© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] WASC 398
Supreme Court of WA
2020-11-04
Martin J
Original judgment source is linked above.
(a) the effect of an amendment on the Court and on other litigants is relevant;
(b) there is no right to amend to introduce an arguable case and it is wrong to say that only in extreme circumstances would a party be shut out from litigating an arguable case;
(c) justice requires that parties have a proper opportunity to plead their case, but limits may be placed on repleading when delay and cost are taken into account;
(d) a just resolution does not mean that a party will always be permitted to raise any arguable case at any point in the proceedings, on payment of costs, even indemnity costs;
(e) the inevitable strains of litigation must be taken into account in weighing the adverse consequences of delay ‑ this applies to natural persons and other litigants;
(f) the nature and importance of the amendment to the party amending must be taken into account;
(g) attention must be given to the extent of the delay, and the costs associated with it, the prejudice which might reasonably be assumed to follow from it and any prejudice that is shown;
(h) the point in the litigation relative to a trial may be an important consideration;
(i) where a discretion is sought to be exercised in favour of a party, an explanation will be called for;
(j) the point can be reached where a party has had a sufficient opportunity to put its case;
(k) Order 1 rule 4A provides that a goal of the Supreme Court practice and procedure is the elimination of delay; and
(l) Order 1 rule 4B provides for the principles of caseflow management including (a) the just determination of litigation, as well as the following (which are, in any event, aspects of (a)); (b) the efficient disposition of the Court's business, the efficient use of judicial resources; the timely disposal of business, and proportionality.
The remaining disputed amendments in the Proposed FASOC
Brief recap of the relevant clauses of the CPOA
Purchase Consideration shall mean US$200,000,000 (two hundred million US dollars) for each and every Sale Interest, plus the CPI Increase from the 1 March 2006 until the date of transfer of any Sale Interest in respect of a Further Company, under any option set out in this Agreement. The Purchase Consideration for the first or subsequent Sale Interests will be reduced by the amount which CITIC spends to comply with the Drilling Obligation.
3.3 The exercise price for the First Option will be the Purchase Consideration.
CPI Increase means US$200,000,000 x (CPI2 ‑ CPI1)
CPI1
Where CPI1 is the last published CPI figure before 1 March 2006 and CPI2 is the last published CPI figure before the date of completion of a Takeover Agreement.
Dear Colleagues
RE: China Project Operation Agreement (CPOA) ‑ Mineralogy Pty Ltd ats CITIC Ltd (CIV1514/2016)
[1] We refer to the China Project Option Agreement dated 22 October 2008 and to Supreme Court of Western Australia Proceeding CIV1514 of 2016.
[2] We write this letter on behalf of Mineralogy Pty Ltd.
[3] We are authorised to send this letter on behalf of Mr Palmer.
[4] We advise that Mineralogy and Mr Palmer (defendants) withdraw the contention that the CPOA has been terminated. The defendants are ready, willing and able to perform the CPOA.
[5] We advise that completion of the First Option will occur consistently with the following paragraphs.
[6] Mineralogy will advise that the Further Company will be Balmoral Iron Pty Lt d.
[7] Mineralogy will advise that the Seller will be Mineralogy.
[8] We understand from CITIC Ltd's previous communications that Cape Preston Resource Holdings Pty Ltd (CPRH) would be the purchaser under the CPOA. If that is not correct, please let us know. Assuming CPRH will be the purchaser, it will acquire the issued shares in Balmoral Iron.
[9] Mineralogy is a party to the following agreements with Balmoral Iron (and other parties, as the case may be):
(a) Mining Right and Site Lease Agreement dated 21 March 2006 (Balmoral MRSLA);
(b) Deed of Variation to the Balmoral MRSLA dated 30 March 2006;
(c) Facilities Deed dated 26 October 2001 (Balmoral Facilities Deed);
(d) Variation to the Balmoral Facilities Deed dated 21 March 2006;
(e) a Fortescue Projects Consolidation Agreement dated 26 October 2001;
(f) Variation Deed to the Fortescue Projects Consolidation Agreement dated 7 February 2003;
[10] Mineralogy will enter into the following instruments with Balmoral Iron in accordance with clause 3.6(c)(i) of the CPOA :
(a) a Fortescue Coordination Deed or, in good faith performance, will become a party on the same terms to the Fortescue Coordination Deed dated 22 October 2008;
(b) an Amendment Deed amending the Balmoral MRSLA to be on the same terms as the Sino Iron MRSLA;
(c) a Variation Deed amending the Balmoral Facilities Deed to be on the same terms as the Sino Iron Facilities Deed.
[11] Mineralogy will advise that Balmoral Iron does not have any assets and therefore does not need to dispose of any assets under clause 3.6(c)(ii) of the CPOA.
[12] Mr Clive Palmer will enter into a Deed of Guarantee with CPRH and CITIC as required by subparagraph (b) of Schedule 3 of the CPOA. The Deed of Guarantee will include an indemnity from Mr Palmer in respect of claims against or liabilities of Balmoral Iron arising before its acquisition by CPRH.
[13] The parties will enter into a Takeover Agreement in substantially the same form as the Korean Steel Takeover Agreement as required by clause 3.6(f) of the CPOA.
[14] The parties will use their reasonable endeavours in good faith to obtain FIRB approval for the acquisition of the shares in Balmoral Iron Pty Ltd as required by clause 8 of the CPOA.
Documents
[15] In good faith, we enclose for your attention:
(b) Deed of Variation to the Balmoral MRSLA dated 30 March 2006;
(f) draft Amendment Deed amending the Balmoral MRSLA to be on the same terms as the Sino Iron MRSLA;
(g) draft Variation Deed amending the Balmoral Facilities Deed to be on the same terms as the Sino Facilities Deed;
[16] We also enclose audited financial statements for Balmoral Iron for the year ending 30 June 2020.
Purchase Consideration
[17] The Purchase Consideration under the CPOA will be USD$135,207,177.77. We have accepted your calculation regarding drilling costs to remove any conflict between the parties.
[18] The calculation of the Purchase consideration is included in Annexure A to this communication.
Clear exit
[19] We advise that Balmoral Iron has been a member of the Mineralogy Pty Ltd tax consolidated group from 1 July 2003 until 16 December 2018 and of the Mineralogy International Limited tax consolidated group from 16 December 2018 until the present time. Mineralogy became a wholly‑owned subsidiary of Mineralogy International Limited on 16 December 2018 and pursuant to a choice made under subsection 615‑30(2) of the ITAA 1997 Mineralogy International Limited became the head company of the consolidated group from [t]his time.
[20] Mineralogy had a valid Tax Sharing Agreement in place for income tax purposes which was entered into on 21 March 2006 which included Balmoral Iron as a contributing member. On 26 March 2019 a new Tax Sharing Agreement with Mineralogy International Limited as the head company was entered into to reflect the 16 December 2018 restructure. Balmoral Iron is also a contributing member under this Tax Sharing Agreement.
[21] The Tax Sharing Agreements provide for a clear exit from group tax‑related liabilities where a contributing member will cease to be a member of the consolidated group. It is proposed that Balmoral Iron, as a contributing member, will on sale exit from the Mineralogy International Limited tax consolidated group under the clear exit provisions such that it will leave the consolidated group clear of all group tax‑related liabilities (refer section 721‑35 of the ITAA 1997) . Mineralogy International Limited will act to comply with these requirements.
Proceeding CIV1514
[22] The content of this letter will affect Proceeding CIV1514.
[23] We note Proceeding CIV1514 is listed for review before the Court on 24 September 2020.
[24] We consider it is appropriate for the parties to raise with the Court this communication.
Next steps
[25] We await your response to this communication.
[26] We trust the parties can work collaboratively towards completion of the First Option consistently with the content of this communication.
Yours faithfully
Geoff Smith Kane Jones
Legal Counsel Legal Counsel
Mineralogy Pty Ltd Mineralogy Pty Ltd
CPI Increase means US$200,000,000 x CPI1 ‑ CPI2 / CPI1 [sic]
Preliminary observations upon Mineralogy's September communication
[13] This plea is contained in FASOC [67A] to [67O].
[14] By letter dated 22 September 2020, Mineralogy and Mr Palmer indicated the plaintiffs' calculation of drilling costs were accepted. Accordingly, there is no utility in granting leave to plead paragraphs [67A] to [67O].
Forensic implications of Mineralogy's September communication
67P. Further, by reason of Mineralogy's and Palmer's breaches of the terms of the CPOA pleaded in paragraph 67 above, Mineralogy and Palmer caused inordinate delay in completion of the First Option.
67Q. By reason of the matters pleaded in paragraph 67P above, Mineralogy and Palmer cannot take advantage of their own breach of contract and, accordingly, the CPI Increase to the Purchase Consideration should apply from 1 March 2006 for no longer than a period of six months after exercise of the First Option (being 13 October 2012), that being a reasonable period for completion of the First Option after its exercise, and, so applied, the CPI Increase is US$42,959,427.21.
Particulars
The CPI Increase is calculated as follows:
US$200,000,00 x (CPI2 ‑ CPI1)/CPI1, where CPI1 is 83.8, being the last published CPI figure before 1 March 2006 and CPI2 is 101.8, being the last published CPI figure before 31 October 2012.
67R. Further or alternatively to paragraph 67P above, it was an implied term of the CPOA that the CPI Increase would not apply to any period of delay in completion of the First Option caused by Mineralogy's or Palmer's breaches of the CPOA.
Particulars
The term was implied in order to give business efficacy to the CPOA.
67S. Further or alternatively to paragraph 67Q above, by reason of the matters pleaded in paragraphs 67P and 67R above, the CPI Increase to the Purchase Consideration should apply from 1 March 2006 for no longer than a period of six months after exercise of the Frist Option (being 13 October 2012), that being a reasonable period for completion of the First Option after its exercise and, so applied, the CPI Increase is $42,959,427.21.
Particulars
The plaintiffs refer to and repeat the particulars to paragraph 67Q above.
67T. Alternatively to paragraphs 67P to 67S above, by reason of Mineralogy's and Palmer's breaches of the terms of the CPOA pleaded in paragraph 67 above, and if (which is denied) the CPI Increase to the Purchase Consideration applies from 1 March 2006 without reduction, CITIC will have suffered loss and damage in the amount of $30,071,599.05, being the CPI Increase from 13 October 2012.
Particulars
The amount of US$30,071,599.05 is calculated as follows:
A ‑ B, where A is US$73,031,026.25, calculated as follows:
US$200,000,000 x (CPI2 ‑ CPI1)/CPI1 is 83.8, being the last published CPI figure before 1 March 2006 and CPI2 is 114.4, being the last published CPI figure before the date of this pleading and B is US$42,959,427.21 calculated as in paragraph 67Q above.
The loss and damage is continuing.
67U. By reason of the matters pleaded in paragraph 67T above, CITIC is entitled to, and hereby does, set off the loss and damage pleaded in paragraph 67T above against the CPI Increase otherwise applying from 1 March 2006 and, as a consequence of that set off, the CPI Increase is US$42,959,427.21.
Particulars
The amount of $42,959,427.21 is calculated as follows:
US$73,031,026.25 (calculated as set out in paragraph 67T above) less $30,071,599.05 (calculated as set out in paragraph 67T above).
Purchase Consideration
67V. By reason of the matters pleaded in paragraphs 67A to 67U above, the Purchase Consideration payable by CITIC or Cape Preston on completion of the First Option is made up as follows:
(b) US$42,959,427.21, as referred to in paragraphs 67Q, 67S and 67U above; less
(i) US$135,562,053, by reason of the matters pleaded in paragraphs 67A to 67N above; or
(ii) US$91,888,129, by reason of the matters pleaded in paragraphs 67A to 67N above, or
(iii) US$135,562,053, as referred to in paragraph 67O above.
Breach of the terms of the CPOA relating to the First Option
(a) to ensure that the Further Company. ACN 606 342 778 Ptv Ltd. becomes a party to the necessary Project Agreements being:
(i) the Sublease dated 25 October 2001 between Mineralogy and Sino Iron Pty Ltd;
(ii) the Facilities Deed dated 28 November 2001 between Mineralogy and Sino Iron (as amended on or about 21 March 2006);
(iii) the Fortescue Projects Consolidation Agreement between Mineralogy, Sino Iron and others; and
(iv) the Fortescue Co‑ordination Deed dated 22 October 2008,
(b) within 90 days of the exercise of the First Option to attempt to have the Further Company, ACN 606 342 778 Pty Ltd, become a party to the State Agreement on the same terms as the terms on which Sino Iron is a party to the State Agreement in accordance with clause 3.6(d) of the CPOA;
(c) to provide the Project Agreement Notice pursuant to clauses 3.6(c)(iii) of the CPOA and the notice pursuant to clause 3.6(d) of the CPOA;
(d) to enter into a Takeover Agreement with CITIC within 7 days of providing the Project Agreement Notice as required by clause 3.6(f) of the CPOA; and
(e) to execute on its own behalf and on behalf of any other party to the State Agreement that has authorised it to do so any document ·necessary or desirable for the purpose of making a Further Company, ACN 606 342 778 Pty Ltd, a party to the State Agreement as required by clause 3.6(g).
CITIC has not received notice that Mineralogy has satisfied its obligations under:
(i) clauses 3.6(c)(i) or 3.6(d) of the CPOA to ensure that the Further Company becomes a party to the necessary Project Agreements and State Agreement;
(ii) clause 3.6(g) that Mineralogy has executed on its behalf or any other party all documents necessary or desirable for the purpose of making a Further Company a party to the State Agreement
(f) to use their reasonable endeavours to obtain the fulfilment of the conditions in clause 8.2 of the CPOA as required by clause 8.3 of the CPOA.
108 As now seen, these proposed CPI Increase limit amendments, in effect would, if allowed, see the CITIC Plaintiffs seeking to contend at trial that a period of six months after the exercise of the First Option by CITIC Ltd (which exercise was at 13 April 2012 and therefore would allow until 13 October 2012 for completion) is said to be 'a reasonable period for completion of the First Option ...': (see proposed pars 67Q, 67S and particulars to par 67T, which in turn refer to the interest calculation under par 67Q).
(a) By proposed par 67Q, an argument grounded on the principle that the contract breaker cannot take advantage of their own breach of contract. The argument as framed identifies a principle of underlying areas of contract law that is well understood. Nevertheless as expressed under proposed par 67Q, the observed proposition, as regards finding a temporal limitation bearing against the text of the CPOA, and so as against allowing any CPI Increase to the Purchase Consideration after 13 October 2012, does not appear to be fully developed. It currently presents as something of a sentiment only. It may be that this proposed plea is seeking to support some argument of contractual interpretation and meaning towards the true meaning of 'Purchase Consideration' as text used by the CPOA. But presently the basis of the plea as framed looks to require some further amplification as to what is actually being contended for.
(b) Next, the proposed ad hoc implied term seen under proposed par 67R, namely that a CPI Increase would not 'apply to any period of delay in completion of the First Option caused by Mineralogy or Mr Palmer's breaches of the CPOA', is clearer and so, more understandable as a matter of legal concept. The plea looks to be linked via proposed par 67S to a like six month cut‑off period as the suggested reasonable period after 13 April 2012 ‑ as the 'reasonable period for completion of the First Option after its exercise'.
(c) A further freshly proposed CPI Increase limit argument emerges arising from the combination of proposed par 67P and par 67S, as to Mineralogy and Mr Palmer's alleged breaches of CPOA terms, and thereby to causing suggested inordinate delay in the completion of the First Option. This again is ultimately linked to the same temporal limit contention, namely, that a period six months after exercise of the First Option, was the reasonable period for completion. I confess I do not as yet fully comprehend the juridical basis of this hybrid plea, seen formulated as to what it carries beyond the true meaning or ad hoc implied term amendment contentions, as already canvassed.
(d) By reference to proposed par 67T is further found another fresh argument, this time of a contended equitable set‑off of breach damages, put against the CPI Increase figure if fully allowed, by reference to CITIC Ltd's contended suffering of loss and damage after 13 October 2012 which, by proposed par 67U, is to be set‑off against any CPI Increase. Again, the same contended maximum allowable six‑month reasonable contention period features.
(a) the previous experience in seeking and obtaining approval of the State and how that might affect enabling a Further Company to become a party to the State Agreement;
(b) seeking and obtaining approval of the Treasurer under the Foreign Acquisitions and Takeovers Act 1975 (Cth), any experience at that time regarding foreign acquisitions of mining interests and otherwise including the processes in respect of the acquisition of Sino Iron Pty Ltd and Korean Steel Pty Ltd;
(c) the time to complete a Takeover Agreement in substantially the same form as the Korean Steel Takeover Agreement, including the considerations that the Korean Steel Takeover Agreement is date 1 November 2007 but completed on 22 October 2008 and itself provided for completion to occur up to 14 calendar months after the contract date (ie, from 1 November 2007).
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
(2009) 239 CLR 175
(1979) 144 CLR 597