© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2023] NSWSC 729
Supreme Court of NSW
2023-05-11
Stevenson J
Original judgment source is linked above.
Solicitors: Tom Howard Legal (Plaintiff/Cross-Defendants) Armstrong Legal (Defendant/Cross-Claimant) File Number(s): 2020/220429
JUDGMENT
Decision
The incident involving the Court Interpreter
The Arrangement
The Further Arrangement
The variation and extension of time claims would be assessed at the end of the Project
That no liquidated damages would be levied by the Developer
That notice and time bar provisions under the Contract would be disregarded
Conclusion as to the Further Arrangement
Contract Claim Sum
Estoppel
Misleading or deceptive conduct
Causation
Alleged representation that Mr Guo had $6 million in equity funds
Alleged representation that Mr Guo would sell his assets to help finance the Project
Alleged representation that the Developer would pay the Builder for remediation works at the end of the Project
Alleged representation that the Project would be completed for $32.3 million
Alleged representation to the effect of the Further Arrangement
Conclusion as to the Builder's misleading or deceptive conduct case
The alleged loan for $600,000
The alleged loan for $151,157.40
The Developer's claim under the 22 March 2019 Handwritten Agreement
The Developer's claim under the Contract: the 10 June 2020 Final Payment Certificate
Mr Guo's purported appointment as the Principal's Representative under the Contract
Was the appointment of Mr Guo as Principal's Representative notified to the Builder?
Could Mr Guo be appointed as the Developer's Principal's Representative?
Did Mr Guo make any "assessment" of the Builder's Final Payment Claim?
Was the Final Payment Certificate issued to the Developer, as well as to the Builder, as required by clause 37.4(b)?
Did the Final Payment Certificate evidence "monies finally due and payable on any account whatsoever" as required by clause 37.4(b)?
Is the Final Payment Certificate void by reason of sections 12 and 34 of the Building and Construction Industry Security of Payment Act?
Variations and Quantum
Site remediation
Shoring piles - changes in scope and additional depth
Shoring piles - anchors - capping beam, additional carparking
Consultants' fees
Delay costs
Conclusion
Endnotes
Ganghui Pty Ltd
YTO Construction Pty Ltd
(1938) 60 CLR 336
(1937) 58 CLR 155
(1984) 2 FCR 82
(2019) 267 CLR 560
(1987) 162 CLR 221
[1938] HCA 34