Big Island Mining
4. Big Island Mining operates the Dargues Gold Mine located at Majors Creek Road, Majors Creek, NSW (the Premises).
5. In February 2012, project approval was granted under the Environmental Planning and Assessment Act 1979 for the Dargues Gold Mine (the Project Approval). A copy of the Project Approval as issued by the Land and Environment Court is at Annexure A. The Project Approval was subsequently modified on 12 July 2012, but those amendments are not relevant to these proceedings.
6. Under the terms of the Project Approval (condition 26), a Water Management Plan was required to:
a. be prepared in consultation with various authorities;
b. contain an erosion and sediment control plan;
c. be submitted to the Director-General of the Department of Planning prior to the commencement of construction; and
d. be implemented.
7. A Water Management Plan was prepared by R.W.Corkery & Co Pty Limited and Strategic Environmental and Engineering Consulting (SEEC) in consultation with the various authorities, including the Office of Environment and Heritage, as required (the Water Management Plan). A copy of the Water Management Plan is at Annexure B.
8. The Water Management Plan contained an Erosion and Sediment Control Plan prepared by SEEC and dated April 2012 (the 2012 ESC Plan) (Appendix 2 to Annexure B).
9. The Water Management Plan (including the 2012 ESC Plan) was approved by the Director-General on 16 May 2012.
10. The 2012 ESC Plan required certain sediment and erosion controls, and certain practices and procedures, to be implemented to ensure that water quality within Spring Creek and Majors Creek was not adversely impacted.
11. Big Island Mining holds Environment Protection Licence number 20095 (the EPL), which, at the relevant time, authorised the carrying out of scheduled development work, including ground disturbing activities and construction activities. Other than the discharge of water from a particular discharge point (which is not relevant for the purposes of this proceedings), the EPL does not permit the pollution of waters. A copy of the EPL is at Annexure C.
12. Big Island Mining is owned by Dargues Gold Mine Limited (ACN 117 848 790) which is itself owned by Unity Mining Limited (ACN 005 674 073).
13. Big Island Mining does not employ any staff. The staff that work on site on behalf of Big Island Mining are employed by Dargues Gold Mine Limited or Unity Mining Limited.
14. In the period of 23 February to 1 March 2013 the works carried out on the Premises involved works associated with the construction of:
a. a Site Access Road from Majors Creek Road on the east of the Premises to the Site Office on the west of the Premises (Site Access Road); and
b. a Box Cut, being an excavated area on the site where access is provided to the underground gold mine (Box Cut) on the west of the Premises.
15. Annexure D is an aerial photograph of the Premises that has been marked to show the location of the following areas:
a. the Site Access Road;
b. the Box Cut;
c. the Temporary Basins;
d. Unnamed Drainage Line 1;
e. Unnamed Drainage Line 2;
f. Spring Creek;
g. Majors Creek;
h. temporary site office and car park area;
i. Culvert Crossing 1; and
j. the boundary of the Premises.
Divalls Earthmoving and Bulk Haulage
16. Big Island Mining entered into an agreement with Denrith Pty Ltd (ACN 060 434 871), trading as Divalls Earthmoving and Bulk Haulage (Divalls) that was titled "General Works Agreement" and dated 4 February 2013 (the Divalls Agreement). The Divalls Agreement is at Annexure E.
17. As part of the tender process for construction work at the Premises, on 29 November 2012, Divalls were informed that all data for the Box Cut, Site Access Road and Tailings Storage Facility could be downloaded from Cortona's File Transfer Protocol site. The Water Management Plan was on this site.
18. Under the terms of the Divalls Agreement:
a. Divalls were required to execute and complete the 'Contract Works' in accordance with the terms of the Divalls Agreement (clause 2.1);
b. the 'Contract Works' were defined to mean "the work specified in Item 2 of Schedule 1 and as described in the Drawings, Specification and any materials or manuals to be supplied as part of that work and includes any Variation" (clause 1.1);
c. Item 2, Schedule 1, set out the details of the Contract Works as being "the excavation and construction of the boxcut, access road, tailings storage facility and associated works at Unity Mining Limited's (Unity) Dargues Gold Mine, as further set out in Schedule 3" (Item 2, Schedule 1);
d. Schedule 3, the "Scope of Contract Works", further attached a 10-page document detailing the scope of services. Page 3 of the document stated "Best practice erosion and sediment control measure to be implemented";
e. The "Drawings" were defined to mean "the Drawings listed or contained in Schedule 7" (clause 1.1);
f. The Drawings listed at Schedule 7 included:
i. construction design drawings for the Box Cut prepared by CRC, Geohart Consultants and Geotesta Consulting Engineers (the Box Cut Plans - Annexure F); and
ii. construction design drawings for the Site Access Road prepared by K & C Brown and Associates (the Site Access Road Plans - Annexure G).
19. On 22 January 2013, Greg Cozens, Project Manager, instructed Divalls by email to download copies of certain relevant documents from the public web site for the project, including a copy of the Water Management Plan, which included the 2012 ESC Plan. The Water Management Plan was not attached to the Divalls Agreement.
20. Divalls commenced work on 11 February 2013.
SEDIMENT AND EROSION CONTROL MEASURES
21. The 2012 ESC Plan contained:
a. notes recommending that works be staged and carried out in a certain way;
b. plans showing the location of certain sediment and erosion control works; and
c. construction notes and diagrams showing how certain sediment and erosion control works were to be implemented.
22. The Box Cut Plans did not contain any information in relation to erosion and sediment control.
23. The Site Access Road Plans showed the location of certain sediment and erosion control works and some of the construction notes on those plans related to sediment and erosion control works.
The Box Cut
24. The Project Approval conditions and the 2012 ESC Plan required the following controls to be installed and practices be followed during the construction phase of the Box Cut:
a. ensuring that best-practice erosion and sediment control measures are implemented during both the construction and operational stages of the project;
b. ensuring that appropriate staging be undertaken to minimise the area of land disturbed at any one time;
c. ensuring that surface water flows are diverted away from disturbed areas and that potentially sediment laden flows from disturbed areas are directed or pumped to sediment controls, this includes installation of:
i. water diversions to ensure that clean water cannot enter the Box Cut construction area; and
ii. water diversions to ensure that dirty water collected at the Box Cut construction area drains or can be pumped from the Box Cut area toward either Sediment Basin 1 or Sediment Basin 2;
d. the installation of Sediment Basin 1 and Sediment Basin 2 near the Box Cut;
e. ensuring that the only dirty water to be captured in the Box Cut is storm water that falls within the surface area of the Box Cut itself;
f. the installation of other erosion and sediment controls, such as sediment fences and straw bales to minimise the risk of sediment from entering downstream drainage lines and Spring Creek;
g. complying with the specifications in relation to the location of soil stockpile areas and practices to control erosion of and catch sediment from soil stockpiles;
h. identification of procedures to ensure adequate capacity in the sediment basins (i.e. treat, de-water and de-silt the basins within 5 days of the conclusion of any rain event); and
i. ensuring that each of the sediment basins has a stabilised outlet to ensure stability for overflows.
The Site Access Road
25. The Project Approval conditions and the 2012 ESC Plan required the following controls and procedures to be put in place during the construction phase of the Site Access Road:
a. ensuring that best-practice erosion and sediment control measures are implemented during both the construction and operational stages of the project and that all roads within the Premises are constructed in accordance with the relevant document;
b. ensuring that surface water flows are diverted away from disturbed areas and that potentially sediment laden flows from disturbed areas are diverted to sediment controls, this includes the installation of:
i. clean water diversions to divert clean water around the entire up-gradient side of the Site Access Road during construction; and
ii. culvert crossings to divert clean water underneath the Site Access Road during construction;
c. inspection of all surface water control structures at least weekly and following any rainfall event of more than 10mm in 24 hours, and maintain a log of inspections to ensure their adequacy and identify where remedial action is required;
d. installation of a sediment fence along the entire down gradient side of the Site Access Road construction area;
e. stockpiling to be undertaken in accordance with the drawings and notes in the 2012 ESC Plan, including the installation of sediment fences around the lower perimeter of the stockpiles;
f. installation of 'energy dissipaters' at set locations along the Site Access Road;
g. adherence to clean water diversion drain sizing and detailing calculations including slope, width, depth and side slope ratio and recommended lining material for each clean water diversion drain around the Site Access Road construction area so that the drains would be capable of conveying a specific size rainfall event;
h. use of specified lining material for clean and dirty water diversion drains (i.e. Jute mesh or vegetated or hard stand such as asphalt);
i. implementation of recommended exposed slope lengths along the Site Access Road construction area; and
j. ensuring that each of the sediment basins has a stabilised rock outlet to ensure stability during a rainfall event.
26. The Site Access Road Plans required that the following controls be installed and practices be followed during the construction phase of the Site Access Road:
a. implementing sediment and erosion control measures which comply with procedures and specifications of the "Blue Book" Landcom, Managing Urban Stormwater - Soils and Construction - Volume 1 - 4th Edition March 2004;
b. stockpiles shall be avoided unless shown in the stormwater management plan; and
c. ensuring silt traps are constructed, including downstream of the culvert crossing construction site in Unnamed Drainage Line 2 prior to commencing which was to be a gabion wall wrapped in bidum membrane with a spillway.
THE WATERS POLLUTED
27. Spring Creek is a small headwater stream. Spring Creek is a tributary of Majors Creek, a larger headwater stream. Spring Creek is generally 2 metres or less in width. It is comprised of still pools and flowing runs with beds of sand, stone and clay, and at the points inspected by Dr Bruce Chessman, had abundant aquatic vegetation and well-vegetated banks.
28. Downstream of its junction with Spring Creek, Majors Creek enters a steep and heavily vegetated gorge. After emerging from this gorge, Majors Creek flows into Araluen Creek, which in turn is a tributary of the Deua River. The Deua River catchment provides 60 per cent of the Eurobodalla water supply for the people of Eurobodalla. Majors Creek provides a water source for rural properties along its course.
29. An Aquatic Ecological Assessment was prepared in relation to the project in November 2011. That report is Appendix 4 to Annexure B.
30. The waters that were polluted included two separate unnamed channels (referred to as "Unnamed Drainage Line 1" and "Unnamed Drainage Line 2" and shown on the map at Annexure D) as well as Spring Creek and Majors Creek.
31. During Incident 1 the discharging water left the incomplete Box Cut excavation, drained into a small sediment basin, drained across the office car park (past the site offices), drained through a culvert pipe underneath the Old Dargues Gold Mine Access Track into Unnamed Drainage line 2 and then into Spring Creek and then flowed to Majors Creek.
32. During Incident 2 the discharging water left the incomplete Box Cut excavation, drained into a small sediment basin and then into two temporary basins, drained across the office carpark (past the site offices), drained through a culvert pipe underneath the Old Dargues Gold Mine Access Track and into Unnamed Drainage Line 2. The discharging water then entered Spring Creek and then flowed to Majors Creek.
33. During Incident 3, the discharging water ran from the Site Access Road construction area, between the intersection with Majors Creek Rd and Culvert Crossing 4, into Unnamed Drainage Line 1, and became yellow and turbid as it continued to flow downstream of the Site Access Road construction area.
34. During each incident, the sediment in the discharging water included soil, earth, silt, clay and/or other suspended solids and/or similar inorganic matter.
THE WATER POLLUTION INCIDENTS
35. There is a weather reporting station located at the Premises that collects rainfall data (Premises' Weather Station).
36. The Bureau of Meteorology has three weather reporting sites in the Majors Creek area. These three sites are:
a. Braidwood (Wallace Street) (Site No. 6910) which is approximately 14.2km from the Premises;
b. Braidwood Racecourse AWS (Site No. 69132) which is approximately 16.2km from the Premises; and
c. Bettowynd (Condry) (Site No. 69006), which is approximately 15.9km from the Premises,
(together, the Three Reporting Sites).
37. The location of the Three Reporting Sites in relation to the Premises is shown on the map at Annexure H.
38. On Wednesday 20 February 2013:
a. the Premises' Weather Station recorded rainfall of 1.1mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 1.8mm at Braidwood (Wallace Street);
ii. 2.2mm at Braidwood Racecourse AWS; and
iii. 1mm at Bettowynd (Condry).
39. On Thursday 21 February 2013;
a. the Premises' Weather Station recorded rainfall of 0.2mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 0.6mm at Braidwood (Wallace Street);
ii. 0.4mm at Braidwood Racecourse AWS; and
iii. 0mm at Bettowynd (Condry).
40. On Friday 22 February 2013:
a. the Premises' Weather Station recorded rainfall of 0.9mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 14.6mm at Braidwood (Wallace Street);
ii. 11.8mm at Braidwood Racecourse AWS; and
iii. 1mm at Bettowynd (Condry).
23 to 25 February 2013 (Incident 1)
41. On Saturday 23 February 2013:
a. the Premises' Weather Station recorded rainfall of 24.6mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 18.6mm at Braidwood (Wallace Street);
ii. 15mm at Braidwood Racecourse AWS; and
iii. 57mm at Bettowynd (Condry).
42. On Saturday 23 February 2013 at approximately 1:00pm, Greg Cozens (Project Manager, Dargues Gold Mine Limited) was conducting an ad-hoc site inspection of the Premises when he observed turbid water with suspended clay draining from the Box Cut, through the sediment fences and straw bales to the south of the Box Cut, through a small sediment basin, past the temporary offices and into Spring Creek.
43. Greg Cozens contacted Ajanth Saverimutto (Operations Manager, Unity Mining) on Saturday 23 February 2013 to inform him that water was discharging offsite.
44. Greg Cozens returned to the Premises on Sunday 24 February 2013. He again observed that water was discharging from the Box Cut, past the site offices and into Spring Creek. The discharge of sediment laden water was also observed by Rebecca Bigg (Environment Officer, Dargues Gold Mine Limited) on Sunday 24 February 2013.
45. On Sunday 24 February 2013:
a. the Premises' Weather Station recorded rainfall of 44.7mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 36.2mm at Braidwood (Wallace Street);
ii. 54.6mm at Braidwood Racecourse AWS; and
iii. 62mm at Bettowynd (Condry).
46. On Sunday 24 February 2013, Big Island Mining directed Divalls to excavate two additional sediment basins (the Temporary Basins) along the flow path of the water discharging from the Box Cut towards Unnamed Drainage Line 2. The Temporary Basins were dug in an attempt to slow the water down and to settle out the sediment before it ran offsite. The photos at Annexure I show where the Temporary Basins were dug on 24 February 2013. The location of these temporary basins is shown on the map at Annexure D.
47. On the same day, at Big Island Mining's direction, Divalls commenced the construction of a temporary wall to seal up the point of discharge of the Box Cut, but this work was not completed on this day.
48. On the morning of 24 February 2013, Mr Matthew Dickinson observed the confluence of Spring Creek and Majors Creek, and saw that Spring Creek was, what he described as, a chocolate colour and that Majors Creek was clear. He observed that the water at the confluence of Spring Creek and Majors Creek was, what he described as, brown in colour. He walked downstream of the confluence of Majors Creek and Spring Creek and observed that Majors Creek was, what he described as, a chocolate colour downstream of this point.
49. During the morning of 24 February 2013, at the confluence of Spring Creek and Majors Creek, Mr Bill Waterhouse observed, what he described as, mustard coloured muddy water in Spring Creek. He observed Majors Creek, downstream of the confluence of Majors Creek and Spring Creek was, what he described as, the same mustard colour as Spring Creek and that the water in Majors Creek upstream of the confluence was not particularly dirty and it was, what he described as, a transparent grey, blue, green colour.
50. At approximately 10.40am on the morning of 24 February 2013, Ms Jackie French observed, what she described as deep muddy orange water flowing in Majors Creek at her property (which is approximately 4km downstream of Dargues Reef Mine).
51. On Monday 25 February 2013:
a. the Premises' Weather Station recorded rainfall of 20.8mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 8mm at Braidwood (Wallace Street);
ii. 7.6mm at Braidwood Racecourse AWS; and
iii. 8mm at Bettowynd (Condry).
52. On 25 February 2013 Mr James Dornan (Project Engineer, Unity Mining) called the EPA Environment Line to report an incident of a discharge of sediment laden water from the Premises to Spring Creek.
53. On Monday 25 February 2013, EPA Officer Matthew Rizzuto inspected the Premises and at the Box Cut, he observed that Sediment Basin 1 had not been installed, the Temporary Basins were full of orangey brown water, a significant amount of loose orangey brown soil around the edges of those sediment basins (see photos at Annexure J) and construction of the wall across the point of discharge from the Box Cut Construction Area had not been completed (the wall was two metres in length and the width of the discharge point was 5 metres in length).
54. On the eastern side of the Box Cut adjacent to Spring Creek, EPA Officer Matthew Rizzuto observed disturbed and cleared soil over a large area which was bounded by a sediment fence. EPA Officer Matthew Rizzuto observed that the surface of the area was directed towards a drainage line which contained hay bales covered in geotextile across part of the drainage line, and that there was sediment on the down-gradient side of the hay bales.
55. The discharge of water from the Box Cut and into Spring Creek stopped sometime between Monday 25 and Tuesday 26 February 2013.
26 to 28 February 2013
56. On Tuesday 26 February 2013:
a. the Premises' Weather Station recorded rainfall of 0.2mm; and
b. the Bureau of Meteorology did not record any rainfall at the Three Reporting Sites.
57. On Tuesday 26 February 2013, EPA Officers Nigel Sargent and Sandra Jones attended the Premises. During this inspection the EPA issued Big Island Mining with a draft Clean up notice.
58. On Wednesday 27 February 2013:
a. the Premises' Weather Station recorded rainfall of 0.1mm; and
b. the Bureau of Meteorology did not record any rainfall at the Three Reporting Sites.
59. On Wednesday 27 February 2013, the EPA issued Big Island Mining a final Clean up notice. Annexure K is a copy of that Clean up notice.
60. Between Monday 25 February and Thursday 28 February 2013 a series of works were carried out at the Premises by Divalls at Big Island Mining's direction, including the following:
a. the completion of the construction of a temporary wall to seal up the discharge point of the Box Cut;
b. the excavation of a deeper sump in the Box Cut enabling it to collect a large amount of water; and
c. the installation of more sediment fences towards the east of the Box Cut.
61. Between Monday 25 February and Thursday 28 February 2013 various works were carried out at the Premises by Big Island Mining, including the following:
a. the installation of a number of strawbale barriers and polythene sediment fences and controls down-slope of the Box Cut;
b. repairing straw bale sediment barriers to the north of the Box Cut (these are shown in Annexure L);
c. the installation of straw bale sediment barriers from the main access road leading into Culvert Crossing 1;
d. the installation of additional sediment fencing along both sides of Culvert Crossing 1; and
e. the installation of additional straw bale structures on the slopes leading down into Culvert Crossing 1.
62. On 27 February 2013,EPA Officers Matthew Rizzuto and Tristan Johnson inspected the Premises at the Box Cut. They observed that the Temporary Basins were full of turbid water. They also observed that the raised wall being constructed at the discharge point of the Box Cut was not complete, that there was no formally constructed discharge controls (such as a rock gabion outlet or lined discharge channel) at the discharge location of the Box Cut and that there was no clean-water diversions installed on the up gradient sides of the Box Cut to stop clean water entering the Box Cut. Photographs at Annexure M show the Box Cut Construction Area and were taken by EPA officers during an inspection undertaken on 27 February 2013.
63. During the inspection on 27 February 2013, EPA Officers Rizzuto and Johnston also inspected the New Site Access Road construction area and observed that there were earthworks across Unnamed Drainage Line 1 at Culvert Crossing 1. The Officers also observed that there was a significant volume of loose soil located in and around the Culvert Crossing 1, that there were a number of sediment fences which had been installed since their inspection on 25 February 2013 but that these sediment fences had exposed soil on both sides of the fences and that there were no structures installed to divert clean water around the construction area which meant that clean water was allowed to move across freshly excavated exposed soil.
64. On 27 February 2013, EPA Officers Nigel Sargent and Sandra Jones inspected Majors Creek at the property at 381 Major's Creek Rd, Araluen, owned by Ms Jackie French, approximately four kilometres downstream of the Premises. On that date, Majors Creek was running and the water within the creek was clear.
65. On Thursday 28 February 2013;
a. the Premises' Weather Station recorded rainfall of 1.3mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 2.6mm at Braidwood (Wallace Street);
ii. 3mm at Bettowynd (Condry); and
iii. 0mmat Braidwood Racecourse AWS.
1 March 2013 (Box Cut- Incident 2)
66. On Friday 1 March 2013:
a. the Premises' Weather Station recorded rainfall of 24.2mm; and
b. the Bureau of Meteorology recorded rainfall of:
i. 29.4mm at Braidwood (Wallace Street);
ii. 26mm at Braidwood Racecourse AWS; and
iii. 38mm at Bettowynd (Condry).
67. On 1 March 2013 EPA Officers Johnson and Rizzuto observed orangey brown, sediment laden water discharging from the Box Cut into a depression in the ground and then into the Temporary Basins. The water had not been emptied from the Temporary Basins prior to 1 March. Photograph at Annexure N shows the water discharging from the Box Cut. Photographs at Annexure O show the water in the depression in the ground and in the Temporary Basins.
68. The turbid water then discharged from the temporary basins, through and around a number of sediment control structures, across the office car park and into the upstream end of a concrete culvert pipe adjacent to the temporary site offices.
69. The turbid water continued to discharge through the concrete culvert pipe and into Unnamed Drainage Line 2. The turbid water flowed down Unnamed Drainage Line 2 and into Spring Creek. The photograph at Annexure P shows water from Unnamed Drainage Line 2 flowing into Spring Creek.
1 March 2013 (Site Access Road- Incident 3)
70. Unnamed Drainage Line 1 runs perpendicular to the Site Access Road. On 1 March 2013, EPA Officers Johnson and Rizzuto observed that the water in Unnamed Drainage Line 1 upstream of the Site Access Road construction area was clearer than the water downstream of the Site Access Road. The downstream waters were observed to be yellow and turbid. Photograph at Annexure Q shows Unnamed Drainage Line 1 upstream of the Site Access Road.
WATER SAMPLES COLLECTED AT OR IMMEDIATELY SURROUNDING THE PREMISES
71. Greg Cozens and Rebecca Bigg took water samples on Friday 23 February and Saturday 24 February 2013. Rebecca Bigg took water samples on Saturday 25 February 2013.
72. Matthew Rizzuto, of the EPA, took water samples on 27 February and 1 March 2013. The sampling points are shown on the map at Annexure R.
73. A summary of some of the results is set out as follows.
Date sample collected Identity of collector Sample Location Result - Turbidity Result - Total Suspended Solids (TSS)
23 Feb 2013 sample 1 G Cozens or Rebecca Bigg Unnamed Drainage Line 2 at the Site Office (sample 5) N/A 1700mg/L
s
23 Feb 2013 sample 2 G Cozens or Rebecca Bigg Spring Creek above confluence with Unnamed Drainage Line 2 (sample 4) N/A 20mg/L
23 Feb 2013 sample 3 G Cozens or Rebecca Bigg Spring Creek below where water enters from Unnamed Drainage Line 2 (sample 2) N/A 800mg/L
23 Feb 2013 sample 4 G Cozens or R Bigg Below the confluence of Spring Creek and Majors Creek (sample 3) N/A 100mg/L
27 Feb 2013 M Rizzuto Spring Creek, upstream of the Box Cut construction area (DR3) 15 NTU <15mg/L
(Box Cut) sample 5
27 Feb 2013 M Rizzuto Temporary basin below Box Cut area (DR 5) 1000 NTU 45mg/L
(Box Cut) sample 6
27 Feb 2013 sample 7 M Rizzuto Spring Creek, approximately 50m upstream of confluence with Majors Creek (DR 15). 6.9 NTU <6 mg/L
27 Feb 2013 sample 8 M Rizzuto Majors Creek, approximately 20m downstream of the confluence with Spring Creek (DR 17). 6.9 NTU <6 mg/L
1 Mar 2013 M Rizzuto Spring Creek, immediately upstream of the Box Cut construction area (DR 23) 49 NTU <15mg/L
(Box Cut) sample 9
1 Mar 2013 M Rizzuto Pool 5m down-gradient of the Box Cut (DR 25) 2000 NTU 580mg/L
(Box Cut) sample 10
1 Mar 2013 M Rizzuto 5m downstream of confluence of Unnamed Drainage Line 2 and Springs Creek (DR 31) 120 NTU 24mg/L
(Box Cut) sample 11
1 Mar 2013 M Rizzuto Unnamed Drainage Line, 1m from where it enters Springs Creek (DR 33) 880 NTU 480mg/L
(Box Cut) sample 12
1 Mar 2013 M Rizzuto Temporary basin below Box Cut area (DR 35) 470 NTU 380mg/L
(Box Cut) sample 13
1 Mar 2013 M Rizzuto Unnamed Drainage Line 1, immediately upstream of culvert crossing 1 (DR 39) 41 NTU <30mg/L
(Site Access Road) sample 14
1 Mar 2013 M Rizzuto Unnamed Drainage Line 1, 50m downstream of culvert crossing 1 (DR 40) 310 NTU 300mg/L
(Site Access Road) sample 15