Gujarat NRE Coke Limited v Coeclerici Asia
[2013] FCA 918
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2013-09-06
Before
Foster J, Katzmann J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Background facts 5 Gujarat NRE Coke Limited ("Gujarat Coke") is an Indian company and Arun Kumar Jagatramka its chairman and managing director. On 15 September 2011 Gujarat Coke entered into a contract with a Singaporean company - Coeclerici Asia (Pte) Ltd ("Coeclerici") - for the sale of metallurgical coke, a key ingredient in the production of steel ("the Purchase Agreement"). Under the terms of that agreement Coeclerici was required to make a pre-payment of USD10,000,000 and Gujarat was obliged to repay the money to Coeclerici if it did not fulfil its side of the bargain. The same day Mr Jagatramka signed a guarantee for the specified sums payable by Gujarat Coke under the Purchase Agreement. Both agreements were governed by English law and in the event of a dispute provided for arbitration by the London Maritime Arbitrators' Association in London ("LMAA"). 6 Coeclerici paid the USD10,000,000 but Gujarat Coke did not deliver the metallurgical coke within the contractual delivery period. In accordance with the terms of the Purchase Agreement Coeclerici demanded repayment. Gujarat Coke repaid only one-fifth of the amount that was due. Consequently, on 17 August 2012, Coeclerici commenced arbitration proceedings against the company and Mr Jagatramka (hereafter "the applicants") for the balance of USD8,000,000. 7 On 30 November 2012 the applicants filed a defence denying liability. The basis of the defence is obscure on the materials to which I was taken. It is, however, immaterial because on 17 January 2013 - four days before the hearing was due to start - the parties reached a settlement. The terms of the settlement were contained in a "Payment Agreement", signed by the parties' solicitors, which relevantly recited that the applicants: acknowledge and admit that the Principal Sum [the USD8,000,000] is due and payable to Coeclerici and which amount is final and is not subject to any set off, counterclaim or other deduction whatsoever… 8 The Payment Agreement imposed obligations on the applicants to make the payments, but provided for them to be paid in instalments. The first instalment was to be USD600,000. The Agreement required that it be paid within 15 days, that is, by 1 February 2013. The second instalment of USD3,000,000 was to be paid by 28 February 2013 and the final instalment of USD4,900,000 by 28 March 2013. The Payment Agreement also provided that the arbitration proceedings be suspended for as long as the applicants continued to perform their obligations under the agreement. In the event of default, the Agreement gave Coeclerici the right to resume the proceedings and/or to bring new proceedings. Importantly, if that were to occur cl 4 of the Payment Agreement stipulated that the applicants: [E]xpressly and irrevocably agree that Coeclerici will be entitled to an immediate consent award, without the need for any pleadings or hearings, for the following: (a) the Settlement Payments … less any sums paid after the date of this Payment Agreement; (b) all reasonable costs and expenses incurred after the date of default, including but not limited to legal costs, the costs of the Tribunal, arbitration costs and any legal or other costs and expenses incurred in enforcing this Payment Agreement and any costs and expenses incurred in obtaining such an award; and (c) interest at 7% from the date of default compounded quarterly until payment in full. 9 Clause 8 of the Payment Agreement stipulated that any dispute arising out of or in connection with it be referred to the arbitral tribunal. 10 The applicants failed to pay the sums due under the Payment Agreement in accordance with the payment schedule. Accordingly, on 4 February 2013 Coeclerici's solicitors sent an email to the tribunal asking it to proceed immediately to make an award in its favour in the terms set out in cl 4 of the Payment Agreement. 11 The tribunal then emailed the applicants' solicitor inviting him to indicate whether there was any reason why the tribunal should not now proceed as Coeclerici requested and, if so, to "make any such reason clear" by close of business the next day at the latest. The applicants' solicitor, William Chetwood of Bentleys, replied in emails dated 4 and 5 February 2013 that he was travelling, his clients were attending a conference in India and he was unable to take instructions. 12 On 6 February 2013 Coeclerici's solicitors pressed the tribunal to make the award, noting that no reason had been given for not doing so. Within the hour the tribunal said it would do as Coeclerici had requested. 13 At 10.06 pm on 6 February, Bentleys sent an email asserting that the applicants were not in breach of the Payment Agreement and the tribunal did not have the power to proceed to an award. They stated that the applicants had a right to present their case and were entitled to a reasonable time to properly develop their submissions. They accepted that the first payment due under the Agreement had not been made but contended that it was an implied term of the Payment Agreement that payment of the sums by the due date was conditional upon the Reserve Bank of India granting exchange control by the due dates. Alternatively, they submitted that if there were no such implied term, the applicants did not have the capacity to enter into the Agreement, "such capacity being a matter of Indian law". I interpolate that neither proposition was apparently advanced in relation to the Purchase Agreement. Bentleys invited the tribunal to confirm that it would not proceed to an award until the applicants had had "a reasonable opportunity to present their opposition". Coeclerici's solicitors replied the next day rejecting each of these contentions. The applicants' alternative submission was later abandoned. 14 There followed an exchange of correspondence with the tribunal. 15 By an email dated 12 February 2013 the tribunal informed the parties that it was proceeding to make its award. It said it had not ignored the applicants' protests. To the contrary, it stated, it had considered them very carefully. But it said it was satisfied that if additional time were extended to the applicants to substantiate the reasons given by their solicitors "the Payment Agreement itself and the circumstances in which it was concluded would still lead us inexorably to conclude that [Coeclerici is] entitled to the Award that [it] seek[s]". 16 Consequently, on 14 February 2013 - 10 days after Coeclerici had requested it to do so - the tribunal made its award. Without referring to the argument about the implied term, the tribunal determined that Coeclerici was entitled to rely on cl 4 of the Payment Agreement and to the relief specified in the agreement. It directed the applicants to pay the sums due under the Agreement. I should point out that at all relevant times the applicants have accepted that they are indebted to Coeclerici for the residue of the USD10,000,000. 17 In refusing to set aside the award HH Judge Mackie QC (in a passage adopted by the primary judge in his reasons) said (at [36]): The very able and courteous submissions of their Counsel should not be allowed to disguise the fact that the [applicants] have repeatedly, deplorably and without justification failed to pay money which is plainly due to [Coeclerici]. 18 In an affidavit filed in the enforcement proceeding Mr Jagatramka referred to the Indian Exchange Regulation (reg 16), which provides that where an exporter receives advance payment from a buyer outside India and the exporter is unable to make the shipment within a year of receipt of the payment "no remittance towards refund of unutilised portion of advance payment or towards payment of interest, shall be made after the expiry of the said period of one year, without the prior approval of the Reserve Bank". He stated that Gujarat had sought that approval and he expected that, upon its receipt, the company would be in a position to "make payment to Coeclerici". It seems that the first request was made in October 2012 but it was not until 10 July 2013 that an answer was forthcoming. 19 On 10 July 2013 the Reserve Bank of India wrote: We accord our approval for refund of balance amount of USD 8 million and liquidated damages of USD 0.75 million in lots depending on the cash flow, on or before October 31, 2013 by the captioned exporter to M/s Coeclerici Asia (Pte) Ltd, Singapore. 20 Since the date of this letter and after the primary judge had pronounced his final orders, the applicants paid a desultory USD200,000. The current amount owing under the judgment (costs of the enforcement proceedings aside) is USD8,604,336.42 and the costs of the English proceedings (including interest) of GBP12,232.85 together with interest, which has been running since 21 August 2013.