(Skylight and roof tiles) of Joint expert report
- The builder seeks leave to appeal against the finding of $18,367.80 in favour of the owners on this item of their claim on the basis that the award was against the weight of evidence, and not fair and equitable having regard to [50] of the reasons.
- The builder correctly submitted that [50] of the reasons refers to an agreement between the joint experts that a structural engineer was to conduct an invasive inspection and determine cause and rectify as per structural engineer.
- There were six (6) matters referred to by the Senior Member at [50] of the decision, including those referred to by the builder. The six (6) matters were taken from the method of rectification agreed by the experts in the Conclave Joint Report which was before the Senior Member. The six matters agreed upon by the experts were:
1. Structural engineer to conduct invasive inspection including removal of roof tiles and ceiling sections as required;
2. structural engineer to determine the cause of the issues and provide a remedial design for the rectification of the roof and truss, if determined;
3. licensed builder to complete remediation works as specified by the structural engineer;
4. structural engineer to inspect completed works and issues certificate of adequacy
5. builder to repair sagging ceiling below; and
6. builder to makegood the entire affected area.
- The builder's submissions state that until the steps referred to in (1) and (2) were completed, the Tribunal would not be in a position to ascertain the rectification cost. On that basis it is said that the finding by the Senior Member that rectification damages of $18,367.80 were applicable was either against the weight of evidence or not fair and equitable.
- The Senior Member found that the owners' expert had provided a costing which he found to be reasonable and satisfactory. The owners' expert's costing was for the work referred to at 7.3 of his report being:
1. Strip all ceilings to family room and dispose of plasterboard;
2. Jack/ modify roof trusses into place to alleviate wavy roof tiles and sagging ceiling;
3. strengthen roof trusses around skylight openings;
4. strip roof tiles around skylight and raise skylight;
5. install new plasterboard ceilings including setting and sanding;
6. paint all ceilings as required; and
7. final clean and make good with allowances for skip bins and materials.
- As previously stated, the first hurdle for the builder in seeking leave to appeal in connection with the finding of $18,367.80 in favour of the owners on this item of their claim, is to establish that it may have suffered a substantial miscarriage of justice because the finding was against the weight of evidence and not fair and equitable. As stated the hallmark of a substantial miscarriage of justice is that there was "significant possibility" or a "chance which was fairly open" that a different and more favourable result would have been achieved for the builder had the finding not been against the weight of evidence or not fair and equitable.
- The Conclave Joint Report stated that the experts agreed that there were visible issues which required rectification as per the owners' expert's report. Once that is acknowledged, we find that it was inevitable that the builder would be responsible for rectification of defective work or the payment of rectification damages. The Senior Member exercised his discretion in favour of a money order, rather than a work order. Because of the admissions made by the builder's expert regarding the existence of defects, it was in our view almost certain that the builder would face liability of one type or another in connection with this item of the owners' claim.
- The guiding principle in s36(1) of the NCAT Act is to:
'facilitate the just, quick and cheap resolution of the real issues in the proceedings.'
- In circumstances where the experts had agreed that there were defects that required rectification as stated in the owner's expert's report, when the owner's expert had provided an estimation of the cost of the rectification work, but the builder's expert had not, when the rectification methodology agreed by the parties' experts in conclave had not been quantified, when the owners' expert's quantification traversed similar work as may have been expected to have arisen from an engineer's remedial design and when the Senior Member was obliged to implement the guiding principle referred to and was entitled to do the best that he could do to estimate the rectification cost, we are not persuaded that the builder may have suffered a substantial miscarriage of justice because the finding in favour of the owners was against the weight of evidence and not fair and equitable. In other words, because of the concession made by its expert, we find that it was inevitable that the builder would be liable to the owners and faced the possibility of an award of damages being made against it.
- Leave to appeal is refused.