Decision
36 In my opinion the primary judge was in error in relation to s.13 of the Act. I adhere to the view I expressed in Brodyn Pty. Limited v. Davenport [2004] NSWCA 394, (2004) 61 NSWLR 421, at [62]-[66], to the effect that after cessation of work there continue to be reference dates in respect of which successive payment claims can be made, up to the twelve month limit under s.13(4)(b), and that s.13(6) permits successive payment claims to be for the same work. Mr. Rudge SC for Equity did not seek to submit to the contrary, and accepted that there was a reference date at about the end of November 2004 in respect of which a further payment claim, claiming the same amount, could have been served.
37 However, for other reasons I consider that Falgat's estoppel case was very weak, so that the primary judge's error in this respect did not vitiate his decision.
38 In the first place, the representation relied on was an assertion in Mr. Hosken's affidavit of 12 November 2004 that the payment schedule had been served on 27 October 2004, a representation repeated by Equity's Counsel at the hearing before Naughton DCJ on 25 November 2004. However, this did not amount to an express representation that the payment schedule was not also served on a previous occasion; and there was no evidence of circumstances which would support a conclusion that there was an implied representation to that effect, and no evidence that anyone on behalf of Falgat understood such an implied representation to have been made.
39 It appears that both Falgat and Equity assumed at around this time that there were no breaches of time limits which could invalidate the adjudication application; but that does not amount to a representation by Equity to Falgat that there was no earlier service of the payment schedule, at least in the absence of evidence of understanding that an earlier service would have invalidated the application. The assumption could possibly support an estoppel by convention to the effect that the adjudication application was not invalidated by any breach of time limits; but Falgat is not seeking to rely on an estoppel to that effect, but rather to rely on an estoppel which would have the effect of establishing a breach of time limits which neither party at that time adverted to.
40 Falgat also sought to rely on representations by Equity's Counsel to the Court of Appeal to the effect that the adjudication application would continue if the injunction was discharged, which was reflected in the passage of Handley JA referred to in par.[14] above. However, this occurred after 5 December 2004, the last date for service of a fresh payment claim.
41 It appears that orders made by the Court of Appeal in favour of Falgat, dissolving an injunction and granting costs in its favour, were based on the common ground that the adjudication could be validly continued; and it may be that, although the decision was interlocutory in form, it was final in substance, so as to support an issue estoppel to this effect: Inasmuch Community Inc. v. Bright [2006] NSWCA 99 at [60]-[65]. However, Falgat did not seek to rely on any estoppel of this kind.
42 The second main reason why I regard Falgat's case in estoppel as very weak is the absence of evidence supporting detrimental reliance. Although evidence of what someone would have done in the past in different circumstances is hypothetical, such evidence is received and should normally be given; and in this particular case, having regard to the difficulty and complexity of the legislation, there was I think a need for someone on behalf of Falgat to give evidence to the effect that he or she appreciated at the time that, if the payment schedule had been received on 22 October 2004, the adjudication application would have been too late; and that, had there not been a representation that no payment schedule was served earlier than 27 October 2004 (or at least, if he or she had been aware of an allegation that a payment schedule was served on 22 October 2004), he or she would, notwithstanding that Falgat's instructions were that no payment schedule was received prior to 28 October 2004, have taken the precaution of serving another payment schedule prior to 5 December 2004.
43 During oral argument, I expressed the view that Falgat faced the further difficulty that, on its own assertion that the payment schedule was received on 28 October 2004, the adjudication application was invalid. That was a view expressed by Mr. Finnane as one of his reasons for refusing to go ahead with the adjudication application.
44 On further reflection, I am not certain that this is correct. Where a respondent does not provide a payment schedule within the time limited by s.14(4) of the Act, s.15(2) states that a claimant may make an adjudication application under s.17(1)(b); but s.15(2) does not explicitly exclude the possibility of an adjudication application being made under s.17(1)(a). Under s.17(1)(a), a claimant may make an adjudication application if the respondent provides "a payment schedule under this Division" and if other requirements are met; but s.17(1)(a) does not require that the payment schedule was provided within time. If a payment schedule is provided in circumstances where there is doubt as to whether or not it is provided in time, I am inclined to the view that a claimant may be able to make an application pursuant to s.17(1)(a): it would not make sense for s.17(1)(b) and s.17(2) to apply in those circumstances, because these provisions are plainly directed to giving the respondent a further opportunity to provide a payment schedule that has not yet been provided.
45 If that analysis is correct, Mr. Finnane was in error in refusing to proceed. If the payment schedule was received for the first time on 28 October 2004, an application could have been made under s.17(1)(a). Any dispute as to whether the payment schedule was also received on 22 October 2004 could have been determined by the adjudicator; and it may be that an estoppel arising out of the Court of Appeal proceedings would have supported validity in any event. As noted earlier, this approach was not at the time pressed by Falgat.
46 In any event, for the two reasons I have given, I think Falgat's case in estoppel in these proceedings was very weak. My analysis also confirms that substantial further evidence and argument would have been required. In my opinion, having regard to the prejudice to Equity that this would have involved, and the lateness of the application, the application was correctly refused.
TIME OF PROVISION OF THE PAYMENT SCHEDULE
47 On the basis of the factual findings set out above, the primary judge held:
(1) The word 'provide' in s.14 of the Act meant the same as 'serve';
(2) It is not necessary that a payment schedule be personally served;
(3) The payment schedule was lodged at Falgat's ordinary place of business during normal office hours (within s.31(1)(b) of the Act) on 22 October 2004 and thus was provided on that date;
(4) The payment schedule was also deemed to be received on 27 October 2004, being 3 days after posting to Falgat's address, this being the effect of cl.29 of the construction contract, which in turn was adopted by s.31(1)(e) of the Act;
(5) The payment schedule was served in accordance with s.109X of the Corporations Act 2001 by being left at Falgat's registered office on 22 October 2004, in terms of s.31(3) of the Act;
(6) The payment schedule was served in accordance with s.109X of the Corporations Act 2001 and s.29 of the Acts Interpretation Act 1901 by post on 25 October 2004; and this was not affected by s.160 of the Evidence Act 1995.
Submissions
48 Ms. Culkoff submitted that the Act required that a payment schedule actually be received by a claimant, before it could be said that the respondent had provided the payment schedule; and that this required personal service on a natural person, and required that the payment schedule come into the hands of some person on behalf of a corporation. Ms. Culkoff referred to Pacific General Securities Limited v. Soliman & Sons Pty. Limited [2005] NSWCA 378 at [27], Taylor Projects Group Pty. Limited v. Brick Department Pty. Limited [2005] NSWSC 439 at [18], and Emag Constructions Pty. Limited v. Highrise Concrete Contractors (Australia) Pty. Limited [2003] NSWSC 903 at [56].
49 Ms. Culkoff submitted that the use of the words "provide" and "receive" showed that, in relation to documents going from a respondent to a claimant, there was a more onerous responsibility placed than in relation to documents going from a claimant to a respondent, which merely had to be served. The use of different words "provide" and "serve" suggested different meanings: The Guardian of the Parish of Brighton v. The Guardians of Strand Union [1891] 2 QB 156 at 167. She submitted that the use of the word "provide" suggested that the document in question must actually come to the notice of the person to whom it is to be provided: Nair v. Minister for Immigration & Multicultural Affairs [2000] FCA 1305 at [67]-[72].
50 Accordingly, Ms. Culkoff submitted, s.31 of the Act did not apply in the case of "provision" of a payment schedule; and thus there was no basis for applying cl.29 of the construction contract. She submitted also that s.109X of the Corporations Act did not apply to provision as opposed to service; and that even if s.109X of the Corporations Act did apply, Falgat's proof that the notice was not received until 28 October 2004 displaced the presumption in s.29 of the Acts Interpretation Act.