Whether the conduct in the contempt proceeding is "substantially the same" as the conduct alleged in this proceeding, and what this comparison requires
59 In Australasian Meat Industry Employees' Union v Mudginberri Station Pty Ltd (1986) 161 CLR 98 at 107, in a longer passage dealing with the artificiality and inappropriateness of past distinctions made between conduct classified as civil contempt and conduct classified as criminal contempt, Gibbs CJ, Mason, Wilson and Deane JJ said :
The theoretical distinction between the two classes overlooks the underlying rationale of every exercise of the contempt power, namely that it is necessary to uphold and protect the effective administration of justice.
60 Disobedience to the court and interference with its processes, either through disobedience to orders or in the manner a person behaves, is central to any contempt:
Since, however, the question seems to resolve itself into this, whether you shall bend to the law, or the law shall bend to you, it is our duty to determine that the former shall be the case.
(Respublica v Oswald, 1 Dall 319, 329 (Pa, 1788) per McKean CJ, cited in N Lowe and B Sufrin, Borrie & Lowe The Law of Contempt (3rd ed, Butterworths, 1996) at p 2.)
61 These unique and central features of contempt are important in undertaking the comparison which s 553 requires.
62 Although I do not accept a solely fact-based approach can be taken to the task in s 553(1), given that, unlike CFMEU v Director of Fair Work, the current circumstances concern charges rather than convictions for contempt, the charges against the CFMEU in the contempt proceeding should in my opinion be taken into account. Together with the orders of Hollingworth J, on which the contempt charges proceed, they put the elements of the contempt "offence" in their factual context.
63 Hollingworth J made indorsed orders on 7 March 2013 and 5 April 2013. Boral alleges the CFMEU is in contempt of both orders. The charges brought by the Attorney were not in evidence. It is appropriate to reproduce her Honour's orders.
64 On 7 March 2013 her Honour ordered:
THE COURT ORDERS THAT
1. The requirements of rule 46.02 be dispensed with insofar as the plaintiffs seek injunctive relief in relation to sites in Victoria other than the construction sites referred to in the summons.
2. Until the trial of this proceeding or further order, the defendant (whether by itself, its officers, employees, agents or however so otherwise) be restrained from procuring, advising persuading, encouraging, inciting or counselling - or threatening to so procure, advise, persuade, encourage or counsel - any person who is employed or engaged to perform work, at any location in Victoria, that involves, or would normally involve, working with concrete supplied by either of the plaintiffs, to fail or refuse to perform that work, or to perform it otherwise in the manner in which it would customarily be performed.
3. By 12:00pm on Friday, 8 March 2013, the defendant (by a duly authorised person) must bring to the attention of all its delegates and shop stewards at Victorian construction sites the facts that these orders have been made and the contents thereof.
4. Without in any way limiting the effect of order 3 above, the defendant (by a duly authorised person) must, by 12:00pm on Friday, 8 March 2013, publish a statement - on the homepage of the Victorian/Tasmania branch of the defendant's Construction and General Division, and addressed to all employees, officers and members of the defendant - that they:
a. must perform any work that they are employed or engaged to perform at any location in Victoria that involves, or would normally involve, working with concrete supplied by either of the plaintiffs ("Boral or Alsafe") in the manner in which it would customarily be performed; and
b. must not procure, advise, persuade, encourage or counsel - or threaten to so procure, advise, persuade, encourage or counsel - any person who is employed or engaged to perform work, at any location in Victoria, that involves, or would normally involve, working with concrete supplied by Boral or Alsafe, to fail or refuse to perform that work, or to perform it otherwise than in the manner in which it would customarily be performed.
5. By 11:00am on Tuesday, 12 March 2013, the defendant, by a duly authorised person, must file and serve on the solicitors for the plaintiffs an affidavit setting out the steps taken by it to comply with paragraphs 3 and 4 of this order.
6. There is liberty to apply to the Honourable Justice Hollingworth.
7. Costs are reserved.
65 On 5 April 2013 her Honour ordered:
THE COURT ORDERS THAT:
Parties
1. Pursuant to rule 9.06 of the Supreme Court (General Civil Procedure) Rules 2005, the following persons be respectively added as the third to sixth plaintiffs to the proceeding and the writ be amended accordingly, namely:
a. Boral Bricks Pty Ltd (ACN 082 448 342);
b. Boral Masonry Ltd (ACN 000 223 718);
c. Boral Australian Gypsum Ltd (ACN 004 231 976); and
d. Boral Window Systems Ltd (ACN 004 069 523).
Injunctions
2. Until the trial of this proceeding or further order, the defendant (whether by itself, its officers, employees, agents or howsoever otherwise) be restrained from procuring, advising, persuading, encouraging, inciting or counselling - or threatening to so procure, advise, persuade, encourage or counsel - any person who is employed or engaged to perform work, at any location in Victoria, that involves, or would normally involve, working with products or services supplied by the plaintiffs (or any of them) to fail or refuse to perform that work, or to perform it otherwise than in the manner in which it would customarily be performed.
3. Until the trial of this proceeding or further order, the defendant (whether by itself, its officers, employees, agents or howsoever otherwise) be restrained from preventing, hindering or interfering with, or attempting to prevent, hinder or interfere with, the supply or possible supply of goods or services by the plaintiffs (or any of them) at any building or construction site in Victoria.
4. By 12:00pm on Tuesday, 9 April 2013, the defendant (by a duly authorised person) must bring to the attention of all its delegates and shop stewards at Victorian construction sites the fact that these orders have been made and the contents thereof.
5. Without in any way limiting the effect of order 4 above, the defendant (by a duly authorised person) must, by 12:00pm on Tuesday, 9 April 2013, publish a statement - on the homepage of the Victoria/Tasmania branch of the defendant's Construction and General Division, and addressed to all employees, officers and members of the defendant - that they:
a. must perform any work that they are employed or engaged to perform at any location in Victoria that involves, or would normally involve, working with products supplied by any of the plaintiffs ("Boral or Alsafe or Boral Concrete or Boral Quarries or Boral Bricks or Boral Masonry or Boral Plasterboard or Boral Windows") in the manner in which it would customarily be performed;
b. must not procure, advise, persuade, encourage or counsel - or threaten to so procure, advise, persuade, encourage or counsel - any person who is employed or engaged to perform work, at any location in Victoria, that involves, or would normally involve, working with products supplied by the plaintiffs, to fail or refuse to perform that work, or to perform it otherwise than in the manner in which it would customarily be performed;
c. must not prevent, hinder, or interfere with, or attempt to prevent, hinder, or interfere with, the supply or possibly supply of goods or services by the plaintiffs (or any of them) at any building or construction site in Victoria.
6. By 11:00am on Thursday, 11 April 2013, the defendant, by a duly authorised person, must file and serve on the solicitors for the plaintiffs an affidavit setting out the steps taken by it to comply with paragraphs 4 and 5 of this order.
Other orders
7. By 4.00pm on Friday, 19 April 2013, the plaintiffs file and serve an amended writ and statement of claim.
8. By 4.00pm on Friday, 17 May 2013, the defendant file and serve a defence and any counterclaim
9. By 4.00pm on Friday, 31 May 2013, the plaintiffs file and serve any reply to the defence and defence to any counterclaim.
10. By 4.00pm on Monday, 15 July 2013, the plaintiffs and defendant each file and serve their affidavits of discovery.
11. There is liberty to apply:
a. to a judge, in relation to any variation to the injunctions granted by the Honourable Justice Hollingworth on 28 February 2013, 7 March 2013 and 5 April 2013; and
b. to an associate judge, in relation to any other interlocutory steps.
12. Costs are reserved.
66 Boral then charges the CFMEU as follows:
STATEMENT OF CHARGES
An Order is sought that the defendant be punished for its contempt in breaching the orders of the Honourable Justice Hollingworth made on Thursday, 7 March 2013 (March Order) and Friday, 5 April 2013 (April Order) as alleged in each of the charges below.
1. In breach of paragraph 2 of the April Order, the defendant, between the approximate times of 12:00pm and 2:00pm on Thursday, 16 May 2013 at the Regional Rail Link construction site at Joseph Road Street, Footscray, Victoria (RRL Site), procured the failure, by a person or persons engaged or employed to deliver concrete supplied by the first plaintiff to that site at or during that time, to perform that delivery work.
PARTICULARS
At the time and place alleged, the defendant - by its employee, Mr Joseph Myles - organised, implemented, participated in, constituted and maintained a blockade of the entry to the RRL Site, which blockade was effected by means of the parking or positioning of motor vehicles across the corner of Joseph Road and Maribyrnong Street, Footscray so as to prevent, hinder or obstruct access to that site by concrete delivery vehicles; and, by so organising, implementing, participating in, constituting and maintaining, prevented persons who were engaged to deliver concrete supplied by the plaintiff to that site at the time or times over which that blockade remained in place (namely Mr Joe Faraci, Mr Nick Bouranis, Mr Cameron Powell and Mr Adrian Farfalla) from performing that work, or otherwise caused them not to perform it.
2. In breach of paragraph 3 of the April Order, the defendant, between the approximate times of 12:00pm and 2:00pm on Thursday, 16 May 2013 at the RRL Site, prevented the supply of concrete by the first plaintiff to that site.
PARTICULARS
At the time and place alleged, the defendant-by its employee, Mr Joseph Myles organised, implemented, participated in, constituted and maintained a blockade of the entry to the RRL Site, which blockade was effected by means of the parking or positioning of motor vehicles across the comer of Joseph Road and Maribyrnong Street, Footscray so as to render access to that site by concrete delivery vehicles impossible.
3. Alternatively to paragraph 2 above: in breach of paragraph 3 of the April Order, the defendant, between the approximate times of 12:00pm and 2:00pm on Thursday, 16 May 2013 at the RRL Site, interfered with the supply of concrete by the first plaintiff to that site.
PARTICULARS
At the time and place alleged, the defendant- by its employee, Mr Joseph Myles organised, implemented, participated in, constituted and maintained a blockade of the entry to the RRL Site, which blockade was effected by means of the parking or positioning of motor vehicles across the comer of Joseph Road and Maribyrnong Street, Footscray so as to render free access to that site by concrete delivery vehicles impossible.
4. In breach of paragraph 6 of the April Order, the defendant did not, prior to the deadline by which it was required by that order to do so - namely, 11:00am on Tuesday Thursday, 11 April 2013 - fi1e and serve on the solicitors for the plaintiffs an affidavit setting out what, if any, steps it took by way of compliance with paragraphs 4 and 5 of the April Order.
5. In breach of paragraph 4 of the March Order, the defendant did not, prior to the deadline by which it was required by that order to do so - namely, 12 noon on Friday, 8 March 2013 - publish a statement, on the homepage of the Victoria/Tasmania branch of its Construction and General Division, setting out the matters specified in paragraph 4(a) and (b) of the March Order.
6. In breach of paragraph 5 of the March Order, the defendant did not, prior to the deadline by which it was required by that order to do so - namely, 11:00am on Tuesday, 12 March 2013 - file and serve on the solicitors for the plaintiffs an affidavit setting out what, if any, steps it took by way of compliance with paragraphs 3 and 4 of the March Order.
67 The summons and charges are exhibited to Mr Clayton's affidavit filed in this application. The summons expressly seeks that the CFMEU be "punished" for contempt, and there is no dispute between the parties that Boral alleges contumacy and will seek conviction and punishment so as to prove that the contempt it alleges the CFMEU committed was criminal in character. There is no dispute that the Attorney-General makes allegations of the same nature.
68 The elements of a contravention of s 348 of the Fair Work Act are:
A person organises or takes "action" (including, read with s 12 of the Fair Work Act, an omission);
Alternatively a person threatens to organise or take "action";
The "action" is against another person; and
There is intent to coerce the other person, or a third person, to engage in industrial activity, as that is defined in s 347.
69 The statement of claim in the current proceeding relevantly alleges a contravention of s 348 of the Fair Work Act by reference to the events of 16 May 2013 in the following way:
Events of 16 May 2013
10 As at 16 May 2013, John Holland and Abigroup, in their capacity as Construction Joint Venturers:
(a) had scheduled the construction of a deflection wall for 16 May 2013;
(b) had engaged Boral Resources (Vic) Pty Ltd trading as Boral Concrete (Boral) to supply the 130 cubic meters of wet concrete needed for the wall structure, to be delivered by concrete trucks arriving in approximately 10 minute intervals over the 3 to 4 hour period (16 May concrete pour);
(c) had engaged and scheduled the following subcontractors to provide labour at the Site on 16 May 2013 for the construction of the wall and the associated 16 May concrete pour:
1) Clifton Formwork (Vic) Pty Ltd (Clifton Formwork), to undertake formwork and vibrating of the concrete being poured
2) ICPS Melb Pty Ltd (ICPS), to pump the concrete delivered by Boral; and
3) Summit Concrete Pumping Pty Ltd (Summit), to pump the concrete delivered by Boral;
(d) employed a number of employees on the Site to undertake the work being performed on the Site on this day.
11 On 16 May 2013:
(a) at around 7:00am, five employees of Clifton Formwork, arrived for work at the site;
(b) at around 9:00am, four employees of ICPS (two pump operators and two hose operators) arrived at the Site with two concrete boom pumps to pump the concrete to the wall structure;
(c) at around 8.30am, four employees of Summit arrived at the Site to perform concrete pumping work;
(d) at around 11:20am, the first Boral concrete truck arrived at the Site and the concrete pour commenced;
(e) by 11:50am, four Boral concrete trucks had delivered approximately 24.4 of the 130 cubic meters of concrete that was to be poured that day.
12 On 16 May 2013:
(a) at around 12:00 noon, Myles and approximately 15 to 20 other people, including other officials of the CFMEU, Drew McDonald and Shaun Reardon, and other members of the CFMEU:
1) arrived at Josephs Road in several cars and parked them across the width of the street outside the entrance gate, blocking vehicle access to the Site;
2) stood around the vehicles on the road.
(b) Summerfield approached Myles and asked what he was doing to which Myles responded sarcastically with words to the effect of "we've lost our keys and are waiting for the RACV";
(c) within 30 minutes, several Boral trucks with deliveries of wet concrete for the 16 May concrete pour were parked up Josephs Road, unable to access the pumping equipment on Site to unload the concrete;
(d) at approximately 12.30pm, Summerfield again approached Myles who was still standing around the parked cars on Joseph Street, and they had a conversation the substance of which was as follows:
"Myles: I haven't got a delegate on site to protect my members so I'm blocking the road.
Sunmerfield: The Alliance has an AWU delegate, we don't need a CFMEU delegate. We are under an AWU Agreement.
Myles: I will only remove the blockade if you stop the pour and pack the concrete pumps up."
(e) the conduct alleged at sub-paragraph 12(a) continued until around 2.30 pm.
(f) at around 2:30pm, the people standing around the vehicles which were blocking the site had a discussion, shook hands, posed for a photograph with a CFMEU banner then left the Site in their vehicles;
(g) before leaving Josephs Road, Myles spoke to Summerfield and threatened to do the same thing again the next day and to continue to stop concrete pours until Summerfield relented and put a CFMEU delegate on the Site, saying words to the following effect:
'I'll be back tomorrow to stop the concrete pour" and "You won't pour again until you put a delegate on and Ralph Edwards is happy".
13 By reason of the matters alleged in paragraph 12, the access to the Site for the Boral concrete trucks was blockaded for approximately 2.5 hours.
14 The blockade had the following consequences:
(a) only approximately 24.4 cubic metres of concrete had been poured;
(b) the rest of the 130 cubic metres on order to complete the construction of the wall could not be delivered;
(c) the work had to be abandoned that day;
(d) the building works were disrupted and delayed and there were wasted construction costs incurred.
Particulars
The wall could not be completed until after 17 May 2013.
The 24.4 cubic metres of concrete already poured on 16 May 2013 was wasted. Aside from the costs of the delivery of that concrete and the labour assigned to it, there were additional costs incurred in demolishing and disposing of it.
Notwithstanding the order with Boral was cancelled shortly after 12 noon on 16 May 2013, there were the costs of an additional 45 cubic metres which already been dispatched to the Site which could not be used.
Further particulars of any costs incurred by John Holland, Abigroup or any other of the Package B Project Alliance participants as a result of the disruption and delay will be provided closer to trial.
…
Contraventions of the FW Act
Section 348
16 By reason of the matters alleged at paragraph 12 herein, on 16 May 2013, Myles:
(a) organised the blockade of access to the Site;
(b) advised, encouraged or incited the blockade,
to stop the concrete pour.
17 Further, by reason of the matters alleged at sub-paragraph 12(g) herein, at approximately 2.30 pm on 16 May 2013, Myles threatened that he would organise, procure and otherwise advise, encourage or incite a continuation of the blockade of access to the Site to stop any concrete pour if John Holland or Abigroup did not comply with the CFMEU Delegate Request.
…
19 Myles took the action alleged in paragraphs 12 and 15, and issued the alleged threats alleged at paragraphs 12(g) and 15, with intent to coerce John Holland or Abigroup into complying with the CFMEU Delegate Request.
Particulars
The Applicant relies on s 362 of the FW Act to attach to Myles the conduct of the other participants in the blockade.
To the extent necessary, the Applicant also relies on sections 360 and 361 of the FW Act.
…
70 Paragraph 21 of the statement of claim pleads the conduct of Mr Myles, the second respondent to this proceeding, is by reason of the operation of s 363 of the Fair Work Act the conduct of the CFMEU.
71 It is common ground that s 553 has no operation in relation to Mr Myles. The statement of claim also makes allegations about events on 17 May 2013. It is common ground these allegations cannot be stayed by operation of s 553.
72 It is clear that the submission of senior counsel for the respondents that the blockade is a factual focus in both proceedings is correct. Notwithstanding the common focus in terms of the sequence of events at the blockade, I do not accept the conduct constituting the contempt is substantially the same as the conduct in relation to which a civil penalty order would be made.
73 The gravamen, and the most critical elements, of the contempt proceeding is the respondents' conduct in breaching a Court order, and doing so contumaciously. In the Grocon and Boral appeal, the Court of Appeal (at [144]-[153]) noted the cases suggest there is a difference between acts which are wilful and those which are contumacious, the former indicating a deliberate choice, but the latter requiring something more. The "something more" has been variously described as "perverse obstinate resistance to authority" (Australasian Meat Industry Employees' Union v Mudginberri Station Pty Ltd (1985) 9 FCR 194 at 207 per Smithers and Northrop JJ) or a "conscious defiance of the court's authority" (Mosman Municipal Council v Kelly (No 3) (2009) 167 LGERA 91; [2009] NSWLEC 92 at [72] per Biscoe J). For the purposes of the determination of this application it is not necessary to engage in the analysis undertaken by the Court of Appeal about how, if at all, the presence of an allegation of contumacy may transform a civil contempt to a criminal contempt, and whether the seeking of a conviction for a contempt alleged to be contumacious means what is being conducted is a criminal proceeding.
74 Those elements are unique to contempt and find no place in a civil penalty provision such as s 348.
75 The breach of the orders of Hollingworth J concerns the CFMEU interfering with the supply of concrete by Boral to the Regional Rail Link site, or "procuring" the failure to deliver the concrete. The other charges could not possibly be said, and are not said, to relate to the s 348 contravention (such as not filing an affidavit of compliance).
76 In contrast, s 348 concentrates on conduct which can be described as "coercion" of another person to engage in industrial activity. The coercion may involve illegitimate conduct. The applicant accepted this was possible by reference to Victoria v Construction, Forestry, Mining and Energy Union (2013) 218 FCR 172; [2013] FCAFC 160 at 90-92. However, the presence of such illegitimacy is not an element of s 348.
77 The coercion must concern industrial activity. The phrase "engages in industrial activity" is defined in s 347 of the Fair Work Act, which provides:
347 Meaning of engages in industrial activity
A person engages in industrial activity if the person:
(a) becomes or does not become, or remains or ceases to be, an officer or member of an industrial association; or
(b) does, or does not:
(i) become involved in establishing an industrial association; or
(ii) organise or promote a lawful activity for, or on behalf of, an industrial association; or
(iii) encourage, or participate in, a lawful activity organised or promoted by an industrial association; or
(iv) comply with a lawful request made by, or requirement of, an industrial association; or
(v) represent or advance the views, claims or interests of an industrial association; or
(vi) pay a fee (however described) to an industrial association, or to someone in lieu of an industrial association; or
(vii) seek to be represented by an industrial association; or
(c) organises or promotes an unlawful activity for, or on behalf of, an industrial association; or
(d) encourages, or participates in, an unlawful activity organised or promoted by an industrial association; or
(e) complies with an unlawful request made by, or requirement of, an industrial association; or
(f) takes part in industrial action; or
(g) makes a payment:
(i) that, because of Division 9 of Part 3 3 (which deals with payments relating to periods of industrial action), an employer must not pay; or
(ii) to which an employee is not entitled because of that Division.
78 Here the industrial activity is pleaded in the statement of claim as the "CFMEU delegate request": namely that the CFMEU wanted one of its delegates put on the Regional Rail Link site, where there was at the time only an Australian Workers' Union delegate and the site Superintendent (an employee of John Holland) insisted this was sufficient given the relevant enterprise agreement was with the AWU. If found guilty of contempt in the Supreme Court, the CFMEU will be punished for the "conscious defiance" of Hollingworth J's orders; not any coercion of a person to engage in industrial activity.
79 Thus, the gravamen of the contravention of s 348 is the using of coercion to obtain an industrial outcome, being the presence of a CFMEU organiser on the Regional Rail Link site. None of this forms any part of the elements of the contempt proceeding, even if one descends to a factual level. Another important distinction is that Boral is one of the prosecutors in the contempt proceeding because its concrete deliveries were subject to alleged interference. In the civil penalty proceedings the "coercion" is alleged to be of John Holland and Abigroup, not Boral. The necessary comparison reveals that in no sense would the CFMEU be punished twice for the same conduct, if it were convicted of the contempt charges and also found to have contravened s 348. It would be punished for deliberate defiance of a court order on the one hand, and for coercion of John Holland and Abigroup to accept the placement of a CFMEU delegate on its worksite on the other.
80 For those reasons, the terms of s 553(1) are not made out and there is no stay of the civil penalty aspect of the current proceeding.