55072/05 Bitannia Pty Ltd & 1 Or v Parkline Constructions Pty Ltd & 1 Or
JUDGMENT
1 HIS HONOUR: This is a building dispute. On 30 June 2008 the whole of the proceedings were referred to the Honourable Mr Robert Hunter QC for inquiry and report. The defendants seek the adoption of the whole of the referee's report. The plaintiffs seek orders that certain conclusions of the referee's report not be adopted, and that in lieu thereof the court make findings and give judgment in favour of the plaintiffs.
Nature of Proceedings
2 In 2003 and 2004 the plaintiffs, in partnership, redeveloped the Ettalong Hotel at Ettalong on the Central Coast of New South Wales from a hotel to a mixed hotel and residential apartment complex. The first defendant ("Parkline") was the plaintiffs' builder. The second defendant ("Quirk") was the plaintiffs' architect and superintendent for the project.
3 The plaintiffs alleged that Parkline breached the construction contract. They alleged delays and defects in the works. They sought liquidated damages for the delays in the works being brought to practical completion. They claimed damages for the cost of rectification of alleged defects in the works.
4 The plaintiffs excluded Parkline from the site from 14 January 2005. They claimed that they were entitled to do so and claimed the costs of completing the construction works and other damages arising from Parkline's alleged repudiation of the construction contract.
5 The plaintiffs alleged that Quirk was negligent in issuing a certificate of practical completion when the works were not practically complete. They alleged that Quirk ought not to have accepted alleged variations claimed by Parkline and that if they were liable to Parkline for the variations, Quirk was liable to compensate them in respect of that liability. The plaintiffs alleged that if it were found that they had repudiated the agreement by wrongly purporting to terminate the agreement on 14 January 2005, Quirk was liable to compensate them for the consequences of their repudiation by not providing appropriate warnings and advice. They alleged that Quirk was liable to them for wrongly recommending payment of progress claims. None of these claims against Quirk is now pressed.
6 The plaintiffs also pleaded that if, as Parkline contended, the whole of the works were deemed to have reached a state of practical completion on 23 August 2004 because the plaintiffs took occupation of the hotel on that day, Quirk was liable for the plaintiffs' being unable to recover liquidated damages against Parkline after 23 August 2004 because it was obliged to serve a notice under clause 9.10.04 of the agreement so as to avoid that consequence. Clause 9.10 is set out later in these reasons. The claim against Quirk, as ultimately pressed after the referee's report, was not the claim pleaded. Rather, the plaintiffs allege that Quirk was obliged to advise them that they would be exposed to a claim that the whole of the works were deemed to have reached the stage of practical completion if the plaintiffs took occupation of the hotel if they did not reach and document an agreement with Parkline as to the consequences of early occupation which covered the various matters dealt with by clause 9.10.04.02.
7 By its cross-claim Parkline alleged that the plaintiffs had repudiated the agreement on 14 January 2005. By its amended cross- summons filed on 16 June 2008 Parkline purported to accept that wrongful repudiation and terminate the agreement. It claimed $525,669.10 being the amount of unpaid progress claims and claimed variations and half of the retention fund, plus a further sum of $174,029.05 for the balance of the retention fund, plus interest.
8 The referee found that the plaintiffs had not established any entitlement to damages against either defendant and that Parkline was entitled to $485,203 plus interest.
9 Parkline seeks an order that the referee's report be adopted in whole. It seeks judgment in the sum of $485,203 plus interest as determined by the referee and costs. Quirk also seeks an order that the referee's report be adopted in whole. It seeks judgment and costs.
10 The plaintiffs seek the following orders:
" 1. The following parts of the Referee's Report of the Honourable Robert Hunter dated 30 April are not adopted, namely the conclusions that:
(i) deemed practical completion took place on 23 August 2004.
(ii) In the alternative to (i), the First Defendant reached practical completion on 12 November 2004.
(iii) The Plaintiffs were not entitled to liquidated damages for the period between 30 July 2004 and 23 August 2004, or alternatively between 30 July 2004 and 12 November 2004, or at all.
(iv) The purported termination of the Contract by the Plaintiffs on 14 January 2005 constituted a repudiation of the Contract by the Plaintiffs.
(v) The Plaintiffs were not entitled to recover any monies from the First Defendant referable to the Plaintiffs' costs of completion of the works and of rectification of defects.
(vi) Nothing flowed from the conclusion that in August 2004 the Second Defendant had an obligation to advise or alert the Plaintiffs to the mechanism and operation of clause 9.10 of the Contract.
(vii) For the purposes of section 18B Home Building Act 1989, the apartments the subject of the Contract do not fall within the definition of a dwelling by reason of the exclusion in clause 6(f) Home Building Regulation 1987.
(viii) In the alternative to (vii), the availability of the implied warranties in the contract in terms of s. 18B of the Act does not advance the case of the Plaintiffs.
2. In lieu thereof, the Court makes the following findings:
(i) Deemed practical completion did not take place on 23 August 2004.
(ii) The First Defendant did not reach practical completion on 12 November 2004.
(iii) The Plaintiffs validly terminated the Contract on 14 January 2004.
(iv) The Plaintiffs were entitled to recover the cost of completion of the works under the Contract and of rectification of defects, such cost to be calculated as follows:
the sum of $1,153,824.72, being the cost of work carried out by Sapphire Projects Pty Ltd, less any part of such cost which the First Defendant has proved did not form part of the Plaintiffs' reasonable costs of completion of the works and of rectification of defects.
(v) The First Defendant has not discharged its onus of proving the amount of any part of the sum of $1,153,824.72 which did not form part of the Plaintiffs' reasonable costs of completion of the works.
(vi) In the alternative to (iv) and (v), the Court remits for further consideration by the Referee, doing the best that the Referee can do, the Plaintiffs' reasonable cost of completion of the works and of rectification.
(vii) The Plaintiffs were entitled to liquidated damages;
(a) at the rate of $10,000 per week for the period from 30 July 2004 to 23 August 2004; and
(b) at the rate of $5,000 per week from 23 August 2004 to 12 November 2004 or 14 January 2005.
(viii) For the purposes of section 18B Home Building Act 1989, the apartments the subject of the Contract fall within the definition of a dwelling and the Plaintiffs are entitled to damages for breach of the implied warranties under the said Act.
(ix) If deemed practical completion did take place on 23 August 2004, the Plaintiffs are entitled to damages as against the Second Defendant:
(a) at the rate of $10,000 per week for the period from 30 July 2004 to 23 August 2004; and
(b) at the rate of $5,000 per week from 23 August 2004 to 12 November 2004 or 14 January 2005.
3. Costs reserved. "
11 At the hearing the plaintiffs did not press their claim in para 2(ix)(a) against Quirk.
Principles on Adoption of the Referee's Report
12 It is common ground that the approach to be taken to the adoption, rejection or variation of the referee's report was as described by McDougall J in Chocolate Factory Apartments Pty Ltd v Westpoint Finance Pty Ltd [2005] NSWSC 784. His Honour said (at [7]):
" [7] The relevant principles, distilled from those decisions, can be stated as follows:
(1) An application under Pt 72 r 13 is not an appeal either by way of hearing de novo or by way of rehearing.
(2) The discretion to adopt, vary or reject the report is to be exercised in a manner consistent with both the object and purpose of the rules and the wider setting in which they take their place. Subject to this, and to what is said in the next two sub paragraphs, it is undesirable to attempt closely to confine the manner in which the discretion is to be exercised.
(3) The purpose of Pt 72 is to provide, where the interests of justice so require, a form of partial resolution of disputes alternative to orthodox litigation, that purpose would be frustrated if the reference were to be treated as some kind of warm up for the real contest.
(4) In so far as the subject matter of dissatisfaction with a report is a question of law, or the application of legal standards to established facts, a proper exercise of discretion requires the judge to consider and determine that matter afresh.
(5) Where a report shows a thorough, analytical and scientific approach to the assessment of the subject matter of the reference, the Court would have a disposition towards acceptance of the report, for to do otherwise would be to negate both the purpose and the facility of referring complex technical issues to independent experts for enquiry and report.
(6) If the referee's report reveals some error of principle, absence or excessive jurisdiction, patent misapprehension of the evidence or perversity or manifest unreasonableness in fact finding, that would ordinarily be a reason for rejection. In this context, patent misapprehension of the evidence refers to a lack of understanding of the evidence as distinct from the according to particular aspects of it different weight; and perversity or manifest unreasonableness mean a conclusion that no reasonable tribunal of fact could have reached. The test denoted by these phrases is more stringent than 'unsafe and unsatisfactory'.
(7) Generally, the referee's findings of fact should not be re-agitated in the Court. The Court will not reconsider disputed questions of fact where there is factual material sufficient to entitle the referee to reach the conclusions he or she did, particularly where the disputed questions are in a technical area in which the referee enjoys an appropriate expertise. Thus, the Court will not ordinarily interfere with findings of fact by a referee where the referee has based his or her findings upon a choice between conflicting evidence.
(8) The purpose of Pt 72 would be frustrated if the Court were required to reconsider disputed questions of fact in circumstances where it is conceded that there was material on which the conclusions could be based.
(9) The Court is entitled to consider the futility and cost of re-litigating an issue determined by the referee where the parties have had ample opportunity to place before the referee such evidence and submissions as they desire.
(10) Even if it were shown that the Court might have reached a different conclusion in some respect from that of the referee, it would not be (in the absence of any of the matters referred to in sub para (6) above) a proper exercise of the discretion conferred by Pt 72 r 13 to allow matters agitated before the referee to be re-explored so as to lead to qualification or rejection of the report.
(11) Referees should give reasons for their opinion so as to enable the parties, the Court and the disinterested observer to know that the conclusion is not arbitrary, or influenced by improper considerations; but that it is the result of a process of logic and the application of a considered mind to the factual circumstances proved. The reasoning process must be sufficiently disclosed so that the Court can be satisfied that the conclusions are based upon such an intellectual exercise.
(12) The right to be heard does not involve the right to be heard twice.
(13) A question as to whether there was evidence on which the referee, without manifest unreasonableness, could have come to the decision to which he or she did come is not raised 'by a mere suggestion of factual error such that, if it were made by a trial judge, an appeal judge would correct it'. The real question is far more limited: 'to the situation where it is seriously and reasonably contended that the referee has reached a decision which no reasonable tribunal of fact could have reached; that is, a decision that any reasonable referee would have known was against the evidence and weight of evidence'.
(14) Where, although the referee's reasons on their face appear adequate, the party challenging the report contends that they are not adequate because there was very significant evidence against the referee's findings with which the referee did not at all deal, examination of the evidence may be undertaken to show that the reasons were in fact inadequate because they omitted any reference to significant evidence.
(15) Where the court decides that the reasons are flawed, either on their face or because they have been shown not to deal with important matters, the court has a choice. It may decline to adopt the report. Or it may itself look at the detail of the evidence to decide whether or not the expense of further proceedings before the referee (which would be the consequence of non adoption) is justified. " (See Bellevarde Constructions Pty Ltd v CPC Energy Pty Ltd [2008] NSWCA 228 at [46]).
Plaintiffs' Claim
13 The plaintiffs contend that the referee made errors of law. They contend that on the basis of the referee's findings of fact, but after correction of the alleged errors of law, they are entitled to judgment for the sum of $1,153,824.72, being the cost they incurred in what they say was rectification of the defective work, together with liquidated damages from 30 July 2004 to 12 November 2004. The only claim they seek to maintain against Quirk is for liquidated damages from 23 August 2004 to 12 November 2004 in the event that it be held that they cannot recover such damages against Parkline.
Relevant Provisions of the Contract
14 The construction contract was entered into on 19 May 2003. It is a standard form contract described as:
" Building Works Contract
JCC-D 1994
Without Quantities
When Staged Practical Completion is
not being used
(Second Edition of JCC-D - August 1994) ".
15 The plaintiffs were the Proprietor. Parkline was the Builder. Quirk was Architect. Clause 1.03 provided:
" The Builder shall:
1.03.01 Upon the Site being made available by the Proprietor commence the execution of the Works;
1.03.02 thereafter regularly and diligently proceed to execute and complete the Works in accordance with this Agreement; and
1.03.03 in doing so bring the Works to Practical Completion by the Date for Practical Completion. "
16 "The Works" were defined as "The whole of the work to be executed in accordance with the Agreement ... including all Variations provided for by the Agreement". The scope of the work was not described in the agreement itself but was to be found in specifications and drawings. Essentially the work involved the demolition of the existing hotel and the construction of a four-storey building with a basement car park. The ground floor comprised the hotel and associated facilities. Fourteen residential apartments were to be constructed on the upper three levels.
17 "Practical Completion" was defined as follows:
" Practical Completion - The state of being substantially complete and fit for use and/or occupation by the Proprietor, all tests required under the provisions of this Agreement having been satisfactorily completed and omissions or defects being limited to items:
.01 The immediate making good of which is not practicable;
.02 the existence of which and/or the making good of which will not significantly inconvenience the Proprietor, taking into account the use or intended use of the items concerned and of the areas in which they occur; and
.03 which do not cause any legal impediment to the Proprietor's use and/or occupation. "
18 The contract provided that the date for practical completion was 24 May 2004. The referee found (at [260]) that:
" It is not in dispute that the date for completion of the works was extended to 30 July 2004 and in final submissions Parkline did not press its claim for an entitlement of further extension of time from that date. "
19 Clauses 3.04 and 3.05 provide:
" 3.04 POSSESSION OF SITE
The Builder shall, upon the Proprietor making the Site available to him, have legal possession of the Site for the purposes of carrying out his obligations under this Agreement until Practical Completion of the Works or until the Proprietor takes possession of the Works, whichever is the earlier.
3.05 ACCESS TO MAKE GOOD
After taking possession of the Works the Proprietor shall allow the Builder reasonable access to the Site and the Works for making good defects as required by Clause 6.11 provided that in carrying out any such making good the Builder shall take all reasonable measures to minimise inconvenience to the Proprietor or those then authorised by the Proprietor to occupy the Works. "
20 The position of Quirk as architect was described in Section 5. That section includes the following clauses:
" 5.01 ARCHITECT AS AGENT
The Architect shall act for and on behalf of the Proprietor as his agent where this is so provided for or required by this Agreement and:
5.01.01 The Proprietor shall not act contrary to that authority and the Builder shall be entitled to disregard any contrary action by the Proprietor; and
5.01.02 all things done and all actions taken by the Architect pursuant to this Clause 5.01 shall, subject to Clause 5.02, be deemed done and taken by the Proprietor for the purposes of this Agreement and are hereby agreed by the Proprietor as ratified and confirmed as such.
5.02 ARCHITECT'S AUTHORITY
The Proprietor and the Builder expressly agree:
5.02.01 That the Architect is hereby authorised to do all or any of the following acts:
.01 To issue instructions to the Builder in respect of any of the following matters:
.01 the Works;
...
.02 To supply to the Builder copies of any documents pursuant to Clause 2.05 and to furnish setting out information to the Builder pursuant to Clause 6.06.
5.02.02 That the Architect is hereby authorised to act as the assessor, valuer or certifier in respect of the following matters:
...
.02 the proper execution and completion of the Works (Clause 6.01);
...
.04 defects to be made good (paragraph 6.11.01)
...
.08 Practical Completion (Clause 9.09);
...
.11 liquidated and ascertained damages (Clauses 10.14 and 10.15);
5.02.03 Either the Proprietor or the Builder may refer to dispute resolution under Section 13 a decision made by the Architect as to any of the matters referred to in paragraph 5.02.02.
...
5.04 WRITTEN INSTRUCTIONS
Any instruction or notice which the Architect is obliged to give or chooses to give pursuant to this Agreement shall be given promptly and in writing. No instruction shall have any force or effect under this Agreement unless given by the Architect.
5.05 COMPLIANCE WITH INSTRUCTIONS
The Builder shall comply promptly with all Architect's instructions. Should the Builder consider that any such instruction is given in error or, although not stated to involve a Variation, in fact involves a Variation then the Builder shall notify the Architect in writing.
5.06 EMPLOYMENT OF OTHERS ON BUILDER'S DEFAULT
If the Builder does not comply with an instruction given by the Architect under any provision of this Agreement then:
5.06.01 The Architect may issue a notice to the Builder requiring compliance within a reasonable time to be stated in the notice;
5.06.02 if the Builder does not comply therewith the Proprietor may employ and pay others to execute any work whatsoever which may be necessary to give effect to such instruction of the Architect;
5.06.03 subject to paragraph 5.06.04 all costs properly incurred by the Proprietor in so doing may be recovered by the Proprietor as a debt due to the Proprietor by the Builder or may be deducted by the Proprietor from any moneys which may then be or thereafter become payable to the Builder by the Proprietor (including any retention moneys then held by the Proprietor) and if such moneys are insufficient for this purpose, the Proprietor may claim the amount due or the balance thereof under any security furnished by the Builder to the Proprietor pursuant to Clauses 10.20 and 10.21;
...
5.07 REPLACEMENT OF ARCHITECT
Should the Architect for any reason cease to act as such then the Proprietor shall:
5.07.01 Promptly notify the Builder in writing; and
5.07.02 promptly appoint another architect, having first ascertained that the Builder has no reasonable objection to the appointment of the other architect, and then promptly notify in writing the Builder of that appointment.
... "
21 Clause 9.11 provides:
" The Defects Liability Period shall commence on the date on which the Works reached or were deemed to have reached Practical Completion according to any of paragraphs 9.09.02, 9.09.04 and 9.10.04 and shall subject to paragraph 6.11.06 continue for the period stated in Item H of the Appendix. "
22 The period stated in Item H of the Appendix was 52 weeks. Retention moneys were to be released after 26 weeks.
23 Clause 6.11 provided for the giving of instructions by the architect to the builder to rectify defects during the Defects Liability Period. It provided:
" 6.11 MAKING GOOD DEFECTS
If at any time during the Defects Liability Period referred to in Clause 9.11 any faults, omissions, shrinkages or other defects in the Works are apparent then:
6.11.01 The Architect may issue an instruction to the Builder during the Defects Liability Period which shall state in what respect there are defects in the Works and may state a reasonable time within or at which the Builder shall complete the making good of those defects.
6.11.02 The Builder shall promptly make good such defects by appropriate rectification work and shall complete the same within or at any time stated in such instruction.
6.11.03 Where such defects are due to materials and/or workmanship not being in accordance with this Agreement, such making good by the Builder shall be at no cost to the Proprietor.
6.11.04 Where such defects occur notwithstanding that materials and/or workmanship are in accordance with this Agreement such making good shall be dealt with as would a Variation and in accordance with Clause 6.10.
6.11.05 If any defect is not made good within or at the reasonable time as may be so stated by the Architect or otherwise within a reasonable time the Proprietor may have the defect made good by others pursuant to the provisions of Clause 5.06.
... "
24 Clause 9.10 dealt with the situation where the proprietor took occupation of the works or part of them prior to practical completion. It provided:
" 9.10 OCCUPATION BEFORE PRACTICAL COMPLETION
Occupation of the Works prior to Practical Completion thereof shall be dealt with as follows:
9.10.01 Should the Builder fail to bring the Works to Practical Completion by the Date for Practical Completion then the Proprietor may with consent of the Builder and after issue by the Architect of the notice of occupancy hereinafter referred to occupy the whole or any definable part of the Works prior to Practical Completion.
9.10.02 In any such case the Architect shall after agreement between the parties as to the matters contained therein issue both to the Builder and to the Proprietor a notice of occupancy stating:
.01 That the whole or certain stated parts of the Works may be occupied prior to Practical Completion;
.02 the date or dates upon or after which such occupation may take place;
.03 the Date for Practical Completion; and
.04 the effect of such occupation upon the provisions of this Agreement relating to insurance, liquidated and ascertained damages, security and the Defects Liability Period.
9.10.03 The provisions of such notice shall take full effect notwithstanding any provisions of this Agreement to the contrary or inconsistent therewith.
9.10.04 If the Proprietor occupies and/or uses the Works or part thereof prior to Practical Completion in the absence of any such agreement and notice or of other written agreement between the Proprietor and the Builder then the whole of the Works shall be deemed to have reached Practical Completion on the date of commencement of such occupancy and/or use. "
25 Clause 10.14 provided:
" 10.14 LIQUIDATED AND ASCERTAINED DAMAGES
If the Builder shall fail to bring the Works to Practical Completion by the Date for Practical Completion:
10.14.01 The Architect may give notice in writing to the Builder and to the Proprietor that in his opinion the Works ought reasonably to have been brought to Practical Completion at some earlier date to be stated in that notice, not being earlier than the Date for Practical Completion.
10.14.02 If such notice is given the Builder shall pay or allow to the Proprietor a sum calculated and certified by the Architect at the rate stated in Item O of the Appendix as liquidated and ascertained damages for the period (commencing from the date so stated) during which the Works shall remain or have remained not brought to Practical Completion.
10.14.03 In the event of no further moneys being payable to the Builder or in the event of the sum calculated in accordance with paragraph 10.14.02 exceeding the amount remaining payable by the Proprietor to the Builder, the Proprietor shall be entitled to recover the same, or any such excess, as a debt due to the Proprietor by the Builder. "
26 Item O of the appendix, which had a cross-reference to clause 10.14.02, stated:
" O. 10.14.02 Rate for Liquidated and At cost at common
Ascertained Damages law (Maximum
$10,000 per week) "
27 Clauses 12.02 and 12.03 provided:
" 12.02 PROPRIETOR'S NOTICE OF BUILDER'S DEFAULT
If the Builder shall make default in any one or more of the following respects:
12.02.01 If he, without reasonable cause, wholly suspends the carrying out of the Works before Practical Completion thereof;
12.02.02 if he fails to proceed with the Works regularly and diligently;
12.02.03 if he fails to proceed with the Works in a competent manner;
12.02.04 if he refuses or persistently neglects to comply with written notice from the Architect requiring him to remove defective work or improper materials or goods; and
12.02.05 if otherwise he is guilty of a substantial breach of the provisions of this Agreement
then in any such case the Architect may deliver by hand to the Builder or send by certified mail addressed to the Builder a written notice stating the intention of the Proprietor to determine the employment of the Builder under this Agreement. That notice shall specify the default and, except for a default as referred to in paragraph 12.02.01, provide details of the default.
12.03 DETERMINATION BY PROPRIETOR FOR BUILDER'S DEFAULT
If the Builder fails to remedy in terms consistent with this Agreement a default of which he had been given notice under Clause 12.02 within ten (10) days of receipt of such notice then the Proprietor, without prejudice to any other rights or remedies, may within a further period of ten (10) days, by written notice delivered by hand to the Builder or sent by certified mail addressed to the Builder, determine the employment of the Builder under this Agreement. "
Deemed Practical Completion on 23 August 2004
28 The plaintiffs took possession of the ground floor hotel on 23 August 2004. The referee found that pursuant to clause 9.10.04, as the plaintiffs occupied and used part of the Works from that date, the whole of the Works were deemed to have reached Practical Completion on that date. No notice was issued by Quirk under clause 9.10.02. Nor could Quirk have issued a notice under clause 9.10.02 because no agreement had been made between Parkline and the plaintiffs in respect of the matters in clause 9.10.02.04.
29 The referee found that at the time the contract was entered into there was no agreement in writing for a staged completion of the project to permit early trading of the hotel portion prior to completion of the project (at [36]). This finding was not challenged. The referee found (at [40]) that:
" No objection was taken to the Principals' occupation of the hotel in August 2004 nor did either party allude to the operation of clause 9.10 of the Contract. "
30 The referee said of clause 9.10:
" 15. The general intent of the clause, I think, is clear. It sounds as a plain warning to the parties that premature occupation of part of the Works has the capacity to seriously disrupt the nature and intent of the Contract especially in areas of commencement of the defects liability period, the provision and withholding of security, the effect on liquidated damages entitlements or exposure, responsibility for liability for damage to property and the insurance to cover such contingencies - all matters of basic importance in the administration of and performance under the Contract.
16. In order to prevent unintended disruption of performance and responsibilities under the Contract, a particularly strict code is laid down to cover occupation of part of the Works prior to completion of the whole. I think that strict regime applies especially to non-consensual occupation of that kind by the Proprietor, but also extends to a consensual occupation.
17. While the occupation by the Principals of the hotel and related works prior to Practical Completion of the whole of the project was consensual, I am satisfied that the consensual arrangement did not effectively cover any of the essential ingredients of the notice of occupancy required pursuant to clause 9.10 prior to occupation by the Principals. The question then arises what 'other written agreement' is sufficient to entitle the Principals to occupy part of the project prior to completion of the whole without triggering the deemed Practical Completion operation of clause 9.10.
18. In the absence of some 'other written agreement' there is no ambiguity in the intended operation of clause 9.10. Before partial occupation may be taken by a proprietor there must first be agreement between the parties to the building contract on the four matters referred to in subparagraphs .01-.04 of clause 9.10.02, that is, agreement on the particular portion of the Works to be occupied; on the date upon which that occupation may take place; identifying the Date for Practical Completion and the effect of the occupation upon the provisions relating to insurance, liquidated and ascertained damages, security and the Defects Liability Period. Once agreement on those matters has been reached as between the parties to the building contract then and only then will the architect be entitled to give a notice of occupancy stating the substance of the agreement reached on each of those matters. It is only after such an agreement has been reached and the notice of occupancy given that the proprietor may take occupancy of part of the Works without triggering the deemed Practical Completion provision in clause 9.10.
19. In those circumstances, given the stringency of the provisions of clause 9.10, I think one is entitled to look for a clear intention of the parties to address the stringencies of these provisions by recourse to some 'other written agreement' to avoid triggering the deemed Practical Completion provisions of this clause. I think the 'other written agreement' should evince an intention to do so and generally that will only happen where the contractual implications of partial occupation highlighted by clause 9.10.02 have been dealt with, or at the very least adverted to. The consequence of not covering those matters in a consensual partial occupation runs the serious risk of voiding the related provisions of the Contract concerned with the enumerated matters in clause 9.10.02. That consequence will necessarily vary from contract to contract, depending upon the circumstances and any special conditions amending the JCC-D form of contract.
20. In their absence it is difficult to see how a liquidated damages clause could survive and agreement that did not address the operation of a [liquidated] damages clause post partial occupation. Not necessarily so, but almost invariably, an agreement, particularly relating to commercial premises, which does not address the effect of partial occupation on liquidated damages, will expose that provision to the construction of being a penalty. Similarly, the security provisions relating to the retention fund run the risk of dislocation as do, I think, the provisions relating to the commencement of the defects liability period, insurance and the Practical Completion contemplated under the Contract.
21. Unless the defects liability period is addressed, how is the architect to administer the Contract? Where is the justification for treating the defects liability period as dating from the completion of the whole of the Works reached at a point, for example, well after partial occupancy has occurred? In addressing those questions it is well to keep in mind the very particular provisions of the Contract setting down the regime for the notification of and rectification of defects. There should be little or no room for uncertainty in the operation of those provisions. Similar observations are equally applicable to the enforcement of the insurance provisions and security retention.
22. It does not follow that the 'other written agreement' must mirror the terms of the agreement contemplated in clause 9.10.02. While that is so the clear intention I have spoken of as required of the other written agreement will usually at least advert to the subject matters of the clause 9.10.02 agreement. However, there may be circumstances where the parties are content to leave the General Conditions unaffected by the partial occupation of the proprietor and may do so in clear terms. However, short of that, it is difficult to identify a written agreement which would satisfy the requirements of clause 9.10.04 such as to avoid triggering the deemed completion provision. For instance, a bare agreement consenting to partial occupation prior to completion of the Works would rarely, if ever, satisfy the requirements of clause 9.10.04.
23. I think it is to avoid such a dislocation of the operation of the General Conditions that the Joint Contracts Committee has opted for certainty where for whatever reason in the case of partial occupancy, be it consensual or otherwise, the parties will be required to strictly adhere to the mechanism of clause 9.10 or, in some equivalent way, avoid the triggering of the deemed Practical Completion operation of the clause by an entering into a written agreement that appropriately addresses the operation of provisions including 9.10, effected or potentially effected by a partial occupation of the Works prior to completion of the whole. "
31 The referee concluded:
" 89. ...
(d) In the absence of an architect's notice of occupation, there should be, in my view, an evinced intention by written agreement of the parties to address expressly or by necessary implication the fundamental implications of a major departure from contractual obligations and entitlements implicit in occupation of portion of the project prior to achieving practical completion of the project. I am satisfied that no such written agreement was brought into existence to satisfy that concept of 'other written agreement' in clause 9.10.04.
(e) The effect of the Principals going into occupation and using the hotel portion from 23 August 2004 prior to practical completion of the project in the absence of a prior agreement or notice of occupancy within the meaning of clause 9.10.02 resulted in deemed practical completion occurring on 23 August 2004. "
32 The plaintiffs challenged this construction of clause 9.10. They submitted that the referee erred in concluding that clause 9.10 applied to a consensual occupation. Alternatively they submitted that provided there was a written agreement between the Proprietor and the Builder in relation to the Proprietor's occupying the works or part of them before Practical Completion, Practical Completion was not deemed to occur on the date of commencement of such occupancy. The plaintiffs submitted that there was nothing in the text or context of the clause to support the referee's interpretation that an "other written agreement" in clause 9.10.04 had to deal with all the implications of the proprietor's taking early occupation of part of the Works. If there were such a comprehensive written agreement it would operate as a variation of the contract and it would be unnecessary to refer to such another written agreement in clause 9.10.04. The deemed consequences of early occupancy would be dealt with by the agreement itself. Counsel for the plaintiffs submitted that the referee's construction could lead to absurd results. They posited an example of a shopping centre with 100 shops being constructed and the date for practical completion having passed, practical completion being still some months off, the builder being very late, and the owner approaching the builder to have one shop occupied prior to practical completion being achieved. The plaintiffs submitted that clause 9.10.04 put beyond doubt that an agreement to such an effect would avoid the absurd consequence that deemed practical completion for the entire shopping centre took place merely because one shop was occupied.
33 Counsel for the plaintiffs submitted that if a proprietor failed to ensure that any agreement as to partial early occupation expressly dealt with liquidated damages, the proprietor would run the risk that a liquidated damages clause would become a penalty. Counsel submitted that there would not be uncertainty in relation to matters not dealt with by an agreement under which the proprietor took early occupation. The contract would operate in accordance with its terms on the basis that practical completion did not occur on the date of early occupation but only when all of the Works were practically complete. If this were harsh on the builder, the remedy was in its hands. It could insist upon terms dealing with the consequences of the proprietor's early occupation and the condition of its consent.
34 Counsel for the plaintiffs submitted that the phrase "other written agreement" in clause 9.10.04 referred to an agreement between the proprietor and the builder recorded in writing in relation to the proprietor's early occupation or use of the works. Counsel for the defendants did not dispute this. There was no requirement in clause 9.10.04 that the written agreement be signed by the parties. The plaintiff relied upon a number of minutes of site meetings and facsimiles which recorded the parties' agreement that the plaintiffs would take occupation of the hotel prior to practical completion and that they would take possession of the hotel area and associated areas on 23 August 2004. Only one such document arguably dealt with the consequences of early occupation. The minutes of the site meeting of 21 June 2004 purportedly recorded an agreement that:
" Liquidated damages would be imposed after the following revised contractual practical completion dates;