Environment Protection Authority v Port Stephens Council
[2011] NSWLEC 209
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2011-08-18
Before
Craig J, Mr J
Catchwords
- (2006) 148 LGERA 278 Environment Protection Authority v Robinson [2004] NSWLEC 629 Markarian v The Queen [2005] HCA 25
- (2005) 228 CLR 357 R v Thomson
- R v Houlton [2000] NSWCCA 309
- (2000) 49 NSWLR 383 R v White, CCA, 25 July 1991, unreported Veen v The Queen (No 1) [1979] HCA 7
Source
Original judgment source is linked above.
Catchwords
Judgment (34 paragraphs)
Judgment 1Port Stephens Council ( the Council ) has pleaded guilty to an offence against s 48(2) of the Protection of the Environment Operations Act 1997 ( the POEO Act ) in that from about 1 July 1999 to 7 July 2008 ( the charge period ) it occupied premises at which a scheduled activity was carried on and, at the time the activity was carried on, it did not hold a licence that authorised that activity to be carried on at those premises. The scheduled activity referred to in the charge is a "waste facility". The activity was conducted on the site of a former quarry, being lot 21 in deposited plan 570152, located at Medowie Road, Medowie ( the Site ). It is now necessary to sentence the Council for that offence. 2At all times throughout the charge period, s 48 relevantly provided: " 48 Licensing requirement - scheduled activities (premises - based) (1) Application of section This section applies to scheduled activities where Schedule 1 indicates that a licence is required for premises at which the activity is carried on. (2) Offence A person who is the occupier of any premises at which any such scheduled activity is carried on is guilty of an offence, unless the person is, at the that activity is carried on, the holder of a licence that authorises that activity to be carried on at those premises." 3During the period from 1 July 1999 to 30 April 2006 inclusive, the maximum penalty stipulated in s 48 for the commission of an offence by a corporation was $250,000 and, in the case of a continuing offence, a penalty of $120,000 for each day the offence continues. During the period from 1 May 2006 to 7 July 2008, the maximum penalty for the commission of the offence by a corporation was increased to $1,000,000 while the daily penalty for a continuing offence remained as it had been. Although the conduct constituting the offence commenced prior to 30 April 2006, the fact that it continued until 7 July 2008, that is during the period in which the higher maximum penalty was applicable, that increased maximum penalty applies when determining the appropriate penalty in the present case ( R v White, CCA, 25 July 1991, unreported). 4During the charge period, the Site was used by the Council in the following way: (i) for storage of materials produced from road works, pavement works and drainage works intended for recycling or re-use, such as soils, road base materials, concrete and pipes; and (ii) for the disposal of surplus materials produced from road works, pavement works and drainage works that were considered unsuitable for recycling. These materials were used to fill the void space created by the quarrying activities formerly carried out on the Site. 5The use of the Site in this manner involved activities that fell within the relevant definition or description found in Sch 1 to the POEO Act and thus required a licence pursuant to s 48. Relevantly, they were activities that engaged the definition of "waste facilities", as that expression was defined in Pt 1 of Sch 1 to the Act between 1 July 1999 and 27 April 2008. Between 28 April 2008 and 7 July 2008 those same activities fell within those described under the heading "waste disposal (application to land)" found in cl 39 of Pt 1 of Sch 1 to the Act.