Brucic Pty Ltd v Turton
[2023] NSWCATAP 129
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2023-03-27
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
REASONS FOR DECISION
- The appellant is a licensed building company, which carried out improvement works to part of an existing, unbitumised road on the respondent's small rural property in the Southern Highlands area of New South Whales. The work was carried out in October 2019.
- The appellant appeals from an order made by the Tribunal in December 2022 requiring it to pay the respondent the amount of $32,561.10 in damages for what was found to be defective work on the road.
- The Tribunal's decision was based upon its conclusion that the appellant breached the statutory warranty of due care and skill in s 18B of the Home Building Act 1989 (NSW) (HBA). The damages were assessed on the basis of the Tribunal's conclusion that the appellant's contention should be accepted that any required rectification should occur by "in situ stabilisation", rather than replacement of the work done.
- For the reasons set out below, we have decided that the appeal should be dismissed, including that leave to appeal should be refused.
Extension of time in which to commence the appeal
- The Notice of Appeal was lodged two days out of time. It should have been lodged by close of business on 16 January 2023 but instead was lodged on 18 January 2023.
- Initially, the respondent opposed the grant of the required extension of time. However, at the hearing of the appeal, we were told by the appellant's solicitor that the Notice of Appeal had been sent by email to the Appeals Registry on 16 January 2023 at 1:53 pm (although this was not a method by which the Notice of Appeal could be lodged) and that the email confirmed that the Notice of Appeal had been mailed by registered post to the Appeals Registry. The respondent accepted that if this was the fact as deposed to in an affidavit from the solicitor for the appellant then it consented to the grant of the required extension of time.