El Boustani v Minister Administering the Environmental Planning and Assessment Act 1979
[2013] NSWLEC 25
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2013-02-22
Before
Pepper J, The J, Mr J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
The El Boustanis Seek an Additional Two Years of Lost Profits 1By notice of motion dated 19 January 2013, Mr Elias and Mrs Guita El Boustani ("the El Boustanis"), the applicants in compensation for compulsory acquisition proceedings, seek an order pursuant to r 36.17 of the Uniform Civil Procedure Rules 2005 ("the UCPR") (otherwise known as the 'slip rule') to correct the Court's calculation of compensation in relation to lost profits. 2The El Boustanis contend that the Court clearly intended to award five years compensation for lost profits but has instead only awarded three. The respondent, the Minister Administering the Environmental Planning and Assessment Act 1979 ("the Minister"), submits that no mistake has occurred and that the Court plainly intended to award three years of compensation for lost profits, which it did, and which is reflected in the Court's orders. 3The El Boustanis relied on correspondence passing between them and the Minister ventilating the issue. It is clear from this correspondence that the parties are in disagreement over the resolution of the question. 4In my opinion the Minister's position is correct and the application must be dismissed.
The Lost Profits Issue 5As stated in the principal decision (El Boustani v Minister Administering the Environmental Planning and Assessment Act 1979 [2012] NSWLEC 266) the El Boustanis grew tomatoes, cucumbers and other vegetables for wholesale on land that was, in part, compulsory acquired on 23 July 2010 by the Minister. 6Prior to the resumption date, the 2010 crop of tomatoes and vegetables had been planted for harvest in late December 2010 or early 2011. Despite initially being told by the Department of Planning that the 2010 crop could be harvested, notwithstanding the proposed resumption, the El Boustanis were subsequently informed on 20 September 2010 that they had to vacate the resumed land by 30 November 2010, thereby preventing them from harvesting the crops referred to above. 7In addition to the market value of the land and relocation costs associated with re-establishing their business elsewhere on a new property, the El Boustanis claimed lost profit by reason of the acquisition. 8By the conclusion of the proceedings the dispute concerning the award of lost profits had narrowed itself as follows: (a) it was not a matter of controversy that the compensation for the lost profits for the 2010-2011 and 2011-2012 years was payable (El Boustani at [138]); (b) for the 2010-2011 year the lost profits were agreed in the amount of $104,579, plus $11,221 (the costs thrown away occasioned by the forced abandonment of the 2010-2011 crop), for a total of $115,800 (El Boustani at [139]); (c) the Minister contended that only two years of lost profits were payable by way of compensation (2010-2011 and 2011-2012); (d) the El Boustanis submitted that four years of lost profits (2010- 2011, 2011-2012, 2012-2013 and 2013-2014) were payable. The claim by the El Boustanis for four years of lost profits was clearly articulated by them in their pleadings, their closing written and oral submissions and in their final updated claim table; (e) the evidence of the El Boustanis' expert forensic accountant, Mr Peter White, calculated the net present value of the total loss of profits based upon three years of lost profits (that is, ending with the 2012-2013 year). A three year time period was adopted by Mr White on the basis of Mr El Boustani's evidence that it would take 24 months to re-establish the business to a state where production could recommence once construction of new facilities was completed; and (f) at no point did the El Boustanis claim or make submissions to the effect that they were entitled to five years of lost profits. 9In El Boustani the Court relevantly dealt with the claim for lost profits in the following way (at [139] and [148]-[150]): 139. For the 2010-2011 year this sum was agreed in the amount of $104,579, which I accept. To this should be added $11,221, which the parties agreed the El Boustanis had incurred as costs thrown away occasioned by the abandonment of the 2010-2011 crop. This brings the total to $115,800 for the 2010-2011 year. ... 148. The El Boustanis also sought compensation for loss of profits for a further two years, namely 2012-2013 and 2013-2014. This represented the amount of time they estimated it would take to re-establish their business to the point of production after construction of the igloos (and related facilities) on any newly acquired property. Accordingly, the El Boustanis seek an amount of compensation in the sum of $121,511 for these additional two years. 149. The Minister's submission was that the El Boustanis were only entitled to an initial two years of lost profits, and that anything further could not properly be characterised as a direct and natural consequence of the acquisition because it was occasioned by the preference of the El Boustanis, as Mrs El Boustani expressed in her oral and written evidence, to wait until proceedings were finalised prior to purchasing a property with an existing dwelling located on it. Put another way, the lengthy delay in re-establishing their business arose as a consequence of the desire by the El Boustanis to "replace something different to that which has been acquired", viz, a farm with no home. 150. I do not agree. The evidence that it would take two years before a crop would be produced after the construction of igloos and related infrastructure on any new property was unchallenged and was not dependant upon whether or not the newly purchased property was vacant. Allowing for a year to find a new property and to construct the facilities necessary to grow tomatoes, in addition to the two years necessary to permit full production, in my opinion the El Boustanis should be compensated for a total period of three years of lost profits. That is to say, $115,800 + (2 x $60,755) = $237,310. I note that this approach is also consistent with the evidence of Mr White. 10Accordingly, disturbance for lost profits was calculated in the sum of $237,310. This was reflected in order 3(b) of the final orders (at [161]).