Reasoning of the Primary Judge
15 The primary judge noted that WSP accepted that it does not fall within Item 8 of the definition of the "Insured", because it did not carry out manual on-site activities, but relied on Item 4 of the definition: [21]. The primary judge referred to the admission by Liberty that WSP is an Insured under the Liberty Policy on the basis that it was a subcontractor engaged by Icon on the project, but said that Chubb and Tokio are not bound in any way by the admission by Liberty and drew no conclusion from the fact that Liberty had taken a different position to that of Chubb and Tokio: [23]-[24].
16 The primary judge said that there was no real difference between the parties as to the relevant principles to be applied in construing commercial policies of insurance: [28]. Among those principles is the proposition that, in the absence of evidence that words are used in some technical sense or have acquired some established meaning among the contracting parties (or the market in which the agreement is concluded), the words used are to be given their natural and ordinary meaning; that is, a meaning that they would be given by a reasonable person in the position of the parties: [28].
17 The primary judge said that the term "subcontractor" has a relatively plain meaning when used by lawyers to describe a particular legal relationship, and refers to a party who has been contracted to perform the contractual obligations of another party under a contract that it has made with a third party: [31]. Adopting that usage, architects, engineers and other professionals may be subcontracted by the principal contractor (to the extent that they are engaged to perform work that the principal contractor has agreed to perform) or they may be engaged as contractors, suppliers or consultants (to the extent that they are engaged to perform work for the project that the principal contractor has not agreed to perform): [32]. The question depends upon the scope of the work to be undertaken by the principal contractor: [32].
18 The primary judge then referred to other possible meanings of the term. His Honour said that the term "subcontractor" may be used in a more general way to refer to any party other than the main contractor who undertakes some aspect of the work that is required as part of a large project, irrespective of the party's precise legal relationship with the principal contractor: [34]. A further possibility is that, in the context of a construction project, the term contractor or subcontractor may be used to refer to a party who has been engaged by the main or head contractor to undertake some part of the construction works required to complete the project, as distinct from activities which support or facilitate undertaking those works: [35].
19 In considering the Liberty Policy as a whole, the primary judge referred to the description of the Insured and the Insured's Business in the Schedule as extending beyond the activity of undertaking construction, and including within the definition of the Insured's Business all business activities of the insured, which are stated to be not limited to "engineers" (among others): [44]. The primary judge said that the express reference to engineers in the Schedule appears to be intended to reflect a particular aspect of the business conducted by the Icon Group, because the defined term "Insured Business" does not refer to engineers but says that the term means, among other things, "all of the Insured's businesses, occupations and/or activities as described in the Schedule": [44]. The primary judge said that the structure of the policy requires the business of the Icon Group to be described in the Schedule to the policy and the description in the Schedule includes "engineers": [44].
20 The primary judge said that no aspect of the Liberty Policy adopts terminology which indicates that it is intended to apply only to Insureds who are construction contractors, as distinct from those who may take on responsibilities for development and design as well as construction: [52]. Rather, the primary judge said that the nature and extent of coverage depends to a considerable degree upon the description of the "Insured's Business" as stated in the Schedule, and that may be expected to be crafted to reflect the nature of the business of the particular Insured: [52]. The primary judge said that, in the present case, that description is not limited to the business of "builders" or "construction contractors" but is much more broadly expressed in the phrase "builders, engineers, construction contractors, project managers, construction managers, property developers, plant and equipment owners/operators and hirers, property owners and occupiers, lessees and lessors": [52]. As a result, the primary judge said that subcontractors under the policy may be expected to be responsible for work and activities that extend well beyond construction work, though still undertaken in what may be described as the construction industry: [53]. Having regard to the breadth of the business of the Icon Group entities named as insureds in the policy, the primary judge said that Icon Group entities' subcontractors may be engineers, construction managers or plant and equipment operators, among others. The primary judge regarded that as a significant aspect of the policy that is evident from the way in which the whole of the policy is expressed to operate: [53]. Accordingly, the primary judge concluded that the definition of Insured in the Definitions section of the policy should not be approached on the basis that the policy concerns an indemnity to be extended to Insureds undertaking only construction work: [54].
21 The primary judge then referred to matters of context, beginning with the quotation slip by which the underwriters were invited to quote for renewal of the relevant policy. The quotation slip described the business of the Icon Group in similar terms to those expressed in the Schedule, and included express reference to "engineers" among the business undertakings and activities of the Insured: [56]. The "Underwriting Information" included reference to the Icon Group engaging subcontractors to perform standard tradesmen's activities, including plumbing, electrical, bricklaying, glazing, and carpentry, and referred to a program being maintained to ensure strict control over any subcontractors engaged, with the subcontractors required to hold their own liability insurance: [58]. The Company Profile document included a statement describing the Icon Group's design and construct methodology: [59].
22 The primary judge said that WSP sought to make much of the terms of Icon's design and construct contract with the developer for the Opal Tower project, but noted that it was not suggested that the precise contractual arrangements that Icon concluded in relation to its design and construct contracts were known to Icon and the underwriters at the time the insurance was proposed and written: [61]. Accordingly, the primary judge was not persuaded that the particular terms of the design and construct contract formed part of the context to which there may be regard in construing the policy terms: [61]. The primary judge said that the only relevance of the design and construct contract, as well as the contract between Icon and WSP, is that it is necessary to understand those arrangements when it comes to determining whether, having construed the policy terms, WSP is an insured on the facts of the present case: [62]. In that respect, the primary judge noted that there was no real issue between the parties as to the nature of the relationships that were established by those contracts; in particular, the relevant work that WSP was engaged by Icon to undertake was engineering design work that Icon had contracted to deliver as part of its design and construct contract with the developer: [62]. The primary judge said that it was the alleged liability of WSP arising from undertaking that engineering design work that was compromised by the settlement of the Supreme Court proceedings, and which gave rise to the liability to make payments on the part of WSP: [62].
23 The primary judge then dealt with various authorities relied on by the parties on the question whether the references to subcontractors in the Liberty Policy included an engineer such as WSP. The primary judge said that none of the authorities were concerned with the proper construction of an insurance policy expressed in the same or similar terms as the Liberty Policy, and therefore the authorities were of little relevance to the present construction question: [63].
24 Chubb and Tokio relied upon reasoning in Pasminco Metals-Sulphide Pty Ltd v Brambles Aust Ltd [1998] NSWCA 169, in particular the statement by Spigelman CJ (with whom Powell JA agreed) that the natural and ordinary meaning of the word "sub-contractor" suggests a person or firm that performs some part of the work, rather than a person or firm that supplies services or equipment for use in the work. However, the primary judge stated that, in the present case, the work to be conducted by Icon included the engineering design work for the project, and the statement in Pasminco did not say anything more than that a subcontractor is one who agrees to undertake work that another person is contracted to perform, thereby distinguishing a supplier from a person who is performing the contractual obligation of another: [66].
25 The primary judge also referred to the reliance placed by Chubb and Tokio upon the decision in Hopewell Project Management Ltd v Ewbank Preece Ltd [1998] 1 Lloyd's Rep 448. In that case, Hopewell entered into an agreement to build, operate and transfer a power station; Hopewell then entered into an agreement with one of its subsidiaries (Slipform) to oversee and manage the design and construction of the power station; and Ewbank Preece entered into an agreement to provide certain engineering services to Slipform. The primary judge noted that Ewbank Preece was not subcontracted to undertake any part of the design obligation for the power station, nor was it subcontracted to undertake the oversight and management obligation of Slipform; rather, it was contracted to provide technical and engineering services to Hopewell in accordance with a "scope of services": [67]. However, in the present case, the primary judge stated that WSP was subcontracted to the main contract, and it was required to carry out the engineering design work that Icon was required to undertake under its design and construct contract with the developer: [71]. The primary judge treated that as an important point of distinction from Hopewell, in that Hopewell was not a case where engineering design obligations had been subcontracted. Rather, the contractual arrangements with Ewbank Preece were determined to require the provision of engineering services or expertise (and not the performance of any Hopewell's own obligations): [75]. The primary judge also noted other points of distinction, namely that Hopewell was a case in which the court received expert evidence as to insurance practice and brought that to account, and it was a case that recognised that there may be instances where design services are offered as an adjunct to construction work and such cases were in a different category from the case before the court: [75].
26 The primary judge also referred to cases concerning very differently worded policies: GPS Power Pty Ltd v Gardiner Willis & Associates Pty Ltd [2000] QCA 495 at [32] (Williams J) and Thiess Pty Ltd v Parsons Brinckerhoff Australia Pty Ltd [2016] NSWSC 173 at [531]-[532] (McDougall J).
27 Turning to the proper construction of the Liberty Policy, the primary judge held that WSP was an insured for the following five reasons: [91].
28 First, the use of the words "and/or" that appear at the end of each item listed in the definition of "Insured" means that an insured may fall within one or more of the eight items, as Chubb and Tokio accepted in their written submissions: [92]. Accordingly, the fact that a person is an architect, engineer or other professional consultant (as described in Item 8) does not mean that they cannot be a subcontractor: [92].
29 Second, the primary judge said that Items 7 and 8 identified categories of persons "but only in relation to their manual on-site activities", and that a construction of the term "subcontractors" as used in Item 4 that was so broad as to encompass the categories in Items 7 and 8 irrespective of whether they were undertaking manual on-site activities would make those provisions redundant: [93]. His Honour said that, although the words "and/or" indicate overlapping categories, the deliberate inclusion of Items 7 and 8 strongly indicates that there was a category of cases where those described in Items 7 and 8 would not be covered by Item 4 (or the other items): [93]. The primary judge said that an interpretation of subcontractors that included architects and engineers but only where they were contracted by an insured to carry out work that the insured was contracted to undertake would leave room for the operation of Item 8. That construction would mean that an engineer who was engaged by the principal directly or by an Icon Group entity to provide engineering services that the Icon Group entity had not itself contracted to provide would only be covered under Item 8 (and therefore only in relation to manual on-site activities): [93]. The primary judge said that Item 8 (and not Item 4) would apply to any engineer who was not subcontracted to undertake engineering work that an Icon entity had contracted to undertake: [94]. Further, the primary judge said that it was not suggested that the policy wording was specific to the Icon Group's circumstances, and the evidence showed that the policy was one that was provided to the market generally by underwriters, and that the Schedule was used to customise the operation of the policy to the circumstances of the particular insured: [94].
30 Third, the primary judge said that the broad definition of the Insured's Business in the Schedule in the present case, particularly the inclusion of "engineers" in that definition, means that there is wider scope for the category of subcontractors in Item 4: [95]. The primary judge said that it was not the case that the Liberty Policy provided for every contracted engineer providing services to a "builder" or "construction contractor" to come within the definition; rather, the scope of coverage depends upon the event giving rise to the relevant legal liability to pay being one which happens "as a result of an Occurrence in connection with the Insured's Business": [95]. His Honour said that the structure of the policy and the capacity for an Insured's Business to be broad or narrow in scope will determine the extent to which that business has obligations which may be subcontracted. In a context where the policy is structured so that it may apply to an insured whose business includes contracting to supply engineering services as well as construction services, it would be inconsistent with the overall structure of the policy to confine the meaning of the term "subcontractor" to those parts of the business which involve the subcontracting of physical construction work: [95]. The primary judge said that the quotation slip described the Insured's Business as including "engineers", and the accompanying company profile for the Icon Group referred to its design and construct methodology: [96]. Accordingly, those contextual matters did not establish a basis for concluding that the business of the Icon Group as described in the policy excluded the provision of engineering services, particularly engineering design: [96].
31 Fourth, the primary judge said that the policy plainly sought to extend the scope of those who were insured beyond those who were named as insureds, and referred to the concluding words of the definition of "Insured" which state that "all other parties for whom the Insured is required under contract or any other legally binding agreement to provide insurance protection are also included as an Insured": [97]. The primary judge said that, therefore, the other categories of insureds are not named in order to fulfil obligations of that kind: [97].
32 The primary judge said that the inclusion of other insureds was seen to be in the commercial interests of the Icon Group entities, in obtaining coverage for other insureds for amounts that those insureds became legally liable to pay in respect of (relevantly for present purposes) Property Damage: [98]. The primary judge said that the evident interest of the Icon Group entities in obtaining that insurance was to ensure that there was coverage for those entities and consequently less room for disputes between parties concerning where the liability ultimately lay, including issues of apportionment of responsibility: [98]. In effect, the primary judge said that there was a form of project coverage for liability arising from the activities that the Icon Group entities would be undertaking as part of the business as defined in the Schedule to the policy (specifically the engineering and construction of buildings): [98]. Coverage for those who had been subcontracted to undertake any part of the works that the relevant Icon Group entity had undertaken to perform was necessary to obtain that kind of coverage, adding that it would be a most uncommercial result if there was coverage for some aspects of the works that an Icon Group entity had contracted to undertake as part of a particular project (such as construction work) but not other aspects of those works (such as engineering design): [99]. The primary judge said that such a result would expose the Icon Group entity to the risk that it would be liable for the activities of its own subcontractor but would itself have no insurance coverage for that liability, and would also be exposed to the cost of having to pursue its subcontractor where it considered that the subcontractor was responsible, and would then bear the risk that the latter would not have the funds to meet the liability: [99]. The primary judge said that the evident purpose of achieving a form of comprehensive cover of others in the interests of the Icon Group entities would then be compromised: [99]. The primary judge stated that, having regard to the evident commercial purpose of the policy, there was every reason not to confine the words "subcontractors engaged by any of the above" in Item 4 to a subcontractor undertaking construction works or on-site works: [99].
33 The primary judge said that the terms of Items 7 and 8 are explained by a different aspect of the way in which liability for the risks covered by the policy may arise, stating that liability may be attributed to an Icon Group entity having regard to the nature of the business as described in the policy on the basis that the Icon Group entity has overall responsibility for activities undertaken on a project site. His Honour stated that it was that separate and distinct way in which liability may arise that explains the terms of Items 7 and 8, but the existence of that separate rationale for those items is not a reason for construing Item 4 as being subject to Items 7 and 8: [100].
34 Fifth, the primary judge said that this was not an instance where it was evident from the language used in the policy considered in the overall context that the term subcontractor was being used to differentiate those who are undertaking the construction works from consultants: [101]. The primary judge added that the reference in Item 4 to "sub-contractors engaged by any of the above" meant that it was not an "any tier" provision that referred to subcontractors of subcontractors, but was confined expressly to those subcontractors engaged by a named Insured: [101].
35 The primary judge concluded that each of these matters pointed to the term subcontractor being used in its legal sense to encompass any party undertaking work that an Icon entity (and others named "above") had contracted to undertake: [102]. The primary judge said that the effectiveness of the policy as providing cover for all liability for damage to property which may be attributed to some extent to an Icon Group entity (or about which there may otherwise be dispute as to attribution of responsibility) would be substantially compromised if it did not cover WSP, which had been subcontracted to undertake the engineering design obligations of Icon under its own contract: [102]. The primary judge added that the inclusion of the express reference to "contractors and sub-contractors" in the description of the Insured in the Schedule to the policy also supports this conclusion: [102].
36 The primary judge noted that the general commercial availability of professional indemnity insurance, and the possibility of an expectation among those participating in the construction industry that professionals such as architects, engineers and professional consultants would have their own professional insurance, may be viewed as operating against the considerations which favour WSP's construction of the policy: [103]. The primary judge referred to the consequence that any coverage for such professional people for their activities under a third party liability policy of the kind in issue would be likely to result in double insurance and the burden of additional premiums in respect of the risks associated with undertaking particular construction works: [103]. However, the primary judge said that there was no evidence as to those matters or the extent to which they were part of the market context in which the insurance was arranged by the Icon Group: [103]. In the end, the primary judge said that there must be regard to the language used by the parties, which leads to the conclusion that WSP is an Insured within Item 4 of the definition of Insured, and Item 4 should not be read as being subject to Item 8: [104]. The primary judge said that the interaction between Item 4 "and/or" Item 8 should be construed to mean that the reference to engineers in Item 8 is to engineers who are not subcontractors engaged by an Insured to undertake work that the Insured is itself contracted to perform: [104].