Illawarra Hotel Company Pty Ltd v Walton Construction Pty Ltd
[2013] NSWCA 211
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2013-07-12
Before
Meagher JA, Barrett JA, Ward JA, Einstein J, McDougall J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Judgment 1THE COURT: There were two parties to these proceedings, both in this Court and in the court below. In the Equity Division, Walton Construction Pty Ltd ("Walton"), the builder, brought proceedings by summons against Illawarra Hotel Company Pty Ltd ("Illawarra"), the proprietor; and Illawarra, in turn, filed a cross-summons against Walton. In this Court, Illawarra was the appellant and Walton, as respondent, filed a notice of contention. 2In the proceedings below, there was a money judgment for Walton against Illawarra and a money judgment for Illawarra against Walton. Each judgment sum included an interest component. 3The substantive decision of this Court (Illawarra Hotel Company Pty Ltd v Walton Construction Pty Ltd [2013] NSWCA 6, 11 February 2013) was that Walton's judgment sum should be reduced and Illawarra's judgment sum should be increased. The adjustments were, by comparison with the judgment sums, modest adjustments. They reflected success by Illawarra on two particular issues, one concerning an allowance for margin on variations and the other as to the appropriate notional rental figure on which to calculate damages for 13 days delay in completion. Those issues were, in context, minor issues. The principal matter that occupied the attention of this Court was Illawarra's challenge (ultimately unsuccessful) to the rejection in the court below of Illawarra's claim for damages for 152 days delay in completion. 4Provision was made in the orders at first instance for set-off of the respective judgment sums. When the methodology of set-off directed by the orders below (including as to treatment of interest) is adopted and the adjustments resulting from this Court's decision are made, there is (a) a reduction of $58,945.86 from Walton's original judgment sum (which was $513,025.99), the deduction being $44,566.93 plus interest thereon of $14,378.93, and (b) an increase of $20,045 in Illawarra's judgment sum (which was $157,077.59), the increase being $14,400 plus interest thereon of $5,645; (c) a judgment sum of $454,080.13 payable by Illawarra to Walton; (d) a judgment sum of $177,122.59 payable by Walton to Illawarra; and (e) a balance, after set-off, of $276,957.54 payable by Illawarra to Walton. 5Interest, in these calculations, is up to the date of the original judgments. 6Each party obtained at first instance the benefit of a costs order against the other. It was ordered that Illawarra pay Walton's costs of the summons and that Walton pay Illawarra's costs of the cross-summons (limited, however, to the claim for defective or incomplete workmanship and that there otherwise be no order as to the costs of the cross-summons). 7These reasons are concerned with five matters consequent upon the Court's decision of 11 February 2013 or otherwise raised by the parties: (a) the form of the orders to be made to dispose of the appeal: (b) whether the costs orders made at first instance should be varied in light of the result on appeal; (c) whether s 100(4) of the Civil Procedure Act 2005 dictates some variation of the orders below as to pre-judgment interest; (d) whether Illawarra should have an order pursuant to s 101(4) of the Civil Procedure Act for interest on costs and disbursements it has paid; and (e) what orders should be made as to the costs of the appeal. 8In accordance with directions, the parties exchanged and filed written submissions on these matters on the basis that the Court would deal with the remaining issues on the papers.