Bannister & Hunter v Transition Resort Holdings
[2014] NSWSC 1081
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2014-08-12
Before
McDougall J
Catchwords
- PROCEDURE - Referee's report - adoption - whether to adopt referee's report - where party tried to reargue issues on the adoption which had already been decided by the Court
Source
Original judgment source is linked above.
Catchwords
Judgment (9 paragraphs)
Judgment 1HIS HONOUR: The plaintiff (BH) agreed to provide design and project management services to the defendant (Transition) for a proposed residential subdivision to be undertaken by transition at Fern Bay, north of Newcastle. Each party claimed that the other was in breach of that contract. BH claimed for unpaid fees. Transition, disputing that it owed all the fees claimed, said in addition that it suffered damage because BH's services were provided negligently and in breach of contract.
The proceedings to date 2I gave judgment on 20 December 2013: Bannister and Hunter v Transition Resort Holdings (No.3) [2013] NSWSC 1943. I concluded in substance that: (1) BH was entitled to recover the fees claimed by it together with interest; and (2) Transition had made good most, but not all, of its claims for damages. 3I quantified Transition's damages, for all but one of the heads of claim on which it succeeded, in amounts totalling $565,521.00. The parties agree that there is an arithmetical error in my calculations, and that, for those heads of damage and on my conclusions, the arithmetically correct total is $667,021.00. 4However, I came to the view that the evidence was not sufficient to enable me to quantify the largest single item of damages claimed by Transition. That claim related to what the parties called, as did I in my earlier reasons, VENM. The acronym denotes "Virgin Excavated Natural Material". It refers to a layer of fill that was used to cap and grade the surface of the site. I found that the VENM layer did not comply with the specification, because it contained numerous oversized particles. 5For the reasons that I gave at [294] to [301], I took the view that the parties should attempt to agree on the method of rectification and the cost. Against the possibility (which, having regard to the way the litigation was conducted, could more accurately be described as "the probability") that the parties could not agree, I said that I would refer those questions out. 6For convenience, I set out those paragraphs of my earlier reasons: [294] The evidence is lamentably imprecise on this point. The basic method of rectification would appear to require that the VENM layer be ripped up, crushed and relaid. [295] Mr Mostyn suggested that it might be possible to put up with the deficiencies in the fill, and to measure damages by the incremental cost of utilising heavier earthmoving equipment for the installation of services. [296] As an alternative, Mr Mostyn suggested that if the fill did require ripping up and crushing, it should be screened so that only oversized material was re-crushed. As he pointed out, if the oversized material comprised 15% of the whole (and he did not accept that the photographs showed this), then 85% of the fill need not be crushed. Mr Shirley appeared to accept that it would only be the oversized material that should be crushed. [297] Mr Shirley gave evidence, although extremely imprecise, as to cost. His view (that the cost of ripping up, crushing and relaying would be about $28.00 per tonne) was based apparently on inquiries made of contractors, supplemented by reference to standard construction costs guide. Without being disrespectful to Mr Shirley, I do not have any confidence in his estimate based on those (principally) unspecified and untested sources. Nor does that evidence deal with the matter referred to in the previous paragraph, or its cost consequences. [298] When I deal with the next and last issue, I conclude that Transition is entitled to recover the reasonable costs of rectification notwithstanding that it has sold the site and appears to have no ongoing interest in its development. That means that it will be necessary for the cost of rectification to be ascertained in some way. [299] Towards the end of submissions, I proposed to Counsel that if matters got this far, I would be inclined (if the parties could not agree on a figure for the cost of rectification) to refer out the questions of how the defects should be rectified and what would be the cost. I said that if I did take this course, it would be necessary to consider the question of the costs of the reference, given that all issues (including all issues of damages) had set down for hearing in court. [300] Mr Weinberger accepted the proposition that there should be a reference out in the circumstances that have arisen. Mr Windsor did not appear to oppose this course. [301] Accordingly, the course that I shall take in respect of the costs of rectification is to stand the matter over so that the parties can attempt to agree on a figure, and to refer the relevant questions out if they cannot. 7The parties could not agree. Accordingly, the issue summarised at [299] was referred out to Mr Steven Goldstein of Counsel as referee. 8The order for reference was made on 18 February 2014. The question referred to Mr Goldstein was: What is the nature, extent and cost of the works required to rectify the bulk earthworks on the land at [title description inserted] arising out of the breach of contract by [BH], as set out in [the relevant paragraphs of my earlier reasons]? 9By agreement, and to rectify what the parties saw as being some lack of precision, that question was varied on 30 April 2014 so as to insert after the word "earthworks" the words "so as to bring the VENM layer into conformity with the specification". For convenience, I repeat the question with that change: What is the nature, extent and cost of the works required to rectify the bulk earthworks, so as to bring the VENM layer into conformity with the specification, on the land at [title description inserted] arising out of the breach of contract by [BH], as set out in [the relevant paragraphs of my earlier reasons]? 10Mr Goldstein reported, with commendable efficiency, on 27 June 2014. It is apparent from his report that the parties' experts had agreed on the method of rectification, and on the cost, in each case on the assumption that the whole of the VENM layer was to be brought into conformity with the specification. As is apparent both from the report and from the outline submissions (including the statements of findings of fact and law for which each contended - UCPR r 20.20(5)), the real issue was whether the cost of rectification should be limited to what BH called the "Undeveloped Portion" of the site, or whether, as Transition contended, it should relate to the whole of the site. 11Mr Goldstein concluded that he was bound, both by my reasons and by the nature of the question referred, to conclude that the cost should be for rectification of the whole site. On that basis, he concluded (as the parties' experts agreed) that the cost would be $2,104,112.00.