(d) (i) Provided that completion is effected not
later than fourteen (14) days after the completion date, and in this respect time is of the essence, the total of the occupation fee paid by the Purchaser (and provided that the occupation fee is paid in accordance with the provisions of this Clause as and when it falls due by the Purchaser to the Vendor), shall be credited towards the balance of the purchase price payable on completion.
(ii) However, if completion of this Contract does not occur on or before fourteen (14) days after the completion date (and in this respect time is of the essence), then the total occupation fee paid by the Purchaser will be forfeited to the Vendor and no credit shall be given to the Purchaser whatsoever.
(iii) The Vendor shall not be entitled to forfeit the total occupation fee under clause 16(c)(ii) if completion does not occur on or before 14 days after the completion date as a direct or indirect result of any default or other act or omission on the part of the Vendor."
11 The parties are now in contest as to whether these clauses are still operative after the variation effected by the June 2010 agreement.
January 2008 to June 2010.
12 The vendor and purchaser had a troubled legal relationship from the first. During the two and a half years from the making of the contract in January 2008 through to the June 2010 agreement that varied it, Mr Hillam was alleged to have been in default in the payment of occupation fees. Leduva attempted several times in 2009 to terminate the January 2008 contract but later accepted payments of occupation fees. Mr Hillam says that Leduva agreed to extend the date for completion. The January 2009 completion date was not met and in August 2009 Leduva commenced the possession proceedings.
13 Mr Hillam's alleged non-payment and Leduva's attempts at termination continued. Although Mr Hillam says that the events of this period before the June 2010 agreement are irrelevant, they have nevertheless featured in the parties' arguments. It is difficult to make any findings on the contested versions of the facts during this time, because there has been very little examination of the competing versions in cross-examination. I have decided that is not necessary to determine these issues as they were all compromised in the making of the June 2010 agreement. But a short account of them is nevertheless useful.
14 Mr Hillam says that between 27 August 2007 and 1 May 2009 he paid a sum of $101,000 either in cash or by way of bank cheque on account of the continuing Special Condition 16 (a) occupation fees of $1000 per week. He says that he was up to date with these payments. Leduva's principal witness, Mr Amerr Taouk disputed that some of these payments had been made and further contended that in addition to the payments actually made Mr Hillam had provided a number of cheques that had been dishonoured. Mr Hillam did not admit that his cheques had been dishonoured.
15 Leduva twice issued notices to complete and then notices to terminate to Mr Hillam between January 2008 and the commencement of the possession proceedings in August 2009. These notices were issued after the passing of the contractual completion date of 8 January 2009. Leduva issued a 14 day notice to complete on 3 February 2009 and a notice of termination on 24 February 2009 after Mr Hillam neither completed nor paid the balance of the deposit of $73,000 by 17 February 2009. Mr Hillam contended that Leduva was not in a position to complete by reason of a defect in title. On 26 February 2009 Leduva accepted a payment of $9,000 from Mr Hillam on account of occupation fees. Then on 23 April 2009 Leduva issued another notice to complete followed by a notice of termination on 12 May 2009. Leduva accepted payments of occupation fees from Mr Hillam after this date.
16 Leduva commenced its proceedings for possession in August 2009. It alleged that it had terminated the January 2008 contract on account of Mr Hill's non-payment of occupation fees and his failure to complete the contract on 9 January 2009. Mr Hillam alleged in his defence that throughout the same period Leduva was not ready willing and able to complete the 8 January 2008 contract and consequently could not issue a notice to complete to Mr Hillam, because of a defect in title due to various flaws in the Alexandria apartment building. These flaws had by then been identified by building consultants and consulting engineers. Mr Hillam alleged that he was not obliged to settle until the defect in title was rectified.
17 After the commencement of the possession proceedings, according to Leduva, Mr Hillam again defaulted in payment of the occupation fee and in completing the contract for sale. Leduva issued a notice to complete on 22 October 2009. After a failure to complete on 9 November 2009, Leduva issued a notice of termination on 1 February 2010. There do not seem to have been any payments on account of occupation fees accepted by Leduva from Mr Hillam after 1 February 2010.
18 There was a vast gulf between the allegations on each side as to what had been paid on account of occupation fees. Leduva alleged that as at the date of statement of claim in the possession proceedings that 127.5 weeks occupation fees (amounting to $127,500) were due of which $56,500 had been received on account, leaving a balance due of $71,000. Mr Hillam was alleging that he had paid $101,000 over the shorter period from August to 2007 to May 2009.
19 The calculation of occupation fee payment figures on both sides is quite strange. Leduva's claim that 127.5 weeks had passed between 23 August 2007 and 12 August 2009 is obviously wrong. The period between these two dates is closer to 100 weeks. On the other hand Mr Hillam does not seem to be able to produce cash receipts for the cash payments that he alleges were made to Leduva. Moreover, if he had paid $101,000 during the period 27 August 2007 to 1 May 2009 he was about $13,000 or $14,000 ahead in his payments for that period.
The June 2010 variation agreement
20 The possession proceedings brought matters to a head. On 26 May 2010 Short Minutes of Order were filed in those proceedings. The May 2010 Short Minutes of Order included a consent judgment in Leduva's favour in the sum of $140,000 which it was agreed could be entered one year later on 29 May 2011 if that amount had not by then been paid. That consent judgment then became the subject of the June 2010 agreement, which was made on 28 June 2010 and entered as court orders on 30 June 2010.
21 The June 2010 agreement provided for a series of steps to cover most contingencies that might arise after attempts were made to complete the contract for sale. The June 2010 agreement sought to cover the possible scenarios whether the contract was completed or not. The terms included an escrow period after which the vendor Leduva would in certain circumstances be at liberty to enter judgment against Mr Hillam in accordance with the May 2010 Short Minutes of Order. The June 2010 agreement relevantly provided:
"BY CONSENT the Court orders that:
1. The proceedings be stood over to 30 July 2010 for directions; and
2. There be liberty to restore on 3 days notice.