(xlii) The product of the above is at December 2002 the plaintiff owned land which had a value of about $1m. The alleged breaches by the defendant denied to the plaintiff the opportunity to develop his land so that by November 2004 it would have had a net value to him of $2,803,000.00, thus the plaintiff has lost $1,803,000.00.
(xliii) The calculation of the loss, if made at December 2002 would have required predictions and estimations but, because the calculations are to be made post November 2004, the plaintiff can rely on actual real estate transactions.
(xliv) It could be contended to account for that loss being made between December 2002 and November 2004 the $1,803,000.00 should be discounted, if so that should be at a rate no greater than 5.5% per annum.
(xlv) Alternatively it could be contended the estimated value of the land as is in November 2004 should be deducted from the $2,803,000.00, if so that estimated value can now be based on actual values and is no more than $1,350,000.00, therefore reducing the loss to $1,453,000.00.
(xlvi) However, no reduction should be made because calculating compensation at the date of the breach will produce an unjust result to the plaintiff because the loss of opportunity is permanent and ongoing, his real loss is far greater than $1,803,000.00 and on balance the quantum should not be calculated in a manner which benefits the defendant.
(xlvii) It may further be contended the plaintiff would have sold either or both of the ground and mid-floor units but if so the quantum of compensation would be the same because instead of having the units the plaintiff would have had the value of the units as at the date of completion in November 2004.