Huxley Homes Pty Ltd v Alexander Augustyn and Rebecca Augustyn; Alexander Augustyn and Rebecca Augustyn v Huxley Homes Pty Ltd
[2015] NSWCATCD 17
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2014-12-17
Source
Original judgment source is linked above.
Judgment (14 paragraphs)
APPLICATION
- The builder's application (HB 13/16053) was lodged first in time on 19 March 2013 seeking orders for damages arising from the homeowners' alleged breach of a contract for residential building work entered into between the parties. The homeowners filed a cross application (HB 13/29645) on 30 May 2013 seeking orders in respect of allegedly defective work.
- The two applications were case managed by the Tribunal and proceeded to a number of directions hearings.
- On 15 October 2014 the Tribunal set the matter down for a one day conclave of experts on site on 31 October 2014, followed by a two day hearing on 16 and 17 December 2014 to determine any remaining issues in dispute.
ISSUES
- Pursuant to directions made by the Tribunal on 15 October 2014 the parties filed written submissions. As a result of those submissions, agreements reached by the experts in conclave and following discussion with counsel for the parties on the morning of 16 December 2014 the following matters were clarified. 1. The parties agreed that the builder owed the homeowners the sum of $26,985.00 in respect of agreed defects. To that sum it was agreed 15% for preliminaries, 20% for builder's margin and 10% for GST should be added. The total therefore agreed to be owed by the builder on account of defective work was $40,963.23. 2. The parties further agreed that the sum of $39,033.31 was owed to the builder by the homeowners and should be set-off against the total sum found to be owed to the homeowners. 3. The remaining issue in dispute was whether the builder is liable for the cost of rectification of mould in the building. The parties agreed that if liability was found the cost of rectifying the mould problem was $185,000.00. It was agreed that it was necessary to add to that sum preliminaries, builder's margin and GST, which resulted in the agreed sum in respect of remediation of mould in accordance with the scope of work suggested by Mr Lark, to be $280,830.00. 4. In addition the homeowners sought damages in the sum of $19,462.50 for supervision of the remedial work. That application was opposed by the builder. 5. The builder did not press the claim for a variation relating to air-conditioning grills or a claim for export of fill. The homeowners agreed that they did not press a claim for liquidated damages or for compensation in respect of rent.