Grounds 7 and 8 - the application of s 556
26 These two grounds concern the declarations and penalty orders made against Mr Collier (ground 7), and in relation to the consequential liability of the CFMMEU arising from Mr Collier's conduct (ground 8) in relation to his contraventions of s 494 (entry without a permit) and s 343 (coercion) arising out of the disruption of a concrete pour at the Rhodes site on 11 March 2015, including using CFMMEU cars to block access to that site. On that day, some 30 concrete trucks were scheduled to deliver 220 cubic metres of concrete to build nine columns and the floor of a podium ([LJ [152]). The end result was that all, or at least a significant part, of the concrete that was able to be poured that day later had to be jackhammered out and repoured. In substance, no productive work was able to be carried out in relation to the concrete pour that day, which was an event that must have involved considerable time, including planning, scheduling and coordination given the scale involved, all of which would have to be repeated if the same was to be carried out on another day. The primary judge found that there were no genuine safety concerns to justify the conduct on that day. His Honour imposed on Mr Collier a penalty of $8,000 for the s 494 contravention and $8,000 for the s 343 contravention, and on the CFMMEU a penalty of $30,000 for the s 494 contravention and $30,000 for the s 343 contravention.
27 The appellants' complaint, in substance, is that the s 494 contraventions were either wholly or substantially covered by the s 343 coercion contraventions, such that s 556 had to apply and dual penalties were not permissible. The appellants submit that the primary judge appeared not to have considered the application of s 556, a point that appears to have substance at first blush when close regard is had to the content of LJ [104]. The appellants rely upon the pleaded conduct to ground the s 494 contravention and to ground the s 343 contravention, characterising the pleading as follows:
(1) the same conduct is pleaded to ground the s 494 contravention (TFASOC [100]-[101A]) and the s 343 contravention (TFASOC [133(c)] and [140]);
(2) the pleaded conduct as to s 343 included entry to the site, a request to Mr Collier to produce his right of entry card, him refusing to leave and him raising safety concerns (TFASOC [57] and [60] as imported by [133(c)]);
(3) s 556 was therefore engaged, as submitted to the primary judge.
28 In support of these grounds, the appellants also relied upon Australian Building and Construction Commissioner v Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union (The Australian Paper Case) (No 2) [2017] FCA 367. Specifically, the appellants submitted that The Australian Paper Case contemplates a crossover with respect to the conduct relied upon and such a "crossover" was, at the very least, also present in this case. The appellants, however, submitted that it went further in this case in that the conduct relied upon for the purposes of s 343 "subsumes" the conduct relied upon for the purposes of s 494.
29 In response, the Commissioner submitted that s 556 operates by reference to particular conduct and, accordingly, if a conclusion is reached that the particular conduct giving rise to the separate contraventions, though there might be an overlap between them, has some qualitative difference to it, then it was open to the primary judge to conclude that there were two contraventions each arising from discrete aspects of Mr Collier's conduct. The Commissioner contended that this was the effect of the primary judge's finding in PJ [102]-[103], where the primary judge described the conduct of Mr Collier that constituted the contraventions as including the following:
• entry upon the Rhodes Site on 11 March 2015 without an entry permit (s 494); and
• involvement on 11 March 2015 at the Rhodes Site in the parking of a car across the driveway preventing access of concrete trucks and his initial refusal to move the vehicle (s 343); and
• entry upon the Wolli Creek Site on 12 March 2015 without an entry permit (s 494).
30 While the Commissioner accepted that there was some "crossover" in this conduct, he submitted that the primary judge was in the best position to make an assessment of that conduct, particularly having regard to the fact that his Honour heard all of the evidence during the course of the liability hearing. He submitted that no error is disclosed in the primary judge's findings above in circumstances where the two contraventions arose from two discrete aspects of Mr Collier's conduct, namely that:
(1) the contravention of s 494 related to Mr Collier's conduct in unlawfully entering the Rhodes site without the necessary entry permit;
whereas
(2) the contravention of s 343 related to Mr Collier's conduct in the unlawful parking of a vehicle across the driveway to Gate 3 preventing access of concrete trucks, as well as his initial refusal to move the vehicle.
As such, the Commissioner submitted that the conduct underpinning the two contraventions was distinct and did not constitute the same "particular conduct" as that term is used in s 556.
31 In reply, the appellants submit that the Commissioner's submissions fail to grapple with the point raised by these grounds of appeal, namely that the contraventions are categorised by reference to the case as pleaded, in which the contraventions are not expressed in a way that is distinct. In support of this argument, the appellants point out that the primary judge at PJ [102] found that Mr Collier entered the site for the purpose of being as disruptive as possible to the activities then being undertaken and on that basis was found to have contravened s 494. That same disruptive conduct was then relied upon in finding the contravention of s 343. The appellants therefore submit that the primary judge gave no regard, or at least insufficient regard, to the identification of the relevant "particular conduct" that gave rise to each contravention, noting that his Honour was required to ensure that the contraveners were not penalised twice for the same conduct, citing by analogy Pearce v The Queen [1998] HCA 57; (1998) 194 CLR 610 at [40].
32 After judgment was reserved in this appeal, the parties drew our attention to the subsequent Full Court judgment in Construction, Forestry, Maritime, Mining and Energy Union v Australian Building and Construction Commissioner [2019] FCAFC 201 (Hassett). That appeal concerns contraventions of ss 499 and 500 of the Fair Work Act. Its relevant factual background and the outcome before the primary judge were summarised by the Full Court as follows (at [6]-[9]):
6 … The respondent made allegations to the effect, and the appellants admitted, that on 5 June 2017, whilst in attendance at a construction site in Devonport, Tasmania:
(i) Hassett climbed on a crane whilst it was in operation;
(ii) Hassett refused a request of the occupier at the site to get off the crane (which request was reasonable because it was unsafe to be on the crane whilst it was being operated - that conduct is defined in the Amended Statement of Claim as the "5 June OHS Request"); and
(iii) Hassett used insulting language and engaged in abusive behaviour.
7 By reason of the conduct in (i), the appellants were found to have contravened s 499 of the [Fair Work Act]. By reason of the conduct in (i), (ii) and (iii), the appellants were found to have contravened s 500 of the [Fair Work Act].
8 The appellants contended before the primary judge that because Hassett's conduct that established the contravention of s 499 (refusing the reasonable request to get off the crane) was also an element of the contravention of s 500, s 556 applied and only one penalty could be imposed on each of the appellants in relation to that particular conduct.
9 The primary judge rejected that contention. At [48]-[50] of his Honour's reasons for judgment, the primary judge referred to the reasoning of Tracey J in Australian Building and Construction Commissioner v Construction, Forestry, Maritime, Mining and Energy Union (No 2) [2018] FCA 1211 at [40]-[43], and in essence, concluded that the conduct constituting the contravention of ss 499 and 500 was not the same conduct for the purposes of s 556 because of the more expansive nature of the conduct constituting the contravention of s 500.
33 In concluding that the primary judge had erred, the Full Court addressed three issues as follows:
(1) the meaning of the expression "particular conduct" in s 556 of the Fair Work Act (at [12]-[16]);
(2) what is covered by the word "conduct" in s 556 (at [17]-[26]); and
(3) whether the penalties applied were appropriate to the two contraventions concerned (at [27]-[31]).
34 The third issue above is not pertinent for present purposes. On the first issue, the Court noted (at [15]) that the primary judge:
… construed s 556 as though "particular conduct" meant the whole of the conduct the subject of a contravention and a consequent pecuniary penalty. It was because the whole of the conduct relevant to the s 500 contravention was larger or more expansive than the conduct the subject of the s 499 contravention (Hassett's refusal to get off the crane), that his Honour concluded that s 556 was not engaged …
35 The Full Court considered his Honour had erred in this construction. It explained that error in the following terms (at [16]):
Hassett's refusal to get off the crane was relevantly the "particular conduct" for s 556 purposes. That particular conduct was part of and was subsumed by, the whole of the conduct the subject of the contravention of s 500. Where that particular conduct was the subject of penalty in relation to a contravention of s 500, s 556 precluded that particular conduct being the subject of a penalty in relation to the contravention of s 499 of the [Fair Work Act].
36 The reasoning the Full Court partly relied upon to reach this conclusion focused on the word "particular" in the expression "particular conduct" and the expression "in relation to", both of which appear in s 556. With respect to the latter, it observed (at [14]) that:
… The purpose of that phrase is to make it clear that the provision is addressing "particular conduct" that is the subject of the penalty imposed, and not necessarily all of or the whole of the conduct for which the penalty was imposed. Where that particular conduct is the subject of a pecuniary penalty, s 556 requires that that particular conduct not be the subject of a further pecuniary penalty.
37 On the second issue, the Full Court adopted the reasoning of Jessup J in The Australian Paper Case at [40] (Hassett at [18]-[19]) and rejected the respondent's argument based on common law principles of double jeopardy that his Honour's construction of s 556 was erroneous (at [20]-[25]). On this issue, the Full Court concluded (at [26]) that:
We respectfully adopt the construction of s 556 applied in The Australian Paper Case. Contrary to the submission advanced on behalf of the respondent and with respect to Jessup J, that construction is not plainly wrong, and in our view it is correct. It accords with the plain meaning of the words by which the section is expressed and also the underlying policy considerations to which we have referred. The "particular conduct" to which s 556 refers is the constituent act or omissions that a wrongdoer has committed - that is, what he or she (or it) actually did.
(Emphasis in original)
38 We do not accept that the same conduct was relevantly pleaded in support of both contraventions. To the contrary, the conduct pleaded in the paragraphs to which the appellants have referred is, in our view, materially different as between the two contraventions. Nor do we accept that the conduct constituting the contravention of s 494 was wholly subsumed in the conduct constituting the contravention of s 343. In our view, the primary judge was well aware that there were distinct and separate components of the conduct constituting each of those contraventions. So much is apparent from his Honour's conclusion at PJ [104] that the contraventions on 11 and 12 March 2015 should attract separate penalties because of "the very different conduct pursued by Mr Collier, in particular on 11 March 2015" and because "[t]he conduct on those two days was not the same 'particular conduct' for the purposes of s 556" (emphasis in original). At PJ [102], the primary judge demonstrated why that was so by summarising, by reference to various paragraphs of the liability judgment (LJ [159], [187] and [285]), the components of Mr Collier's conduct that constituted the contraventions of s 494 of the Fair Work Act, namely purporting to exercise a State or Territory occupational health and safety right on both sites on both days when he was not a permit holder under the Fair Work Act. His Honour then proceeded, at PJ [103], to contrast that conduct with the conduct constituting the contravention of s 343 by summarising, by reference to various separate paragraphs of the liability judgment (LJ [173], [179], [182], [234] and [289]), the very different conduct that constituted that contravention, namely engaging in coercive conduct at the Rhodes site on 11 March 2015 by parking a vehicle across Gate 3 at that site and thereby obstructing the entry of cement trucks to the site. The Commissioner is therefore correct in his contention that the conduct underpinning the two contraventions was distinct and did not constitute the same "particular conduct" as that term is used in s 556 of the Fair Work Act. In our view, nothing that the Full Court said in Hassett detracts from this conclusion. To the contrary, its treatment of the reasoning of Jessup J in The Australian Paper Case at [40] is entirely consistent with it.
39 For these reasons, grounds 7 and 8 must fail.