Bartel v Ryan
[2018] NSWCATAP 231
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2018-09-10
Source
Original judgment source is linked above.
Judgment (25 paragraphs)
Summary
- These reasons concern an appeal from the Consumer and Commercial Division of the Tribunal (the Tribunal) of 2 May 2017 (the Decision).
- The appellant, Mr Peter Bartel (the Builder), commenced proceedings HB 17/04880 against the respondent, Ms Catherine Ryan (the Homeowner). Subsequently, the Homeowner commenced proceedings HB 17/07028 against the Builder.
- In the Decision, the Tribunal dismissed the Builder's proceedings. In the Homeowner's proceedings, the Builder was ordered to pay Ms Ryan $62,300.00. The Builder appeals in relation to that decision.
- For the following reasons, we have decided to extend the time for the Builder file the Notice of Appeal, to dismiss the appeal, and to refuse leave to appeal.
Preliminary
- The grounds of appeal are many and various, and have been set out in three iterations, namely:
- the four grounds of appeal set out in the Further Amended Notice of Appeal dated 7 August 2018;
- the further seven grounds of appeal appearing in the Builder's submissions dated 31 July 2018; and
- the further ten matters (some of which overlap with the grounds in the Notice of Appeal and the submissions) appearing in a Schedule titled "Schedule of Monies Appellant Says He Should Not Have Been Ordered to Pay" (the Builder's Schedule). This was provided to the Appeal Panel after the hearing. The Appeal Panel sought the Schedule so as to clarify precisely the matters sought to be agitated by the Builder.