77 In considering whether the Council's termination on 3 October 2005 was effective, even in the absence of any obligation on the part of Exhibition Marketing to carry out the drainage works, I was referred to the proposition found in Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR 359, and relied upon in Honner v Ashton (1979) 1 BPR 9478, that termination based upon an invalid ground will not necessarily be ineffective, if a valid ground of termination exists.
78 I note that there is some question as to whether or not this extends to a valid ground of termination of which the terminating party was aware, but on which the terminating party chose not to rely (see Seddon and Ellinghaus, Cheshire and Fifoot's Law of Contract 9th Aust Ed at [21.24]). This issue was not raised before me in argument. Even if I were to take the principle at its most favourable to the Council (and as it is expressly put in the judgment of Dixon J in Shepherd), namely that a terminating party that has purported to terminate upon an invalid ground of termination may nevertheless rely upon a valid ground of termination whether or not it was aware of it, I am not satisfied for the reasons set out below that there was another valid ground for termination as at 6 July 2007.
79 Reliance was placed by the Council on Aberfoyle Plantations Limited v Khan Bian Cheng [1960] AC 115; Suttor v Gundowda Pty Limited (1950) 81 CLR 418 and Gilbert v Healey Investment Pty Limited [1975] 1 NSWLR 650 for the proposition that where, as here, a contract was subject to a condition subsequent (namely registration of the easement) being satisfied within a specified time; that time being of the essence; and that condition was not satisfied within the specific time, then the Contract is voidable at the election of the party who has the benefit of the condition.
80 Special Condition 7 required that the easement be registered "within three months of the Contract, and prior to completion". Time was clearly of the essence in this regard: (Special Condition 12).
81 The Council contends that the Contract was therefore voidable as at the date three months from entry into the Contract (namely by about early December 2004) and that at all times since then (or at least up to and including 31 October 2005 when the Council notified Exhibition Marketing of a period of nine months to carry out the drainage works) the Council had a right to terminate or rescind the Contract for breach of Special Condition 7 (by reason of the failure of Exhibition Marketing to register an easement in a form acceptable to the Council by then). The Council says there was no contract capable of being completed unless and until that condition had been fulfilled.
82 The Council contends that the giving by it (in October 2005) of an extension of time for performance for a specified period, coupled with a warning that failure to perform within the extended time will lead to termination, involved no election to continue performance unless there was actual performance by Exhibition Marketing - relying on Barclay v Messenger (1874) 30 LT 351; Tropical Traders Limited v Goonan (1963-1964) 111 CLR 41, and therefore that it was entitled, as at 3 October 2006 to terminate the Contract for breach of that Special Condition 7.1 (or to rescind what was, by reason of the failure to satisfy that condition, a voidable contract).
83 In Tropical Traders Limited v Goonan where the grant of an extension of time was said, far from constituting an election to affirm the Contract, to be an announcement of an intention to refrain from electing either way, Kitto J said (at 55):
Any act done by it and consistent only with the continuance of the contract on foot the law would hold to constitute an election against rescinding; and an election once made could not be retracted. But the appellant was not bound to elect at once. It might keep the question open, so long as it did nothing to affirm the contract and so long as the respondents' position was not prejudiced in consequence of the delay.
84 Reference was made to Kilmer v British Columbia Orchard Lands Limited [1913] AC 319 for the proposition that a stipulation making time of the essence may be rendered no longer applicable by the grant of an extension of time in particular circumstances but it was said this is not authority for the more general proposition that every grant of an extension of time deprives such a stipulation of effect for the future. In Barclay v Messenger Jessell MR held that a mere extension of time and nothing more is only a waiver to the extent of substituting the extended time for the original time, and not an utter destruction of the essential character of the time.
85 However, in April 2005 the Council called for immediate settlement of the Contract by Exhibition Marketing. At that point there would seem to have been a clear affirmation of the Contract, by the Council calling for settlement (at a time when there was, on the Council's case, a clear right of termination).
86 The fact that the Council did not insist on immediate settlement (accepting, it would seem, that settlement was not due until registration of the easement) does not seem to me to detract from that affirmation. Thereafter, the Council and Exhibition Marketing continued on the basis that the Contract was on foot and that each was bound by its obligations thereunder (whatever they may have been). This is not a case where the Council, face with a right of termination for failure of a condition subsequent, simply gave an extension of time for performance of the Contract or did nothing one way or the other by way of election.
87 In my view the relevant affirming conduct was not the extension of time from October 2005 but the conduct of the Council at an earlier point, namely at the expiry of the initial three month period. At that point the Council had an election between two inconsistent rights, to rescind or to affirm the Contract. It did not rescind. Its actions were consistent only with an affirmation of the Contract. The circumstances of any subsequent extension of time go not to the question of waiver of the initial right of termination or rescission but to whether or not, by its conduct, the Council had adequately put Exhibition Marketing on notice that time was again being made of the essence.
88 Accordingly, in my view the Council could not terminate for failure to register the easement without first having again made time of the essence in relation to registration. It would have been necessary for the Council to send a notice allowing Exhibition Marketing a reasonable time to register the easement (during which time the Council would have been obliged to cooperate with Exhibition Marketing to allow it the opportunity to satisfy that condition). This seems to have been what was contemplated when the Council issued its letter of 19 April 2005.
89 What would be reasonable for the purposes would be a time calculated by reference to the tasks which were to be carried out in order to finalise the easement. Moreover, to the extent that registration of an easement would be dependent upon consent from the Council, Council would not be able unreasonably to hinder or obstruct that process.
90 However, when notice was in fact given, in October 2005, it was, instead, a notice expressly requiring Exhibition Marketing to carry out obligations which (under the Contract) Exhibition Marketing did not have. The notice that was given in October 2005 was a notice to require that drainage works be carried out. No reference was made in that notice to the requirement to register the easement. I do not accept that by that notice time was made of the essence in relation to the registration of the easement; nor was Exhibition Marketing on notice of the Council's intention to terminate if the easement was not registered by then.
91 Even if the 31 October 2005 notice (or the earlier April 2005 letter) might otherwise have been construed as a notice for Exhibition Marketing to do whatever was necessary to satisfy Special Condition 7.1 (including registration of the easement), the fact that over the period from April 2005 onwards the Council continued to place insistence on completion of the drainage works (and thereby might be said to have represented that no easement would be accepted unless and until those drainage works were completed or that it reserved a right still to terminate irrespective of any acceptable easement if by the expiry of nine months the drainage works were not complete) in my view would preclude Council from now seeking to rely solely on the non-registration of the easement as justifying termination.
92 Exhibition Marketing further contends that the Council cannot rely upon the failure to register the easement within the three month period specified (or indeed to date) because it says the Council is in breach of the obligation contained in standard clause 29.4, or an implied obligation to the same or similar effect, to cooperate with Exhibition Marketing in relation to the finalisation of an acceptable easement to the Council.
93 I was taken to standard clause 29 (which applies if the Contract or completion is conditional on an event) which provides, relevantly, that if anything is necessary to make the event happen, each party must do whatever is reasonably necessary to cause the event to happen (cl. 29.4) and that a party can rescind under clause 29 only if the party has substantially complied with clause 29.4 (cl. 29.5).
94 Even if clause 29.4, which on its face seems applicable to the current situation did not apply, the Council would have an implied obligation to cooperate (or at least not to hinder) the attempts of Exhibition Marketing in relation to the preparation and registration of an acceptable easement over the area to be occupied by the reshaped channel. Where something has to be done under the Contract which requires cooperation between the parties, one party may be in breach of a term of the Contract if it does not cooperate accordingly: Electronic Industries Limited v David Jones Limited (1954) 91 CLR 288.
95 Did the Council comply with that obligation?
96 While submissions were made by Exhibition Marketing as to the Council not being able simply to reject everything put to it (reference being made to Chopard v Vamiso (1998) 9 BPR 16,813), it nevertheless did not suggest that the Council had been unreasonable in not accepting what had been put to it to date.
97 There was some suggestion that the Council may have been reluctant to enter into the transaction in the first place, preferring to leave the channel as it was - from which one might speculate that the Council would not have been sorry if it had an opportunity validly to terminate the Contract for failure to construct the drainage works. However, that is not to the point.
98 The evidence before me does not support the contention that the Council, at least from the time it engaged in debate with Exhibition Marketing or its engineers as to what was required by way of easement, was in breach of the obligation of cooperation. (It would, in my view, have been in breach of that obligation if its sole reason for rejecting or refusing to consider an easement proffered to it was that the drainage works had not been carried out; or if it imposed as a condition of any approval of the easement, a requirement that the drainage works first be carried out.)
99 In circumstances where Exhibition Marketing was seeking at the time to finalise easement plans with the Council, what it now says is that the Council was not in a position as at 3 October 2006 to terminate based on failure as at December 2004 to conduct the drainage works (which I accept) and that the Council cannot now terminate relying on breach of Special Condition 7.1 without at least allowing a further reasonable time for registration of the easement and complying with its express or implied obligations in that regard (which I also accept).
Repudiation
100 Was there nevertheless a repudiation by Exhibition Marketing which, irrespective of the essentiality or otherwise of the obligation under Special Condition 7.1, as at 3 October 2006, allowed the Council to terminate at that date?
101 The Council placed reliance on the judgment of McLelland J in The Millstream Pty Limited v Shultz [1980] 1 NSWLR 547 where his Honour referred to Ogle v Comboyuro Investments Pty Limited (1976) 136 CLR 444 as a case in which Barwick CJ considered that where there was only one actual breach of the contract there might nevertheless be successive repudiations of the contract by failure to make good that breach. McLelland J said (at 555):
It is established that such a breach as is constituted by a failure to deliver goods under a contract of sale (or by a failure to complete a contract for the sale and purchase of land) is a discrete and not a continuing or recurrent breach. In the words of Dixon J in Larking v Great Western (Nepean) Gravel Ltd (In Liq) , (approved by all members of the Court in Carr v J A Berriman Pty Ltd ): "If a covenantor undertakes that he will do a definite act and omits to do it within the time allowed for the purpose, he has broken his covenant finally and his continued failure to do the act is nothing but a failure to remedy his past breach and not the commission of any further breach of his covenant."
But, as the decision in Carr v J A Berriman Pty Ltd demonstrates, the "once and for all" quality of a breach of this kind is not inconsistent with the existence of a continuing or recurrent repudiation of the Contract following upon that breach, evidenced by a long continued failure to remedy the breach, or by an express or implied disclaimer of intention to do so.
102 In The Millstream, as long as the contract continued unterminated the defendant was at liberty to remedy the relevant breach. However, prior to so doing the plaintiff made an election to terminate the contract. It was held that the plaintiff was entitled to make such an election (notwithstanding an earlier election to affirm the contract) because since that earlier election the defendant's continuing conduct in denying the existence of a contract as alleged by the plaintiff and the lengthy duration of his failure to perform gave rise to a fresh right of election - there referring to Carr v J A Berriman (1953) 89 CLR 327.
103 In Carr v J A Berriman it was said that a second breach could be taken into account together with an earlier breach, notwithstanding an affirmation of the contract in the interim. It was held that an election not to rescind for failure to deliver on the due date could not deprive that failure of all significance and therefore when a second breach occurred the two combined might have a significance which it might not be legitimate to attached to the first alone.
104 I was referred to Koompahtoo Local Aboriginal Land Council v Sanpine Pty Limited [2007] 233 CLR 115. There, the majority in the High Court said:
The term repudiation is used in different senses. First, it may refer to conduct which evinces an unwillingness or an inability to render substantial performance of the contract. This is sometimes described as conduct of a party which evinces an intention no longer to be bound by the contract or to fulfil it only in a manner substantially inconsistent with the party's obligations. It may be termed renunciation. The test is whether the conduct of one party is such as to convey to a reasonable person, in the situation of the other party, renunciation either of the contract as a whole or of a fundamental obligation under it. (In this case, we are not concerned with the issues that arise where the alleged repudiation takes the form of asserting an erroneous interpretation of the contract. Nor are we concerned with questions of inability as distinct from unwillingness.) Secondly, it may refer to any breach of contract which justifies termination by the other party. It will be necessary to return to the matter of classifying such breaches. Campbell J said this was the sense in which he would use the word "repudiation" in his reasons. There may be cases where a failure to perform, even if not a breach of an essential term (as to which more will be said), manifests unwillingness or inability to perform in such circumstances that the other party is entitled to conclude that the contract will not be performed substantially according to its requirements. This overlapping between renunciation and failure of performance may appear conceptually untidy, but unwillingness or inability to perform a contract often is manifested most clearly by the conduct of a party when the time for performance arrives. In contractual renunciation, actions may speak louder than words.
105 I am unable to reach the conclusion that Exhibition Marketing's conduct has been such as to evince an intention no longer to be bound or not to perform its obligations under the Contract (or to perform only in a manner substantially inconsistent therewith).
106 In this regard, it would seem from the evidence before me that there have been a number of meetings and discussions between Exhibition Marketing's engineers and representatives of the Council in which plans have been drawn up, after consultation with the Council, to reflect what Exhibition Marketing's engineers believed (wrongly or otherwise) the Council wanted. The fact that Exhibition Marketing submitted plans which were at variance from the plans drawn up in 2004 does not suggest an unwillingness to comply with the Contract. It is, rather, suggestive of further consideration having been given to how the easement might (more favourably perhaps) better be drawn. Once the Council rejected it, Exhibition Marketing sought to ascertain just what was required by the Council. Exhibition Marketing has at all times professed its willingness to comply with the obligation to grant an easement. It has simply refused to perform an obligation which, on the proper construction I have found of the Contract, it does not have.
107 Accordingly, the delay since September 2004 in registration of the easement does not evince an intention by Exhibition Marketing not to be bound by or honour the Contract. (The Council's wrongful insistence on carriage of the drainage works might itself be seen as a repudiation or renunciation by it of the Contract, but it is open to Exhibition Marketing not to accept that and to call instead for the Contract to be performed, as it has).
Relief
108 The summons seeks an order that the Council specifically perform and carry into execution the Contract; in essence an order directing the Council to perform its obligations under the Contract in accordance with its terms.
109 Specific performance in the traditional sense would be an order requiring execution of the Contract. I apprehend that what is sought in this instance is specific performance in the nature of a mandatory injunction to oblige Council to comply with its obligations under the Contract and to carry the Contract into effect.
110 I do not understand Exhibition Marketing to be asking for an order that Council now complete the Contract in the absence of registration of the easement required under Special Condition 7. What I understand Exhibition Marketing to be seeking is an order which would, in effect, compel Council to comply with its obligations under clause 29.4, or alternatively under the implied obligation arising out of Special Condition 7, to cooperate with Exhibition Marketing in relation to the substance of the easement to be granted.
111 In the circumstances I am concerned that such an order may give the parties insufficient definition as to what must be done in order to comply with the order of the court. In Tito v Waddell (No 2) [1977] Ch 16 at 321-2 it was said that:
In cases of this kind it was at one time said that an order for specific performance of the Contract would not be made if there would be difficulty in the court supervising its execution … the real question is whether there is a sufficient definition of what has to be done in order to comply with the order of the court. That definition may be provided by the Contract itself, or it may be supplied in the term of the order, in which case there is the further question whether the court considers that the terms of the Contract sufficiently support, by implication or otherwise, the terms of the proposed order.
112 In Posner v Scott-Lewis [1987] Ch 25; Lord Hoffmann said, referring to Lord Wilberforce in Shiloh Spenders v Harding [1973] AC 691 at 724:
Lord Wilberforce was in my view drawing attention to the fact the collection of reasons which the courts have in mind when they speak of difficulty of supervision apply with much greater force to orders for specific performance, giving rise to the possibility of a committal for contempt, than they do to conditions for relief against forfeiture. While the paradigm case to which such objections apply is to carry on activity, they could also apply to an order requiring the achievement of a result.
113 In Patrick Stevedores Operations No 2 Pty Limited v Maritime Union of Australia (1998) 195 CLR 1 at 78 the court considered that there was no defect in the orders there sought of the kind "sometimes … expressed as the involvement of the court in 'constant supervision' of continued conduct". There the majority said:
The House of Lords [in Co-operative Insurance Society Ltd v Argyll Stores (Holdings) Ltd ] discharged the order for specific performance which the Court of Appeal had made. The significance of Lord Hoffmann's speech for present purposes is not the rejection of the lessor's submissions. That rejection, with respect, was virtually inevitable. What is significant is the acceptance by the House of Lords that the concept of "constant supervision by the court" by itself is no longer an effective or useful criterion for refusing a decree of specific performance. Rather, Lord Hoffmann placed stress on other propositions. First, a person who is subject to a mandatory order attended by contempt sanction (which "must realistically be seen as criminal in nature") ought to know with precision what is required; and, second, the possibility of "repeated applications for rulings on compliance" with orders requiring a party "to carry on an activity, such as running a business over a more or less extended period of time" should be discouraged.
114 In the present case, there may well be an issue as to what the Council has to do (the Contract remaining on foot) in relation to the consideration of any easement subsequently proffered to it by Exhibition Marketing. I do not consider it appropriate to make orders in effect requiring The Council to "cooperate" in negotiations for an easement nor can I order the Council to agree to a particular form of easement. (It would be a different matter if Council were in due course to reject an easement and there was an issue as to whether it had done so acting reasonably).
115 The Council should not be in a position where it is unclear what conduct might constitute contempt of any order made against it.
116 In those circumstances, therefore, I am not prepared to grant an order that the Council specifically perform and carry into execution the Contract because it is not clear to me that the parties would know precisely what the Council was required to do in order to comply with such an order. Nor do I think such and order is the minimum equity necessary to do justice in this matter.
117 I think it is appropriate in this case to grant declaratory relief namely to declare that the purported notice of termination by Council was not valid and that the Contract remains on foot and the parties remain bound by their obligations under the Contract as properly construed. Those obligations, as I have earlier indicated, do not include an obligation on the part of Exhibition Marketing to carry out the drainage works prior to completion of the Contract.
118 If the Council now wishes to make time of the essence again in relation to the obligation contained in Special Condition 7 it is open to it to serve an appropriate notice to perform. It would need to allow reasonable time for Exhibition Marketing to effect the registration of the easement and during that time the Council would in my view have an obligation to assist and cooperate with Exhibition Marketing in order to enable it to satisfy that condition by way of an agreement on terms of an easement which were reasonably acceptable to the Council.
119 It was submitted by the Council that it was not open to me to grant declaratory relief of the kind because it had not expressly been sought by Exhibition Marketing and that if I were of the view that the notice of termination was invalid and ineffective to terminate the Contract then I should simply dismiss the summons because no other relief had been sought. I do not think it is appropriate for me to follow this course.
120 I note that Exhibition Marketing did seek a declaration that it is entitled to have the Contract specifically performed and to be carried into execution. In those circumstances I think it cannot be said that the making of orders by way of declaratory relief was not something contemplated when the proceedings commenced.
121 Moreover, the court has power under s 63 of the Supreme Court Act 1970 and under r 36.1 of the Uniform Civil Procedure Rules to grant all such relief as a party may be entitled to, whether or not a specific claim for that relief has been made in the originating proceedings.
122 It is within the jurisdiction of the court to grant declaratory relief in appropriate circumstances and I am of the view this is one.
123 In Waterways Authority of NSW v Coal & Allied Operations Pty Limited [2006] NSWSC 183, Barrett J accepted that r 36.1 of the UCPR enabled the making of declarations even when not specifically sought but questioned the utility in so doing in that case in light of s 63 of the Act which places emphasis on all matters in controversy between the parties being completely and finally determined and multiplicity of legal proceedings being avoided, and the principles laid down in Neeta (Epping) Pty Limited v Phillips (1974) 131 CLR 286.
124 In Neeta Barwick CJ and Jacobs J said at 307:
Unless the parties are agreed on the consequences which flow from a declaration that such a contract has not been validly rescinded it is generally undesirable that a court should so declare without any orders for consequential relief. If a party to such a contract claimed the Contract has not been validly rescinded such a judicial declaration is proper if that party continues ready and willing at the conclusion of the declaration to perform the Contract . A consequence of the declaration should be that the parties submit to the performance of the Contract on his part and for an order for specific performance of the Contract if that is appropriate. If such an order is not, or cannot be made, nor an inquiry into damages ordered then a declaration that on a certain day the Contract has not been validly rescinded serves no purpose in litigation.
125 In Meagher, Gummow and Lehane (4th ed) it is said that the fact that a declaration might not finally conclude the dispute between the parties can hardly ever be, of itself, a proper ground for not making a declaration. The authors, citing Hope J in Integrated Lighting & Ceilings Pty Limited v Philips Electrical Pty Limited (1969) 90 WN (Pt 1) (NSW) 693, state that the likelihood of further litigation is something which should affect, but does not determine, the exercise of the court's discretion.