vega and Mr Asciutto determined that they would use a ladder in order to gain access to the balcony of apartment number 22. ( Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [30] -[33]; Vol 1, Tab 7.1 - Photo's 13, 14 of Photographs taken by Vince Castro on 19 March 2008)
43-B. But did not advise anyone that they intended to do so.
44. Mr Vega and Mr Asciutto obtained an aluminium extension ladder which was owned by Stratabuild (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A69-72; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [32]) .
45. The ladder was an 'OLDFIELDS, Tradesman 120 kg load rating' extension ladder, which was approximately 3650 mm in a folded position and 6 metres long in its extended position (Vol 1, Tab 5 - Factual Inspection Report signed by Inspector Vince Castro dated 26 March 2008 at [6] & [7]; Vol 1, Tab 7.1 - Photo's 8, 9, 10, 11 of Photographs taken by Vince Castro on 19 March 2008) .
46. Mr Vega and Mr Asciutto intended to conduct work by painting from inside of the balcony. (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A41 and 101-104; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [29])
47. The second-floor balcony had a concrete/brick rendered beam and wall topped with a metal balustrade approximately 600 mm high. (Vol 1, Tab 5 - Factual Inspection Report signed by Inspector Vince Castro dated 26 March 2008 at [12]; Vol 1, 7.1.1 -Sketches and measurements undertaken by Inspector Castro on 19 March 2008; Vol 1, Tab 7.1 - Photo's 8, 12, 13, 14 of Photographs taken by Vince Castro on 19 March 2008).
48. he height of the top of the metal balustrade of the second-floor balcony was in excess of 6 metres from the terracotta tile floor of the courtyard of apartment number 16. (Vol 1, Tab 5 - Factual Inspection Report signed by Inspector Vince Castro dated 26 March 2008 at [12]; Vol 1, Tab 7.1 - Photo 17 of Photographs taken by Vince Castro on 19 March 2008 .
53-A. Mr Galvez did not give any instruction or direction as to how access could be gained to the balcony apartment or to asses the risk of getting onto the balcony.
53-B. Galvez did not have an opportunity to give Vega an instruction as to how he should access the balcony apartment or asses the risk because he did not know that Vega intended to access the Balcony.
54. Neither Mr Vega or Mr Asciutto undertook a formal documented risk assessment in relation to the specific task of utilising a ladder to access the balcony of apartment number 22.
55. Mr Vega set the ladder up inside the courtyard of apartment number 16. The courtyard dimensions were approximately 5 m x 2 m square of uncovered area. This uncovered area was formed by a metal gate with a brick rendered pillar to each side of the gate. The pillars were connected to walls approximately 1.8 m long by 1 m high. The floor was a terracotta/concrete floor. (Vol 1, Tab 5 - Factual Inspection Report signed by Inspector Vince Castro dated 26 March 2008 at [13]; Vol 1, Tab 7.1 - Photo's 18- 25 of Photographs taken by Vince Castro on 19 March 2008)
56. The ladder was set up to the right of the gate and pillar (looking at the apartment from the outside), with the base of the latter close to the inside of the connecting wall (Vol 1, Tab 6.11 - Witness statement of Necole Gawne dated 11 January 2011 at [16] ; Vol 1, Tab 7.1 - Photo's 31, 32 of Photographs taken by Vince Castro on 26 March 2008) .
57. The top of the ladder was placed against the outside of the rendered brick/concrete wall of the second-floor balcony (Vol 1, Tab 6.7 - Witness statement of Mario Torres dated 22 April 2008, Q&A18; Vol 1, Tab 7.1 - Photo's 26 -28 of Photographs taken by Vince Castro on 26 March 2008) .
58. Due to the height of the second-floor balcony with the balustrade, the length of the ladder was not sufficient for it to reach above the top of the balustrade. (Vol 1, Tab 7.1 - Photo's 26 -28 of Photographs taken by Vince Castro on 26 March 2008) .
59. As a result the top of the ladder did not extend above the level of the balustrade by a distance of no less than 1 metre, so as to allow Mr Vega to access the balcony without having to climb from the ladder over the balustrade and on to the balcony. (Vol 1, Tab 7.1 - Photo's 26 -28 of Photographs taken by Vince Castro on 26 March 2008) .
60. The ladder used was not placed in compliance with the requirements of section 2.6 - Part 5: Selection, safe use and care of "Portable ladders", in AS/NZS 1892.5-2000. This required that when a ladder is used to gain access to a working platform or roof, the top of the ladder should extend above the level of the working platform or roof by distance of no less than 1 metre. (Vol 2, Tab 7.15 p. 7 - Australian/New Zealand Standard "Portable ladders Part 5: Selection, safe use and care")
61. Mr Vega then commenced to climb the ladder.
62. Whilst climbing the ladder Mr Vega had a painter's drop sheet in his right hand and had a pot which had paint and a brush in it in his left hand. Mr Vega used his right hand (which also had the drop sheet in it) to help him climb. (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [5]; Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [38]; Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A83)
63. After Mr Vega had climbed about 10 steps, Mr Asciutto, stood against the ladder to support it. Mr Asciutto, stood with his two feet against the bottom rungs of the ladder and placed his hands on either side of the ladder and leaned against the ladder to stop it from falling back or becoming unsteady. (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [5])
64. Mr Vega climbed to near the top of the ladder where it met the outside of the rendered brick/concrete wall of the second-floor balcony. (Vol 1, Tab 6.1 - P olice statement of Roberto Navarro dated 19 March 2008 at [7] ; Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6];).
65. As Mr Vega got close to the top of the ladder, Mr Asciutto noticed that the ladder started to move around and become unsteady. When the ladder started to move around Mr Asciutto looked up and saw Mr Vega begin to fall backwards. Mr Vega fell from the top of the ladder. (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6]; Vol 1, Tab 6.1 - P olice statement of Roberto Navarro dated 19 March 2008 at [8]).
66. Mr Asciutto stated that he did not hear Mr Vega say anything before or whilst he was falling. Mr Asciutto did not observe what caused Mr Vega to fall from the ladder. (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6])
67. Mr Ascuitto stated that he observed that Mr Vega was falling backwards towards the right-hand side of the ladder. When he saw Mr Vega falling Mr Asciutto moved to where he thought he was going to land (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6]) .
68. Mr Vega was falling about 1 to 2 metres away from where the ladder was. Mr Asciutto put both his arms out to try and catch Mr Vega before he hit the ground (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6]) .
69. Mr Asciutto stated that Mr Vega fell into his arms, but he was not able to stop him falling completely. The back of Mr Vega's head hit the top of the rendered brick pillar in the courtyard of apartment number 16 (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6]) .
70. After hitting his head, Mr Vega landed on the terracotta tile floor of the courtyard approximately 1 metre inside from the wall (Vol 1, Tab 6.6 - Police statement of Gustavo Alejandro Asciutto dated 19 March 2008 at [6]) .
71. Mr Vega was bleeding from the back of his head, ears and mouth. He was lapsing in and out of consciousness.
72. A number of persons working for Stratabuild then commenced to give first aid to Mr Vega. Mr Acevedo performed mouth to mouth resuscitation and chest compression on Mr Vega whilst awaiting for the emergency services to arrive.
73. Subsequently, the NSW Ambulance Service attended and commenced giving Mr Vega first aid including cardiopulmonary resuscitation.
74. NSW Ambulance Service's initial assessment was that Mr Vega had suffered a fractured skull, bleeding on the brain and several fractured ribs.
75. Mr Vega was transported by Ambulance to the Royal Prince Alfred Hospital, Camperdown where he was admitted at 0845 hours on 19 March 2008.
76. On the initial examination on admission, the attending medical practitioner, noted evidence of closed century was bleeding from the right year in blood from nose. A CT scan of the brain demonstrated right frontal haemorrhage and left frontal contusion. There was also evidence of diffuse cerebral oedema and evidence of raised cranial pressure.
77. Mr Vega was taken to theatre to undergo an emergency decompressive craniotomy.
78. Whilst undergoing surgery Mr Vega suffered a hypovolemic shock/arrest. This was contributed to by cerebral herniation and out of hospital cardiac arrest.
79. Mr Vega was pronounced dead at approximately 11:30 am on 19 March 2008. (Vol 2, Tab 7.3 -NSW Police Report of Death to Coroner form undated; Department of Health NSW Report of Death Associated with Anaesthesia/Sedation dated 19 March 2008; Royal Prince Alfred Hospital Report of the Death of a Patient to the Coroner dated 19 March 2008).
Stratabuild's Systems of work at the Site
80. At or prior to the date of the incident, Stratabuild did not provide to its workers including Ivan Vega a documented formal Safe Work Method Statement specific to the work to be undertaken at the Site. (Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A127 & 137; Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Vol 1, Tab 6.3; Witness statement of Christopher Vega dated 22 April 2008 - Q&A88 & 93; Vol 1, 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [9]; Vol 1, Tab 6.7 - Witness statement of Mario Torres dated 22 April 2008, Q&A21; Witness statement of Mario Torres dated 31 January 2011 at [11]) .
82-B. At or prior to the date of the incident all site specific management and training discussions took place at the worksite in Spanish. No written site specific safety management plan was provided to Mr Vega or the other workers.
81. Stratabuild's system for the works to be performed by its workers at the site included an initial informal site induction.
82. This informal site induction involved the Stratabuild workers walking around the Site and being shown the location of the amenities as well as an informal assessment of the risks involved in the work to be performed on the different facades of the different buildings. (Vol 1, Tab 6.1 - Witness statement of Roberto Navarro dated 18 April 2008, Q&A56 - 58; Witness statement of Victor Galvez dated 1June 2011 at [7]).
83. Stratabuild did not have a formal Site induction document for the inductions that were undertaken for the Site.
84. The fact that site inductions were conducted or who attended was not recorded in a document by Stratabuild.
85-B. The workforce was however small comprising 7 persons
86-A. However, Gustavo Asciutto and Mario Torres state that they did not undergo a formal s ite specific induction when they commenced on Site. (Vol 1, 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [7]; Vol 1, Tab 6.7 - Witness statement of Mario Torres dated 31 January 2011 at [9]-[10])
86-B. As each building and each faade was different each faade required its own assessment and painting plan. ( Witness statement of Victor Galvez dated 1June 2011 at [7]).
Prior to work commencing on each faade, a site meeting would be held to discuss the work to be done and the way it was proposed that the faade was to be painted. ( Witness statement of Victor Galvez dated 1June 2011 at [7]).
These discussions included who was to perform the work and whether scaffolding, swing stages or other methods would be used to access work areas and undertake work at heights in excess of 2 metres at the Site. ( Witness statement of Victor Galvez dated 1June 2011 at [20]).
These site meetings would occur in the morning before work commenced or during lunch breaks.
85. However, these assessments were not formalised or documented prior to or at the time of the Incident.
87-B. Mr Acevedo would also discuss safety when he saw someone something in an inappropriate and unsafe way safety instruction took place on site before, during and after work doing something unsafe. Mr Galvez, in his role of Supervisor, would also raise any safety concerns that he had with workers.
87. Stratabuild did not have in place at the Site a formal document that dealt with hazard identification, assessment and control.
88. Stratabuild did not have available for use a pro forma document for workers to utilise to assess any hazards or risks in respect to the work they were doing.
89. Prior to the Incident, Stratabuild had not completed a formal documented risk assessment of the hazards associated with the use of ladders to access work areas including balconies at heights in excess of 2 metres at the Site.
90. Prior to or at the time of the Incident, Stratabuild had not completed a formal documented risk assessment of the hazards associated with gaining access to work areas and working from areas including balconies at heights in excess of 2 metres at the Site;
91. At or prior to the date of the Incident, Stratabuild did not have any documented system that detailed the requirements and circumstances for the use of portable ladders when accessing work areas and working from heights in excess of 2 metres at the Site.
92. On occasions portable ladders were used by Stratabuild to access and paint second floor apartments of the buildings at the Site. Fall arrest systems such as harnesses and lanyards were provided for use in these circumstances. ( Witness statement of Victor Galvez dated 1June 2011 at [20]).
93-A. However, on occasions portable ladders were used by Stratabuild workers to access and paint balconies of the buildings at the Site without using a fall arrest system. ( Witness statement of Gustavo Asciutto dated 11 February 2011 at [18]; Witness statement of Mario Torres dated 31 January 2011 at [17] - [24]).
93-B. However, on occasions portable ladders were used by Stratabuild workers to access and paint balconies of the buildings at the Site below 2 meters, without using a fall arrest system. (Witness statement of Gustavo Asciutto dated 11 February 2011 at [18]; Witness statement of Mario Torres dated 31 January 2011 at [17] - [24]).
94-A. At or prior to the date of the Incident, Stratabuild did not have a site specific formal documented system that advised its workers that
(a) portable ladders were not be used without a fall restraint systems such as a harness and lanyard systems portable ladders not be used where the top of the ladder did not extend above the level of the working platform, balustrade or roof by a distance of not less than 1 metre;
(b) whilst ascending portable ladders the person must have both hands free to grip the ladders;
(c) whilst climbing portable ladders persons should not carry paint pots, brushes, drop sheets, tools or other equipment in their hands;
94-B. At or prior to the date of the Incident, Stratabuild did have a formal documented system that advised its workers that:
(a) portable ladders were not be used without a fall restraint systems such as a harness and lanyard systems (Defendant's Documents Additional Documents II Rail Safety Course (b) Railcorp Working Safely Handbook issue date 12/12/2007 at page 31)
(b) three points of contact with the ladder must always be maintained (Defendant's Documents Additional Documents II Rail Safety Course (b) Railcorp Working Safely Handbook issue date 12/12/2007 at page 33)
(c) whilst climbing portable ladders persons should not carry paint pots, brushes, drop sheets, tools or other equipment in their hands, a tool belt / bag is be be used to carry any tools (Defendant's Documents Additional Documents II Rail Safety Course (b) Railcorp Working Safely Handbook issue date 12/12/2007 at page 33)
(d) the 1:4 rule for ladders must be followed (Defendant's Documents Additional Documents II Rail Safety Course (b) Railcorp Working Safely Handbook issue date 12/12/2007 at pages 32).
Details of systems of work after the Incident
94. After the Incident Stratabuild engaged the services of an OHS consultant, Sarkis Elias.
95. Mr Elias carried out a detailed investigation of the Site and buildings and documented a Site Safety Plan for implementation by Stratabuild ( (Vol 3, Tab 7.18.1 p.7 - Stratabuild Site Safety Policy - Project Name: 3 Wulumay Close, Balmain Cove, Task: Painting Works dated 1 April 2008) .
96. The new Site Management Plan was signed off by Carlos Acevedo on 1 April 2008 (Vol 3, Tab 7.18.1 - Stratabuild Site Safety Policy - Project Name: 3 Wulumay Close, Balmain Cove, Task: Painting Works dated 1 April 2008) .
97. The new Site Management Plan addressed issues including 'Hazard Identification and Risk Assessment', 'Consultation' and 'Working at Heights' (p.37) which included control safety measures such as the use and erection of scaffolding around the buildings.
98. Stratabuild's employees working on the Site were formally inducted on 28 March 2008. (Vol. 3, Tab 7.18.2 Induction Register).
99. A Safe work Method Statement for the Painting and Maintenance works at the Site was implemented on 1 April 2008. (Vol 3, Tab 7.18.3 -SWMS - Maintenance & Painting Works to 3 Wulumay Close, Balmain Cove completed by Carlos Acevedo, Manager dated 01 April 2008).
100. Stratabuild employees were inducted into the safe work method statements on 1 April 2008 and were given copies of the safe work method statements (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A117) .
101. Stratabuild also implemented a Site Safety Inspection Checklist performed risk assessments and undertook a weekly risk register. (Vol 3, Tab 7.18.4 -Site Safety Inspection Checklist (5 pages), Daily Hazard Assessment form revised 02 July 2006 (2 pages), Hazard Control Form for Stratabuild Pty Ltd (2 pages) and Hazardous Substance Register).
102. An Induction Register was also introduced which included details of the employee's qualifications and any medical conditions they had (Vol 3, Tab 7.18.2 Induction Register; Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A117) .
103. Stratabuild also issued a directive that workers were not to use any two-stage ladders at all on the Site. Further, a directive was issued that workers were not permitted to go above two metres on any ladder (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A117: Vol 1, Tab 6.6 - Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 at [38]) . They were also directed that they were not allowed to gain access to balconies using ladders or to use the ladders to undertake painting work. (Vol 1, Tab 6.7 - Witness statement of Mario Torres dated 22 April 2008, Q&A26) .
104. Stratabuild also introduced a separate site Office with a lunch room, which included details of emergency contacts and had management systems posted on the wall, and as well as containing copies of safety management plans and safe work method statements (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A117) .
105. Stratabuild also introduced more frequent toolbox meetings and improved communication between workers, for supervisors and the director (Vol 1, Tab 6.2 - Witness statement of Victor Galvez dated 21 April 2008, Q&A117; Vol 3 Tab 7.18.10 -Toolbox Meetings Minutes (Weekly Meeting) .
106. Stratabuild documented rules that its workers were not to answer mobile phones while working on ladders or scaffolding.
107. Stratabuild documented the mandatory use of personal protective equipment including gloves and safety boots.
8The prosecutor also tendered what Mr Magee described as "the prosecutor's tender bundle". It contained the following material:
- ASIC Current and Historical Extract for Stratabuild Pty Limited (ACN 120 624 679) dated 6 April 2010 and 9 July 2010;
ASIC Personal Names Extract for Mr Carlos Acevedo dated 10 June 2011;
ASIC Personal Names Extract for Mr Carlos Alberto Acevedo Cadiz dated 10 June 2011;
- WorkCover Prior Conviction Reports dated Thursday 8 April 2010 and 10 June 2011 for:
i. Stratabuild Pty Limited (ACN 120 624 679), and
ii. Mr Carlos Acevedo
iii. Mr Carlos Alberto Acevedo Cadiz
Each defendant has no prior convictions.
- Inspector Vince Castro's Statement signed 17 December 2008 (8 pages).
- Letter from Stratabuild Pty Limited to Inspector Derek Pryor dated 18 January 2010 (1 page) enclosing Section 62 Notice issued upon Stratabuild Pty Ltd by Inspector Derek Pryor dated 12 January 2010 (1 page) and material produced by Stratabuild Pty Ltd in response (39 pages).
- Factual Inspection Report signed by Inspector Vince Castro dated 26 March 2008 (4 pages).
- WorkCover Statements:
6.1 Witness statement of Victor Galvez dated 21 April 2008 (22 pages) attaching appendix "C" copy of police statement between Victor Galvez and Constable Darren Kelly dated 19 March 2008 (3 pages) including 4 payslips envelopes for the following dates:
From 4/4/08 to 10/4/08
From 28/3/08 to 3/04/08
From 27/3/08 to 21/3/08
From 11/4/08 to 17/4/08
Additional Statement of Victor Galvez dated 1 June 2011 (8 pages) together with annexure VG#001 and VG#002 (69 pages).
6.2 Police statement between Gustavo Alejandro Asciutto and Constable Chris Fraser dated 19 March 2008 (2 pages) and blank witness statement of Gustavo Asciutto dated 21 May 2008 (27 pages). Witness statement of Gustavo Alejandro Asciutto dated 11 February 2011 (6 pages).
6.3 Witness statement of Mario Torres dated 22 April 2008 (5 pages) and blank witness statement of Mario Torres dated 22 April 2008 (23 pages). Witness statement of Mario Torres dated 31 January 2011 (6 pages) and Translation from English to Spanish of Witness statement of Mario Torres dated 31 January 2011 (6 pages). These statements were not relied upon in the sentencing hearing.
- Supporting Documents:
7.1 Photographs taken by Vince Castro (45 pages).
7.2 3 sketches (3 pages).
7.3 WorkCover Prohibition Notice No. 146149 issued upon Stratabuild Pty Ld by Inspector Castro on 19 March 2008 (1 pages);
WorkCover Prohibition Notice No. 146149 issued upon Stratabuild Pty Ld by Inspector Castro on 20 March 2008 (1 pages);
Facsimile transmission report dated 26 March 2008 (1 page);
Facsimile from Inspector Castro to Carlos Acevedo dated 26 March 2008 (1 page) enclosing:
WorkCover Improvement Notice No. 7-155446 issued upon Stratabuild Pty Ltd by Inspector Castro on 26 March 2008 (1 page);
WorkCover Improvement Notice No. 7-155448 issued upon Stratabuild Pty Ltd by Inspector Castro on 26 March 2008 (1 page);
WorkCover Improvement Notice No. 7-155449 issued upon Stratabuild Pty Ltd by Inspector Castro on 26 March 2008 (2 pages).
7.4 Paint Tech Contract for Building Repairs and Painting dated 1 October 2007 (5 pages).
7.5 WorkCover Guide "Safe Working at Heights" dated 2006 (51 pages).
7.6 Australian/New Zealand Standard "Portable ladders Part 5: Selection, safe use and care" (19 pages)
7.7. Documents including:
7.7.1 Stratabuild Site Safety Policy - Project Name: 3 Wulumay Close, Balmain Cove, Task: Painting Works (39 of 40 pages).
7.7.2 Induction Register (1 page).
7.7.3 SWMS - Maintenance & Painting Works to 3 Wulumay Close, Balmain Cove completed by Carlos Acevedo, Manager dated 01 April 2008 (11 pages).
7.7.4 Site Safety Inspection Checklist (5 pages), Daily Hazard Assessment form revised 02 July 2006 (2 pages), Hazard Control Form for Stratabuild Pty Ltd (2 pages) and Hazardous Substance Register (1 page).
7.7.5 Various documents including:
Emergency Management Plan for 3 Wulumay Close, Balmain Cove (Preparation, Painting to Tors, Tors Annex & Landings) dated 01 April 2008 (10 pages from page 9 - 14 and 19 - 22).
Accident/Incident Investigation Report (2 pages).
First Aid Treatment Details & Register (6 pages).
7.7.6 Workers Compensation Accident Investigation Report for Ivan Vega dated 01 April 2008 (2 pages).
9Counsel also tendered extracts from plain clothes Constable Darren Kelly's notebook for the period 13 March 2008 to 18 March 2008 and his duty book entries for 19 March 2008.
10The material referred to at 4 above included a document titled "Maintenance & Painting Works to 3 Wulumay Close, Balmain Cove", being a safe work method statement developed by the personal defendant dated 3 April 2008, approximately two weeks after the incident. It was developed in consultation with employees who signed the document. Also included was an emergency management plan together with a site safety inspection checklist.
11Three statements of Mr Victor Galvez were tendered in the proceedings. The first statement dated 19 March 2008 (the date of the incident), was provided to Constable Kelly. Much of what was contained in this statement was consistent with the agreed statement of facts. However, the terms of paragraph 6 became controversial in the sentencing hearing. Paragraph 6 read:
I then proceeded down to the front of 'The landings' building. When I got down there I saw my colleague Ivan and Gus were painting the outside wall of the bottom section of the building. I spoke to Ivan and Gus in Spanish (As a result, I told them they were painting the building in the wrong colour, so they should pack up that colour and use the correct colour). We had a further conversation (As a result, they both said they would move there position and use the current colour on another part of the building). The other part of the building was still a the front of the building, but it was the top section. This means they could stay where they were, but needed a ladder to the other section, which is the second floor from the ground. I agreed with them and went with Tom, who is the maintenance guy of the 'Balmain Shores' complex, to Unit 15 which is on the fourth floor (so we could remove the furniture off the balcony into the unit, as the units balcony was being retiled).
12The second statement of Mr Galvez was that provided to Inspector Vince Castro dated 21 April 2008. Once again, much of the statement was consistent with the agreed statement of facts. Mr Galvez adopted his statement given to Constable Kelly as forming part of his interview with Inspector Castro. Asked if there was anything else that he wished to tell Inspector Castro regarding what he saw or heard at the time of the incident, he replied "no, that statement is very fresh from the day".
13Inspector Castro took Mr Galvez to paragraph 6 of the statement he provided to Constable Kelly and the following question and answers were provided:
Q35: Point 6 of the police statement you said "Ivan and Gus were painting the outside wall". Which side wall are you referring to?
A: We refer the outside walls to the face of the outside of the building.
Q36: Which colour paint were they using on the day of the incident?
A: They were using Summer Straw when they should have been using Grand Canyon.
Q37: Why was that?
A: They made a mistake, the colours are very similar and I guess they made a mistake.
Q38: Point 6 of the second floor from the ground. Which apartment is that?
A: I don't know.
Q39: What were the instructions given to Ivan from you?
A: I didn't see him the morning because I arrived late. Carlos told Ivan and Gus to keep going with what they were doing yesterday, then when I got down to the landings to see what they were doing, I realized they were painting the wrong colour so I told them off because they were painting the wrong colour and told them to change it and get the correct colour. They told me instead of getting that colour to paint one of the units that had the colour they had and I said ok.
Q40: Point 6 again, they needed a ladder. Did you ask them to get one?
A: No, I put this in my statement because when I was reading it through with the Constable if anyone else was reading it, it didn't make sense. I put it in the statement so they knew they had to get a ladder. I've worked with the boys for a while now and they know what to do so when I say go and do a certain colour they know what materials and equipment they need.
Q41: What work were Gus and Ivan going to be doing there:
A: They were going to paint the inside of the balcony.
14Also relevant were questions 101, 121, 122 and the answers provided. They read as follows:
Q101: Who directed Ivan and Gustavo to go to the area where the incident happened?
A: Carlos told them in the morning to paint the ground levels but they were using the wrong colour so instead of changing it they decided to continue with the work on the second floor balcony which wasn't painted and as I said in my police statement.
...
Q121: Do you wish to add anything to this statement?
A: I would like to add, one thing about Carlos and Stratabuild they like to encourage us to do further studies. When I first started working with Carlos in Acevedo Building Services he encouraged me to do a building course which I did, also Robert is doing his building course. I also know some of the boys have their elevated work platform certificates which Carlos organized and paid for and they did do their scaffolding course as well but because they were lazy they never handed in their paperwork so never go their licence. All these things were provided by Carlos before this incident ever occurred and Carlos and Stratabuild has never pushed us to do anything unsafe or dangerous ever.
Q122: Would you please read over this statement and tell me if there is anything that you wish to add?
A: Yes.
15On 1 June 2011, Mr Galvez made a further statement to the solicitors for the defendants. The critical paragraph was 28 which read:
I had the following conversation with them in Spanish:
Me: "you dumb ass. Can't you see that that's the wrong colour - you're using Summer Straw when it should be Grand Canyon. Go and put the paint and tools away and come back with the right colour."
Ivan: "I don't want to walk all the way to the site shed and clean the tools can't we use this colour on the other balconies?"
Me: "No. We have to first finish the ground floor balconies and fix your fuck up, after that when the scaffolding is erected we will paint the upper balconies."
16Annexed to this statement were the following documents:
(i) Safe Work Method Statement / JSA for Maintenance & Painting Works to Coledale Train Station dated 02/02/08 (25 pages);
(ii) Daily Hazard assessment Coledale Station 09/02/08 (2 pages);
(iii) Safe Work Method Statement / JSA for Maintenance & Painting Works to Como Train Station dated 08/02/08 (25 pages);
(iv) Daily Hazard assessment Como Station 10/02/08 (2 pages);
(v) Daily Hazard assessment Como Station 27/02/08 (2 pages);
(vi) Occupational Health and Safety General Induction for Construction Work in NSW - OHS Construction Induction Training Certificate date of issue 10/10/05 (2 pages);
(vii) First Aid International Apply First Aid Certificate Number 39347 and First Aid International Perform CPR Certificate Number 59045 (1 page);
(viii) Rail Industry Safety Induction Certificate Number CERT-TSIC-N04156 (2 pages);
(ix) Contractor Licence - Painter & decorator Number 159502C and Renewal Application (3 pages);
(x) TAFE NSW Certificate IV in Building Studies, Residential 90944NSW dated July 2005 (1 page);
(xi) TAFE NSW Certificate III in Painting & decorating dated December 2000 (1 page);
(xii) Certificate of Proficiency in Painting & Decorating - Apprenticeship completed 29 April 2002, date issue 18 July 2003 (1 page).
17Mr Galvez was called by the prosecutor to give further evidence. Mr M Luitingh of counsel, who appeared for the defendants, took no objection to Mr Magee cross-examining Mr Galvez, submitting that in the interests of justice it was unnecessary to go through the process of having him declared a hostile witness under the Evidence Act 1995.
18Mr Galvez acknowledged that during the interview with Inspector Castro, he showed him a copy of his record of interview with Constable Kelly.
19He agreed that his statement of 1 June 2011 was prepared with the assistance of the defendants' solicitor and counsel. It was prepared over two conferences he attended with the defendants' lawyers towards the end of May this year. Asked about providing the statement to Constable Kelly, Mr Galvez' evidence was that Constable Kelly first took the statement by writing in a notepad. He said he was speaking very quickly and that Constable Kelly said it was going to take too long so he started typing the statement on the computer, which was read to him when the statement was completed. Mr Galvez also read the statement himself. He made some changes to the document on the computer before being provided with a further version which he signed. This occurred on the day of the incident. His evidence was that when he signed the statement, he "just kind of skimmed through it and signed it because I wanted to leave there and go to the hospital to see Ivan".
20Mr Galvez was taken to paragraph 6 of the statement. He agreed that the first sentence in brackets in paragraph 6 which read "(As a result, I told them they were painting the building in the wrong colour, so they should pack up that colour and use the correct colour)", represented the effect of the conversation that he had with Mr Vega and Mr Gustavo Asciutto. He had spoken to them in Spanish and said " That's not the exact words I used no, there was swearing involved, a bit of swearing involved and more slang Spanish talk between each other".
21Mr Galvez was subsequently taken to the record of interview with Inspector Castro and agreed that he was taken line by line by Inspector Castro through paragraph 6 of the statement he had provided to Constable Kelly. Mr Galvez agreed that he had not sought to correct either the police statement or his answer at question 39 where he agreed that they could continue to use the paint that they had knowing that it would be used on the level 2 balcony and unit.
22Mr Galvez was then taken to his statement of 1 June 2011. He agreed that in light of the passage of time, that the events were not as clear in his mind as they were in March and April 2008 when he made his earlier statements. He was taken to his evidence at paragraph 28 and agreed that version was not mentioned in his earlier statements and that it was diametrically opposed to the effect of the conversations recorded in his interviews with Constable Kelly and Inspector Castro.
23Mr Galvez was cross-examined about the differences in the statements and gave the following evidence:
Q. Because you told Constable Kelly that you agreed with that proposal and you told Inspector Castro you said, "Okay"?
A. But as I mentioned, I should have said I didn't agree. But in the WorkCover with Mr Castro it says that I said, "Okay." Well, I said, "Okay.
Q. Sir, are you trying to say now on both occasions, both, you got it wrong when you were telling the police and when you were telling Inspector Castro?
A. No.
Q. Well?
A. The first one I did and the second one it says I said, "Okay".
Q. Because the truth is that the position was that you did say, "Okay" or you agreed, isn't it?
A. I still believe that I said, "No" and walked away.
Q. Well, sir, you further add?
A. That is sorry to interrupt you. But that is the reason I gave in this interview, the reason why I said, "No", because the areas were they were proposing to do the works hadn't been washed and hadn't been prepared in any way. Ceilings hadn't been painted, which is a common practice to point the ceilings before the walls if you are doing the painting work. That is why I believe that I didn't tell them to go paint the wall that hadn't been prepared, hadn't been primed, hadn't been filled or rendered in any way to go and paint them in the finish colour, which is the colours they were that painting.
Q. Sir, those were fairly important matters that would have been important to raise with both the police and Inspector Castro at the time, wouldn't they?
A. I guess so.
Q. And you didn't seek to raise those matters at all with either Inspector Castro or the police?
A. I didn't. With the police, as you of course would understand, I still see the image of Ivan on the floor every day.
Q. It would be very clear in your mind, wouldn't it, sir?
A. Yes, it is still very clear in my mind, yes, his face.
Q. And it was only hours after this conversation had occurred that you were telling the police what occurred?
A. We didn't want to go to the police, we wanted to go straight to the hospital and we had to go to the police station.
Q. And sir, it would have been very important to both exculpate any part of the blame that might be cast upon you for Ivan doing this work to disclose that you had told him, no, not to do it, and he had done it directly contrary to your instruction?
A. Well, when you are giving a statement you are not looking after the blame of anybody. You are not trying to save you arse in any way. You are just giving what you believe, you are just giving what you remember or what was happening on the day. And honestly, I said this a million miles an hour and that is why he started to do it on the computer and not on the note pad as it was originally getting done. And I just wanted to get out of there, to be honest with you.
Q. You are not suggesting Constable Kelly made up that you agreed. He would have had to have got that notion that you agreed from you?
A. I believe that he just missed a word out, or even Ivan's name isn't spelt correctly, there is mistakes in the statement itself, I didn't say that.
Q. Assume that is correct, and that the Constable got it wrong and, missed the "not agree", you can't use that same rationale for saying, "Okay" when you told Inspector Castro, can you, because you can't mistake, I said, "Okay"?
A. No.
Q. So did you get it wrong when you were telling Inspector Castro?
A. I think, well now I see, yeah I must have said it wrong or I honestly I know where you are coming from, I can see in the statement that it clearly says that I said okay.
Q. Sir, you have tried to explain at paragraphs 30 and 31 of your most recent statement how this mistake in the police statement came about. But at paragraph 32 you note that there were other errors in the statement. So you had identified, having gone through at statement, that there were errors and you corrected them?
A. Yes, but that is the first time I read it, yes.
Q. Sir, you identified that there were errors and you had the Constable change them. And sir, you didn't identify , "I agreed" as an error and get the Constable to change that, did you?
A. No.
Q. And surely, if you agree, if the words 'I agreed' was an error it would have been important to correct that?
A. Yes, it would have been, yes.
Q. Because that would have been misleading if you said the exact opposite of what had occurred?
A. Yes.
Q. Now you say in paragraph 33 of your new statement that after he printed out statement, this the second time, I presume, is it?
A. Yes.
Q. "I scanned it but were (sic) did not read it closely as I was in shock"?
A. That's right.
24Mr Galvez acknowledged that he had not mentioned the reference to scaffolding found in paragraph 28 of his statement of 1 June 2011 in any of his previous statements. His evidence was that the painters were going to paint from the scaffolding on that day, although he acknowledged that the scaffolding was to be used by the tilers who were to tile the balconies. He said that whilst the tilers were working, the painters could have painted the ceilings of the balconies because the balconies overhang each other.
25Asked by Mr Magee if it was possible that over time, Mr Galvez had convinced himself that in fact he had told the painters not to paint the balconies, his evidence was " I don't know how to answer that. It could it be. I am not saying that I did, but it could be that I have. But I still believe that I said no on that day." He denied that his evidence of the necessity to prepare and prime the balconies, including scraping and sanding them was an attempt to rationalise why his evidence at paragraph 28 of his statement of 1 June 2011 was correct. He accepted that as the supervisor, employees would normally do what he told them.
26Mr Galvez stated that whenever the painters were using ladders above two metres, they wore fall arrest harnesses. However, Mr Magee put to Mr Galvez that Mr Torres and Mr Asciutto stated that they and other painters had used ladders above two metres without wearing fall arrest harnesses. Mr Galvez said he had not seen that occur.
27Mr Galvez acknowledged that the documents annexed to his statement that related to the safe work method statements for Everest Contracting Pty Ltd related to work being undertaken by that company, which was not associated with the corporate defendant. He stated that the corporate defendant did not have a document for the Balmain Cove development work similar to the safe work method statement prepared by Everest Contracting. He agreed he did not have any involvement in the preparation of the document and although he and some of the employees of the corporate defendant had signed it, he accepted that the corporate defendant had not introduced a similar document for the Balmain Cove work. He further agreed that the Everest Contracting daily hazard assessment documentation was in a similar position. In addition, that document made no reference to working at heights from ladders and in respect of fall arrest or harness equipment, the box alongside the word "no" had been ticked.
28In cross-examination, Mr Galvez' evidence was that he told Constable Kelly of a conversation he had with the painters and what Constable Kelly had written in paragraph 6 of the statement he took from Mr Galvez was in place of that conversation.
29Mr Luitingh asked Mr Galvez, putting to one side the conflicting evidence contained in the statements made by Mr Galvez, to give evidence of what happened on the day of the incident in respect of his discussions with Mr Vega and Mr Acevedo. His evidence was as follows:
A. Okay. As I mentioned, like just kind leading to where the Gustavo was late, I spoke to Carlos. He told me to do certain things with other workers. I went downstairs to see them. On they way down there I saw that Ivan and Gus were painting things in a colour. I went up and spoke to them, confronted to them and told them off in Spanish. And in a, you know, swearing, saying, you know, you are doing it wrong. They had painted a whole lot of the works.
Q. Mr Galvez, would you describe what they had painted. And when you tell his Honour about the conversation don't summarize it. Tell him who said what on that date?
A. Okay.
Q. In the best recollection that you have?
A. Okay. They had painted the incorrect colour on the ground floor units. They had painted three or four units i the incorrect colour. I went to speak to them and told them , "You're fucking idiots. You painted the wrong colour. How can you get it wrong? You need to change the colour and you need to change the paint you are using and get the right colour and use it. Fix your fuckup." And then he, they, Ivan told me why don't we, instead of changing it, we're going to take too long to change the paint, having to go and paint, having to go and pick the paint out, get the new paint, clean all the tools, why don't we paint that the colour that I'm using, where, you know on the walls where it is supposed to be." And I said, "No." And I went off with Tom, which is the caretaker, went upstairs with him up the lifts to the top floor unit where we had to move the furniture. And then I got a phone call from Carlos saying to look down, something had happened. He sounded really shaky, really nervous, which is not like Carlos. And when I looked outside I saw, and I still see it to this day, Ivan's face looking up at me.
Q. Okay, we are concerned with the incident. Now Mr Galvez, Mr Magee correctly points out to you, and I am giving you an opportunity to deal with it, having regard to what you have just said?
A. Yes.
Q. In your statement at paragraph 28 when you have said that after that when the scaffolding was erected you were painting out the balcony. Now, Mr Magee has put to you that that that is an afterthought, because it doesn't appear in your other statements, and in fact you didn't mention it now when you gave evidence to his Honour. And Mr Magee has correctly put to you whether or not that is something that you think you might have said, or something which would you tell his Honour whether or not that conversation took place? Because we would like you to present yourself with the most accurate opportunity to give evidence of what has happened. Either that is correct or to it is incorrect. You had need to tell your Honour what the position is in relation to that?
A. I believe now that it is correct, or what I said on the time saying, you know, scaffolding to go up, I don't believe, I don't recall saying for them to do the works.
30Mr Galvez stated that the personal defendant and Mr Roberto Navarro, a painter employed by the corporate defendant on the day of the incident, were getting scaffolding off a van for it to be erected a couple of balconies from where Mr Vega was working.