75 I do not consider however this is a case such as Transgrid where the Court found that there was a complete failure to apply the relevant policies of the corporation to the offences in that case. The defendant in that case, a state owned corporation, was found guilty of polluting watercourses by clearing of vegetation. Vegetation of easements had overgrown and deteriorated to a stage where they became a potential fire hazard. Emergency clearing ensued, however there was a failure to put in place sediment controls to prevent the bare earth from washing into the nearby waterways. It was found by Lloyd J in that case at [109] that the clearing should not have occurred at all in the manner in which it did, and at [108], that the consequences of the clearing were reasonably foreseeable and that the programs and policies in place were not enough where they are not accompanied by actions. Clearly the Defendant in the present case had in place environmental management policies and a program it was implementing to ensure that all transformers were appropriately bunded. Under that program the transformer from which the leak escaped would have been protected by a bund which was to built about one month after the incident giving rise to the offence. While I have held that the harm caused was foreseeable I also accept that the Defendant was taking active steps to correct the circumstances giving rise to this offence.
76 While general deterrence is relevant to consider in the context of statutory authorities I do not consider the circumstances warrant a penalty which takes into account specific deterrence for this Defendant.
Evenhandedness
77 Evenhandedness is an important consideration in sentencing. The Defendant referred to a number of cases it said were similar in terms of the objective seriousness of the offence which is low. In Environment Protection Authority v Olex Australia Pty Ltd [2005] NSWLEC 475, the pollutant overflowed into a stormwater drainage system and entered in a creek. This was caused by a faulty sensor alarm, a waste-pit pump failure and an isolation valve in the drainage system not being sealed. There was no actual environmental harm. In Environment Protection Authority v Timber Industries Ltd [2001] NSWLEC 25, run-off from a timber mill discharged into a drainage channel due to faulty repair works. The pollutant did not proceed to a natural watercourse downstream. There was no actual environmental harm and only limited potential harm. In Environment Protection Authority v Excel Fuels Pty Limited [2002] NSWLEC 160, oil was transferred by mistake into a tank already full. The overflow entered the stormwater system and travelled into a creek, causing limited environmental harm. In Environment Protection Authority v Allied Industrial Services Pty Ltd [2005] NSWLEC 501, contaminated liquid escaped and travelled into a creek due to a blockage in the wastewater treatment system, causing limited likely environmental harm. In Environment Protection Authority v Coe Drilling Australia Pty Ltd [2005] NSWLEC 719, drilling works resulted in the discharge of a pollutant into a listed sensitive wetland, resulting in material actual environmental harm. None of these involved a statutory authority. Penalties imposed were in the range of $15,000 to $25,000 after mitigating circumstances were taken into account. The facts of these cases are generally analogous to the matter before me.