should costs follow the event
4 Paragraphs [1]-[18] of my earlier reasons for judgment set out by way of introduction the nature of the proceeding, the claims made in the proceeding and the way in which I resolved each of the issues in contest. For the purposes of dealing with the question of costs, it is sufficient for me to observe that whilst by its Further Amended Statement of Claim, F5 made a number of claims against M2006 (including for breach of the Trade Practices Act 1974 (Cth), collateral warranties and estoppels), F5 only pressed its contractual claim at trial. Claims brought by F5 against the second and third respondents were dismissed by consent in the course of the trial.
5 F5's contractual claim was that; firstly, by reason of the breach of what (in my earlier reasons) I called the "concessionaire as manufacturer clause"; and secondly, M2006's repudiation of the contract, F5 suffered loss and damage.
6 In relation to that claim, the Court had to determine a number of issues. Principally, those issues were as follows:
(a) Had the parties made a concluded and binding agreement?
(b) What were the terms of the concessionaire as manufacturer clause?
(c) Was the concessionaire as manufacturer clause breached by M2006?
(d) If a contract was made, was it repudiated by F5 and validly terminated by M2006?
(e) If a contract was made, was the contract repudiated by M2006 and validly terminated by F5?
7 Although F5 succeeded in persuading me that a concluded and binding agreement had been made by the parties, it failed in its claim that it was entitled to damages. F5's case based on breach of contract, was reliant on F5 succeeding on the construction of the concessionaire as manufacturer clause for which it contended. F5 failed on that construction issue and therefore I rejected its case of breach of contract. F5 also failed in its claim for damages based upon the repudiation of the contract by M2006. It failed in that respect because of my findings that: firstly, it was not ready and willing to perform the contract; and secondly, because it had not accepted the repudiation by M2006. F5 was thus not entitled to claim damages. I also found that, in the circumstances, the contract between F5 and M2006 had been abandoned by mutual consensus.
8 F5 failed in its claim for damages and its application was dismissed. F5 was wholly unsuccessful in respect of the claims that it made.
9 Despite that, F5 argues that the usual order, that the successful parties should be awarded its costs, should not be made. It contends that should be so because F5 was successful on what it characterises as the 'principal issues', namely, whether a contract was concluded and whether M2006 had repudiated that contract. F5 contends that it should be awarded its costs of dealing with these principal issues or, in the alternative, that the costs awarded to M2006 should not extend to the costs of defending these issues.
10 Further, F5 contends that M2006 failed to have the Court accept the interpretation of the concessionaire as manufacturer clause for which it contended. F5 further says that M2006 did not plead that the contract was abandoned and that issue was first raised in M2006's closing submissions. F5 contends in relation to those two matters (which it calls the 'subsidiary issues') that any costs awarded to M2006 should be reduced by an appropriate percentage.
11 M2006 contends that the circumstances of the proceeding do not justify departure from the usual order. It says that the applicant has not shown any special circumstances of the kind that will justify departure from the usual order that costs follow the event.
12 Section 43(2) of the Federal Court of Australia Act 1976 (Cth) ("the Federal Court Act") confers upon the Court a wide discretion in relation to costs. That discretion must be exercised judicially.
13 In Cadbury Schweppes Pty Ltd v Darrell Lea Chocolate Shops Pty Ltd (No 3) [2007] FCAFC 119, Black CJ, Emmett and Middleton JJ said at [11]:
The usual practice is that costs follow the event and that the Court will order the recovery of costs by the successful party on a party-party basis but success or failure on separate issues may lead the court to engage in a process of apportionment: see Dodds Family Investments Pty Ltd (formerly Solar Tint Pty Ltd) v Lane Industries Pty Ltd (1993) 26 IPR 261.
14 In Dodds Family Investments Pty Ltd (formerly Solar Tint Pty Ltd) v Lane Industries Pty Ltd (1993) 26 IPR 261 at 271-272, Gummow, French and Hill JJ said in relation to the general discretion conferred by s 43(2) of the Federal Court Act that:
Considerations relevant to the exercise of that discretion were enunciated by Toohey J in Hughes v Western Australian Cricket Association (Inc) (1986) 8 ATPR 40-748 at 48,136:
1. Ordinarily, costs follow the event and a successful litigant receives his costs in the absence of special circumstances justifying some other order …
2. Where a litigant has succeeded only upon a portion of his claim, the circumstances may make it reasonable that he bear the expense of litigating that portion upon which it has failed …
3. A successful party who has failed on certain issues may not only be deprived of the costs of those issues but may be ordered as well to pay the other party's costs of them. In this sense, ``issue'' does not mean a precise issue in the technical pleading sense but any disputed question of fact or of law …
The propositions enunciated in that case are subject to the further consideration that justice may not be served if parties are dissuaded by the risk of costs from canvassing all issues which might be material to the decision in the case: Cretazzo v Lombardi (1975) 13 SASR 4 at 12. In Trade Practices Commission v Nicholas Enterprises Pty Ltd (No 3) (1979) 42 FLR 213; 28 ALR 201, Fisher J regarded the discretion to apportion costs as one to be exercised only in the most exceptional circumstances. Nevertheless he accepted that where a considerable part of the trial is taken up in determining issues upon which a party fails, it is a proper exercise of the discretion to reduce the costs allowed to that party. Generally speaking, and notwithstanding the considerations referred to by Toohey J and the other authorities mentioned above, the demands of the community for greater economy and efficiency in the conduct of litigation may properly be reflected in a qualification of the presumption that a successful party is entitled to all its costs. In Commissioner of Australian Federal Police v Razzi (No 2) (1991) 101 ALR 425 at 430, Wilcox J, after referring to the importance of the general principle enunciated by Toohey J, said:
But I do not think that courts should be reluctant to recognise the existence of exceptional cases. In these days of extensive court delays and high legal costs the courts should use all proper means to encourage parties to consider carefully what matters they will put in issue in their litigation. If parties come to realise that they will not necessarily recover the whole of their costs, even though they have unsuccessfully raised a discrete issue, they are likely better to consider whether the raising of that issue is a justifiable course to take.
Where there is a mixed outcome in proceedings, the question of apportionment is very much a matter of discretion for the trial judge. Mathematical precision is illusory and the exercise of the discretion will often depend upon matters of impression and evaluation.
15 In my view, the circumstances raised by F5 do not justify departure from the usual rule that a successful party is entitled to all of its costs. What F5 has identified as the 'principal issues' were each issues which raised an element of the contractual cause of action that ultimately F5 failed upon. This was not a case in which a successful party succeeded on some of its claims but failed on others. M2006 was wholly successful in having the Court dismiss the contractual claim made by F5. Whether there was a concluded contract and whether that contract had been repudiated by M2006 were two of the necessary elements that F5 needed to succeed on in order to succeed in its claim for damages. There were other elements in that cause of action upon which it failed. There was nothing unreasonable or unjustifiable in M2006 contesting the fact that those two particular elements of the cause of action were not made out. Each of the issues was material to the decision in the case. Each was an essential element in the cause of action which F5 had to establish.
16 F5 has failed to point to any special circumstances that would warrant departure from the rule that ordinarily costs follows the event.
17 As to the reliance by F5 on what it called the 'subsidiary issues', I am not persuaded that either of those issues warrants a departure from the usual order as to costs. It is correct that the Court ultimately adopted a construction of the concessionaire as manufacturer clause that neither party had contended for. The construction adopted was closer to that contended for by M2006 than it was to that contended for by F5. However, I need place no reliance on that fact. F5's contention is that there should be some discounting of the costs awarded to M2006 simply because M2006's construction of the clause was not accepted. That contention is without merit. Whilst the construction that M2006 contended for was not adopted, what was crucial to the outcome of the case was the fact that the construction for which F5 contended was successfully resisted by M2006. The failure by F5 to persuade the Court to adopt its construction was crucial to F5's failure to make out a breach of the contract and thus its claim for damages flowing from the breach. That failure was also important to my conclusion that F5 was not ready, willing and able to perform the contract and was thus disentitled to seek damages flowing from the repudiation by M2006.
18 The issue as to whether or not the contract had been abandoned by F5 and M2006 occupied a very small part of the conduct of the proceeding. In the absence of a finding that the contract was abandoned, the outcome of the case would have been no different. F5 failed on its claim for damages flowing from the breach of contract because it failed to establish a breach. It failed on its claim for damages flowing from the repudiation by M2006 because it failed to establish that it was ready, willing and able to perform the contract and thus entitled to claim damages.
19 For those reasons, the suggestion in F5's submission that M2006's success in the proceeding is based on an issue that it had not pleaded is misconceived. Further and in any event, even if it be the case that abandonment of the contract had not been pleaded, that issue was clearly "in the ring": Nescor Industries Group Pty Ltd v MIBA Pty Ltd (1997) 150 ALR 633 at 640, 647 and 650 and Ward Group Pty Ltd v Brodi and Stone Plc [2005] FCA 471 at [64].