© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] NSWCA 25
Court of Appeal (NSW)
2019-10-30
White JA, Brereton JA, Parker J
Original judgment source is linked above.
nda Nominee Pty Ltd (Respondent) Representation: Counsel: F Hicks SC with S Ahmed and F Anwar (Appellant) S G Finch SC with D R Sibtain (Respondent
Solicitors: Madison Marcus (Appellant) Mills Oakley (Respondent) File Number(s): 2019/280811 Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity Division Citation: [2019] NSWSC 1157 Date of Decision: 6 September 2019 Before: Parker J File Number(s): 2019/136937
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the decision] The appellant challenged a decision of a judge of the Equity Division upholding the respondent's summons seeking orders that the appellant provide certain items and documents that were required to achieve 'Practical Completion" in accordance with the parties' contract. On 18 April 2017 the parties entered into a contract for the appellant to design and construct two residential buildings, car park, pool and other facilities as part of a development at Miranda known as the Palisade. The Contract Price was a lump sum amount of $65,758,576 exclusive of GST. The respondent in accordance with the contract appointed a project manager, Resource Co-ordination Partnership Pty Ltd (RCP), which was described as the "Principal's Representative". On 19 March 2019 a sum of $293,984.42 became due to the appellant and payable by the respondent in accordance with the contract and the payment schedule. That sum was not paid on that day. The primary judge found that the respondent initiated an electronic payment of the amount due without interest on 22 March, which was a Friday. Payment did not reach the appellant until the following Monday, 25 March. Interest claimed by the appellant in the sum of $177.20 payable under s 11 of the Building and Construction Industry Security of Payment Act 1999 (NSW) ("Security of Payment Act") remained outstanding. On 25 March 2019 the appellant issued two notices, one under the Security of Payment Act and the other under the contract, notifying the respondent of its intention to exercise its right to suspend works as a result of the default in payment. After the effluxion of two business days after service of the notice the appellant suspended works on 28 March 2019 in accordance with the Security of Payment Act. Construction of works was never recommenced by the appellant, which resulted in RCP, in association with the respondent, issuing a 'show cause notice' on 20 March 2019. Despite 'without prejudice' meetings between the parties aimed at resolving the dispute the respondent issued a 'take out notice' on 29 April 2019 removing the remaining works from the hands of the appellant. At this stage the respondent commenced the proceedings before the primary judge seeking the orders referred to above. The respondent did not return the appellant's security after issuing the 'take out notice'. The issues on the appeal were: (i) Was the appellant entitled to continue to suspend works under the Security of Payment Act until payment of the outstanding interest. (ii) Was the 'show cause notice' valid due to the appellant's breaches of contract (iii) Was the 'show cause notice' valid where the respondent was involved in RCP's decision to issue the notices in circumstances where the power was conferred on RCP. Did RCP give adequate or proper consideration to the factual circumstances prior to issuing the 'show cause notice'. (iv) Did RCP give adequate or proper consideration to the appellant's response to the show cause notice and the factual circumstances prior to the respondent issuing the 'take out notice'. (v) Was RCP precluded from having regard to information obtained during a 'without prejudice' meeting which did not result in settlement of the dispute. (vi) Was the appellant entitled to the return of it security under clause 18.2 of the contract once the 'take out notice' was issued.
The Court of Appeal (White and Brereton JJA, Barrett AJA), dismissing the appeal, held:
Per White JA (Brereton JA and Barrett AJA agreeing at [182] and [183] respectively) As to issue (i) The right to suspend works arises were there has been a failure to pay a "scheduled amount". The definition of "scheduled amount" does not include interest payable under s 11 on the unpaid amount of a progress payment unless that amount is included in a "scheduled amount": [53], [63], [68], [69]. Building and Construction Industry Security for Payment Act 1999 (NSW), applied. Taylor v The Owners - Strata Plan No 11564 (2014) 253 CLR 531; Wentworth Securities Ltd v Jones [1980] AC 74, referred to. As to issue (ii) Due to the resolution of issue (i) in favour of the respondent the appellant was in breach by wrongly suspending its construction of works: [106], [107]. No error was shown in the primary judge's conclusion that the appellant was also in breach throughout the relevant period due to the failure of the appellant to achieve Practical Completion under the contract: [109], [117], [122], [126], [127], [132], [133], [139], [140]. As to issue (iii) The involvement of the respondent in issuing the 'show cause notice' did not invalidate the notice as RCP was satisfied that the notice should be issued and was satisfied with the grounds for the giving of the notice as stated in it: [79], [80]. It would be inconsistent with the respondent's rights under the contract and its right to see that its representative acts properly if it could not be involved in RCP's decision: [97]. RCP did not need to exercise its judgment independently of the Principal where RCP was genuinely satisfied with the notice as drafted by the respondent: [91]. As to issue (iv) RCP did give adequate and proper consideration to issuing the 'take out notice' as the evidence that RCP's officer reviewed and discussed the appellant's response to the 'show cause notice' was not successfully challenged: [157], [158]. There was no prejudgement or lack of consideration by RCP of the appellant's response to the show cause notice or the factual circumstances in reaching the required level of satisfaction for the respondent to issue the 'take out notice': [159], [162], [163]. As to issue (v) The 'without prejudice' privilege is not based upon an implied agreement that if the negotiations do not result in an agreement for settlement of the dispute, the parties will make no use of what has been disclosed by the other party in the negotiations: [167], [172], [173], [175], [176] Pihiga Pty Ltd v Roche [2011] FCA 240; (2011) 278 ALR 209; Unilever plc v The Proctor & Gamble Co [2001] 1 All ER 783; Cutts v Heads [1984] CH 290, referred to. As to issue (vi) This argument was dealt with in detail by the primary judge and no error was shown as to the primary judge's disposition of the argument in favour of the respondent: [179], [180].
Judgment
Grounds 1 and 2: no statutory right to suspension of work after 28 March 2019
Ground 3a.: Galileo's involvement in issuing the show cause notice
Ground 3(b): validity of the Show Cause Notice
Ground 4: validity of the take out notice
Ground 5: release of security
Conclusion
Amendments 09 September 2020 - Minor typographical errors corrected. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 09 September 2020
Duffy Kennedy Pty Ltd
Galileo Miranda Nominee Pty Ltd
(1957) 99 CLR 285
(2000) 203 CLR 579
(2011) 278 ALR 209
(1993) 45 FCR 84
(2014) 253 CLR 531
(1983) 153 CLR 52