Indemnity Costs based on the Offer of Compromise
16The alternative claim the plaintiff makes is based upon the Offer of Compromise claimed to be served pursuant to Uniform Civil Procedure Rules (UCPR), r 20.26. The Offer of Compromise served on 27 June 2011 is annexed to the affidavit of Francis Farmakidis of 14 June 2012. It followed a strong 12 May 2010 plaintiffs' letter of complaint about the defendant's progress of the proceedings.
17The plaintiffs claim the Offer of Compromise complies with UCPR, r 20.26 and that the plaintiff has done better than that offer and should receive indemnity costs. The Offer of Compromise provided:-
"1. The Plaintiffs offer to compromise all of their claims in these proceedings on the following terms:
(a) the Defendant pay the Plaintiffs the sum of $90,000 plus costs as agreed or assessed;
(b) the parties consent to the making of the following order by the Court, namely that the Defendant be restrained from allowing the roots from any of the 3 fig trees growing in the verge between the Plaintiffs' land and Florence Avenue or Vernon Avenue, Eastlakes, to encroach onto the Plaintiffs' land as to cause a nuisance.
2. This Offer of Compromise shall remain open for a period of 28 days."
18The issues on this matter the defendant raises are: (1) this was not an Offer of Compromise complying with UCPR, r 20.26; (2) in the alternative, it did not qualify as a Calderbank letter; and (3) it was not unreasonable of the defendant to refuse to accept the Offer of Compromise. So the defendant argues an indemnity costs order should not be made against it.
19One of the fundamentals of compliance with UCPR, r 20.26 is that the plaintiffs must obtain a result better than the offer of compromise. The plaintiffs did obtain a result better than the Offer of Compromise here. The damages awarded were $124,352, compared with the $90,000 in the offer. On any view, the passage of time of about 12 months from the expiry of the Offer of Compromise would not account for the difference between those two amounts. In my view the plaintiff has bettered the money component of the Offer of Compromise. Also the injunction obtained at trial was more extensive than that offer in the Offer of Compromise.
20Also it does contain a genuine compromise when it is compared with the full amount of the plaintiffs' claim then being made. That claim included, among other things, the affidavit of Salvatore Di Bartoli of 25 February 2011 which identified and estimated building costs and the notified claim for loss of amenity that significantly exceeded the offered amount of $90,000.
21So the first question becomes did the Offer of Compromise comply with UCPR, r 20.26. The second question is, if it did, was it unreasonable of the defendant not to accept it.
22In my view the Offer of Compromise does comply with UCPR, r 20.26, because the plain effect of the document is consistent with the operation of UCPR, r 20.26. So much is clear from Vieira v O'Shea (No 2) [2012] NSWCA 121 at [7] which explains that, although an offer does not declare itself to be "exclusive of costs", a mere reference to costs in an offer otherwise complying with the part will not take the offer outside the rules, unless the reference operates inconsistently with the relevant costs rule. In my view, construed in a commonsense way, this offer does not operate inconsistently with UCPR, r 20.26 and is therefore compliant. It is not therefore necessary to answer the question of whether the offer of compromise might work in the alternative in the Calderbank letter.
23The final question is: was it unreasonable of the defendant not to accept the offer of compromise? In my view it was unreasonable of the defendant not to accept the offer. It should have been accepted and indemnity costs will be awarded from 28 days after the date of that offer.
24The applicable principles are clear. The court must consider the factors relevant to determining whether the rejection of offer was unreasonable on a wide basis including those matters set out in Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover Authority (No 2), [2005] VSCA 298 and Miwa Pty Ltd v Siantan Properties Pty Ltd (No 2) [2001] NSWCA 344. Those relevant factors include:
(a) the stage of the proceeding at which the offer was received;
(b) the time allowed to the offeree to consider the offer;
(c) the extent of the compromise offered;
(d) the offeree's prospects of success, assessed as at the date of the offer;
(e) the clarity with which the terms of the offer were expressed;
(f) whether the offer foreshadowed an application for indemnity costs in the event of the offeree's rejecting it.
25There are many reasons why the Offer of Compromise should have been accepted in this case and it was unreasonable of the defendant to have rejected it. There had been lengthy correspondence between the parties over 10 years, in which the plaintiffs had pointed out the detail of their problems to the defendant. This correspondence is fully detailed in my principal judgment between paragraphs [12] and [52]. The defendant had plenty of opportunity before June 2011 to investigate the problems the plaintiffs' had brought to attention.
26Next there was in the history of contact between these parties a number of implicit concessions of tree root penetration by the defendant identified in my principal judgment. All of these matters indicate a degree of knowledge on the part of the defendant of the existence of a genuine problem and a long standing opportunity to investigate the plaintiffs' claims over a very long period of time. It behoved the defendant in my view when this offer of compromise was served after such a long time, to take a considered decision to act upon it.
27Moreover, enough of the quantum and technical evidence had been served on the defendant in my view for it to take a fair and considered view of the offer. There had been arborist's reports served on the defendant in 2008 as the history in the principal judgment shows. The Di Bartoli report of 25 February 2011 had also been served by then. The defendant criticised the February 2011 Di Bartoli report as not having set out a detailed description of the amounts of money the plaintiffs' claimed. But in my view the Di Bartoli report is broken up in a way that was quite close to the final evidence given in the proceedings, although it was expanded later.
28True it was that the engineering and arborist's reports were served after the expiry of the offer. But in my view, looking at the matter in terms of what was served and what technical evidence was available to the defendant, there was enough for the defendant to act on the offer and it should have done so.
29For those reasons therefore I will award the plaintiff indemnity costs in these proceedings from a date 28 days after 27 June 2011. I order the defendant to pay the plaintiffs' costs on an indemnity basis from 25 July 2011.