(Nine matters were then set out which I will consider in due course). The submission then continued:
"31. The only basis that Brodyn appears to seek to attack the decision of the deed administrator is that he should [?should not] have accepted matters as where [sic] accepted by Mr El Safty. That is not a fair consideration of the task of the deed administrator or indeed the court in the present hearing."
51 It is an impossible task for the Court to be told that it cannot rely on the evidence before the Court because it was so different to what was before the administrator and yet the administrator refuses to tell the Court what was before him. It is difficult in any event to uphold a claim by an administrator who has made his decision, on the material that he gleaned from Mr Bard and Mr Farrell and from the officers of the company without even securing comments from the claimant, let alone even informing the Court what that material was. Then to dismiss seven volumes of detailed evidence as being more or less irrelevant because it was never considered by the administrator is, with respect, the height of absurdity. It would appear that the administrator has made a deliberate forensic decision not to put before the Court any proper evidence, he has chosen to cross-examine Mr El Safty by his counsel, and for him then to say that the material is worthless because it was never before the administrator is, with respect, quite absurd.
52 A practical solution is to send the matter back to the administrator to decide on the proof of debt according to law by informing the plaintiff of the matters told to him by Mr Farrell, Mr Bard and the officers of the company which influenced his decision, allow time for proper comment and then for the administrator to consider also Mr El Safty's report. However, one has got to be financially realistic about all this. The company has no money, it is never likely to be able to pay the plaintiff even one cent, the plaintiff has already spent, according to the evidence over $130,000 in fighting the administrator or the company in three courts, a deliberate forensic decision has been made by the administrator, and although I have no real desire to decide a building case on inadequate evidence, in my view, justice requires that the matter be determined now without further expense.
53 I thus turn to Mr El Safty's report. He says in his summary and recommendations that he has assessed the plaintiff's claim and analysed it with specific reference to the general conditions of contract, notices issued by the plaintiff, correspondence from the company and other forms of supporting documents. He then says:
"With regards to consequential loss, this related largely to the question of the termination of the agreement and the conduct of both parties. The question of repudiation must be answered from a legal perspective, [sic] as neither party followed the correct procedure set down in the contract. In any case the costs associated with the contract termination have been verified from a cost perspective [sic] only and is shown in italics in the summary schedule."
54 The claims for liquidated damages/delays fall into 10 sub-heads. Of the 10 sub-heads, three, namely items (d), (e) and (ll) relate to delays before 13 June 2003 when the contract terminated. The other seven relate to matters after the termination.
55 On the three claims that relate to prior delays, the plaintiff claimed $148,683.91 of which Mr El Safty was only prepared to consider, for the good reasons that he gave, a total of $45,288.55.
56 Of the other seven items (f) straddles the line. This is for additional crane hours from 27 May to 30 July. The amount allowed by Mr El Safty seems to be for the early period so it was $7,132.81 (as against the $28,0783.70 claim) which should be added to the $45,288.55, so as to make a total of $52,421.36.
57 Mr El Safty calculated as nothing for value of claims (b), (c) and (jj) so that they can be removed from further consideration.
58 The three remaining claims are (ii) which Mr El Safty assessed at $10,108; (kk) which he assessed at $35,000 and (mm) which he assessed at $17,150, a total of $62,250.
59 Mr El Safty's total assessment of the claim was $486,371.57. If one deducts the $62,250 one still gets a claim in excess of $400,000. Mr El Safty himself says that he considered $169,996.92 was subject to "legal opinion with regards to repudiation/contract termination", but even accepting this figure, there would be due to the plaintiff if Mr El Safty's figures are accepted, over $300,000.
60 I will say something about Mr El Safty's report generally and then come back to the issue of repudiation/termination.
61 As I have said earlier, the ultimate question is whether the administrator's decision should be reversed. Particularly in situations where the liquidator or administrator has not put before the Court the material before him, this amounts to whether the plaintiff's claim has been established. The only material that I have is Mr El Safty's material, plus the comments allegedly made by Mr Farrell to Mr Silvia or a member of his staff which have not been subject to cross-examination. Mr El Safty was cross-examined, and with respect, no dint was made on the reliability of his evidence. The evidence is supported by seven volumes of calculations and attachments. I see no reason why I should not accept Mr El Safty's evidence.
62 It follows that the plaintiff is owed in excess of $300,000 and there must be reversal of the administrator's decision, at least to that extent.
63 So far as repudiation is concerned, I am left to consider the raw material which is annexed to Mr El Safty's report, particularly that in volume 6. The volume shows that there were continuous complaints by the plaintiff from at least March. On 4 June 2003, the plaintiff faxed the company a letter which included:
"The step down heights to the above slab on ground are not in accordance with the contract requirements, and as such follow on work is unable to continue until this is rectified. This area of work is on our critical path to the project and as such your incomplete works are delaying the progression and completion of work to this project. Please be advised the liquidated damages … are effective as at 10 am today … ".
64 On 11 June Mr Taddio, the Dasein construction manager, faxed back that there had been an unco-operative meeting and that Mr Matterson "did not elevate our concerns about receiving payments still outstanding to Dasein Constructions, in the spirit of common sense and doing our best to keep this whole idiotic mess out of the courts we are prepared to provide an olive branch and provide TCQ with time to Friday 13 June 03 to assess and process all the outstanding variation and back charges".
65 On 11 June Mr Matterson faxed Mr Karam of Dasein, referred to the meeting of 10 June and said, "At this meeting Mr Carl Karam commenced the cancellation of the concrete pour scheduled for today. Mr Carl Karam whilst in the meeting telephoned the concrete pump operator, the concretor and concrete supply cancelling all orders and arrangements which had been put in place to pour the Attic slab today the 11-6-03, when asked by Brett Matterson what he was doing Carl Karam stated 'you are going to hear your site go to shit'." Mr Matterson said that the plaintiff considered that Dasein had repudiated the contract and that it had 48 hours to remedy its default.
66 On 13 June 2003, Mr Matterson again faxed Mr Karam:
"Dasein … have made no effort to return to the site to complete its contractual obligations to the main contractor. TCQ have no alternative but to accept that the conduct of Dasein Constructions Pty Ltd amounts to repudiation of the agreement. With this acceptance, TCQ will immediately put in place alternative arrangements to have the work completed."
67 On 17 June 2003, Mr Matterson faxed Mr Karam that it was pointless continuing a paper war as the plaintiff's position was very clear and it noted that Dasein's successfully disrupted and postponed the planned concrete pour on Monday 16-6-03.
68 On 17 June 2003, Mr Matterson faxed:
"We deny the contract was terminated by TCQ and that we are in breach of contract, we remind you that the contract was wrongfully repudiated by Dasein Constructions Pty Ltd and TCQ had no alternative but to accept the repudiation after notices and opportunity was given to Dasein Constructions Pty Ltd to remedy the repudiation."
69 On 19 June 2003, there is an e-mail from an officer of the plaintiff to Mr Matterson:
"Tony [I assume this is Mr Taddio] rang me on the mobile after meet with TCQ at H/O to tell me they would not be pouring any concrete at W/craft job as we had previously programmed on site."
70 I appreciate that I do not have full information, but that has been a result of a forensic decision made by the administrator. I appreciate also that the method of dealing with the alleged repudiation was not in accordance with the printed contract. In the end I do not think that matters too much. The parties had got to the stage where, on the material before me, the concrete pour was critical to the whole project, the company had refused to pour any concrete and indeed had cancelled the planned pour and this was as big a disruption to the project as could be imagined. I know that one does not lightly infer repudiation, but on the material before me there would seem to be a clear repudiation.
71 Accordingly, one should accept Mr El Safty's figures and find that the administrator should have admitted the proof of debt for $486,371.57. However, I repeat that even if I were wrong in this, the minimum for which the proof should have been allowed was $316,374.65 being the total of Mr El Safty's calculations less his $169,996.92.
72 Plaintiff's counsel are content to have the proof admitted for $262,388.65. This sum is certainly the minimum sum due to the plaintiff.
73 I said that I would come back to Mr Fisher's objections to Mr El Safty's report. These were: