HEADNOTE
[This headnote is not to be read as part of the judgment]
In August 2014, Ausgrid, a State-owned corporation, compulsorily acquired three easements over land at 31 Bligh Street, Sydney in order to construct a substation on the adjoining property. Bligh Consulting was the registered proprietor of 31 Bligh Street and the three easements acquired were a crane swing easement, a rock anchor easement and a scaffolding easement. At the date of acquisition, 31 Bligh Street was occupied by the Lowy Institute for International Policy (Institute), pursuant to a sub-sub-lease from Bligh Consulting. The Institute's sub-sub-lease expired on 30 September 2014. Thereafter the Institute remained in possession as a monthly tenant. In September 2015, Bligh Consulting entered into a lease of premises at 1 Bligh Street and the Institute relocated to these premises on 11 December 2015.
Bligh Consulting claimed compensation in relation to the compulsory acquisition, but objected to the amount offered in accordance with the Valuer-General's determination. The objection was heard by Justice Pain in the Land and Environment Court (L & E Court), with Bligh Consulting claiming compensation pursuant to three provisions of the Land Acquisition (Just Terms Compensation) Act 1991 (NSW) (Just Terms Act):
s 55(a) (market value of the easements);
s 55(d) (loss attributable to disturbance); and
s 55(f) (decrease in the value of Bligh Consulting's land by reason of the proposal to construct the substation).
At trial, the parties agreed that the amount of compensation payable under s 55(d) was $232,000. As such, the main issue at trial related to whether compensation was payable in respect of Bligh Consulting's injurious affection claim under s 55(f). While Bligh Consulting sought $4.25 million for injurious affection, the L & E Court declined to assess compensation pursuant to s 55(f) other than by awarding $25,000 in respect of the scaffolding easement. In addition, the L & E Court assessed the market value of the crane swing easement at $400,000 and of the scaffolding easement at $25,000. This brought the total compensation to $682,000.
Bligh Consulting appealed against this decision on several grounds:
(1) The first three grounds related to Bligh Consulting's contention that compensation was payable for injurious affection pursuant to s 55(f) of the Just Terms Act. Bligh Consulting submitted that the primary Judge had erred in assessing compensation by reference to the market value of each easement instead of by reference to s 55(f).
(2) Ground 4 related to the crane swing easement. Bligh Consulting submitted that the primary Judge had erred in assessing compensation for this easement by failing to consider Besmaw Pty Ltd v Sydney Water Corporation (2001) 113 LGERA 246 (Besmaw).
(3) Ground 5 related to the construction of s 62(1) of the Just Terms Act, which, in certain circumstances, limits compensation to situations in which there is actual damage. Bligh Consulting contended that s 62(1) does not apply to a rock anchor easement because such an easement serves the purpose of other works and is not an end in itself.
Held, per Sackville AJA (McColl and Basten JJA agreeing at [1] and [2]) dismissing the appeal:
Concerning Grounds 1, 2 and 3
(1) Sackville AJA found that the primary Judge did not err in her assessment of Bligh Consulting's injurious affection claim: [103]. Firstly, the primary Judge did not purport to apply the "before and after approach". Instead, her Honour addressed the threshold question of whether a hypothetical purchaser in the after scenario would have valued 31 Bligh Street on the assumption that the Institute would vacate the premises due to the proposed construction and that the premises would remain vacant for an extended period: [101]. In relation to this threshold issue, her Honour found that the hypothetical purchaser would not have valued 31 Bligh Street on these assumptions and, as such, the basis for Bligh Consulting's injurious affection claim dissolved: [102]. Further, Sackville AJA found that the primary Judge committed no error of law in considering what a reasonable person in the position of the Institute would do in the after scenario instead of what the Institute itself would do: [106]-[108].
Concerning Ground 4
(2) Sackville AJA rejected Bligh Consulting's submission that the primary Judge erred in law when assessing compensation for the crane swing easement: [133]. Her Honour did not fail to apply Besmaw. Instead, her Honour distinguished it on the basis that an informed hypothetical seller of the crane swing easement would take into account that, realistically, the easement would not interfere with the use of 31 Bligh Street: [132].
Concerning Ground 5
(3) Sackville AJA applied the ratio decidendi in Pennant Hills Golf Club Ltd v Roads and Traffic Authority (NSW) [1999] NSWCA 110 (Pennant Hills) - that is, that s 62(1) does, in fact, apply to easements for rock anchors: [122]. However, Sackville AJA also noted that even if Pennant Hills had not settled the issue, he would not have accepted Bligh Consulting's argument because nothing in the language of s 62(1) justifies reading into the provision a requirement that the relevant works be "ends in themselves": [124].
Additional Observations
Basten JA made an additional comment in relation to the scope of appeal, noting that if, at trial, a party did not require the court to consider a particular question of law then that party could not appeal on the basis that the court failed to consider the question. His Honour noted that this also applies where the case at trial was conducted by referring to a number of mandatory steps, as it was in this case. If the appellant failed at the first step, for reasons that could not be appealed against, he or she could not complain that the subsequent steps were not addressed: [12].