(4) Minor variation of overshadowing controls
The consent authority may make a determination to vary, to a minor extent only, the operation of subclasses (2) (b) or (c), or both, in respect of a particular development application, but only if:
(a) it is satisfied that the variation is justified due to the merits of the development application and the public benefit to be gained, and
(b) it is satisfied that any increase in overshadowing will not reduce the amenity of any land, and
(c) in relation to a variation of the operation of sub clause (2)(b), the variation will result in not more than 2 hours net increase in overshadowing of land referred to in that paragraph between the hours of 9am and 3pm, 21 June, and
(d) in relation to variation of the operation of subclause (2)(c), the variation will result in not more than 15 minutes net increase in overshadowing of land referred to in that paragraph between the hours of 10am and 12 noon, and no net increase between the hours of 12 noon and 2pm, on any day.
(5) Building design and public benefits
When determining whether or not to grant consent to a development application in respect of land within the North Sydney Centre, the consent authority must consider:
(a) the impact of the proposed development in terms of scale, form and massing within the context of the locality and landform, the natural environment and neighbouring development and in particular lower scale development adjoining the North Sydney Centre; and
(b) whether the proposed development provides public benefit such as open space, through-site linkages, community facilities and the like; and
(c) whether the proposed development preserves important view lines and vistas; and
(d) whether the proposed development enhances the streetscape in terms of scale, materials and external treatments, and provides variety and interest.
21 It can be seen that clause 28D(2)(a) of the LEP establishes the maximum height of RL 195 for the site. However, the height is also controlled by sub clauses 28D(2)(b), (c) and (d), 28D(4) and (5) and by the BHP in cl 30 (see section below).
22 A great deal of Mr Byrnes' defence of the proposal is based on the assumption that the maximum height of RL 195 has primacy over other controls, so that where other controls suggest a height considerably below RL 195, then they should not be stringently applied. I do not see anything in the LEP that sanctions this construction. In my opinion, all controls must be given serious consideration and varied only when variation is justified.
23 The proposal overshadows the northwest façade of the Century Plaza building, which is outside the North Sydney Centre and falls within the composite shadow. The applicant submitted an Objection under SEPP 1 to the development standard in cl 28D(2)(d), ie that
there will be no increase in overshadowing that would reduce the amenity of any dwelling that is outside the North Sydney Centre and falls within the composite shadow area referred to in paragraph (b)…
24 I am not sure that an Objection under SEPP 1 is possible to cl 28D(2)(d), since I do not think that it is a development standard or that it can be expressed as one. However, I set aside my doubts and consider the Objections as if cl 28D(2)(d) contained a development standard. The gist of the justification in the Objection is that the shadow impact is for an hour and a half in the afternoon and falls only on bedrooms. The diagrams show that for much of that period, all 20 floors of the building are affected. I do not think that the impact could be considered minor or moderate, even taking account of the fact that it falls on bedrooms rather than living areas. The Objection is not well founded. The proposal breaches cl 28D(2).
25 The proposal also breaches cl 28D(5). It is out of scale with almost everything around it, including the Century Plaza building, which itself is out of scale with its surroundings. It dominates the street and destroys any remnant of character left in Walker Street. Its impact, in terms of scale, form and massing within the context of the locality, landform and neighbouring development, and in particular lower scale development adjoining the North Sydney Centre, is unacceptable.