Sixth issue: supervision of Coffey
231For convenience, I set out once more the services that BH offered to provide in respect of bulk earthworks:
3. Bulk Earthworks
(Including contamination treatment based on capping only required)
Project Management: Peter Barclay
- Liaise with Client, Geotechnical Engineer, Council or Certifier call tenders, report to client
Engineering Design: Chris Slater
- Regrade existing surface details
- Fill Detail
- Soil and Water Management Plan
Contract Supervision: Chris Slater/Peter Barclay
Survey: Peter Barclay
Set out SEPP 14 boundary
Monitor levels/Work as Executed
232I deal first with Mr Weinberger's submission that the fee agreement called for supervision of, among other things, "work as executed". I do not accept that submission.
233"Contract Supervision" is a separate item, for which a separate fee was quoted. The reference to "Work as Executed" appears in relation to the separate item "Survey". It is apparent that whatever was comprised in respect of "Survey" was additional to, or separate from, whatever was required in respect of the previous topics covered by the fee proposal, which included "Project Management" and "Engineering Design" as well as contract supervision.
234As I read the proposal, the services that BH offered to provide, in respect of survey, were those that followed this subheading. That is to say, BH offered:
(1) to set out the SEPP 14 Boundary;
(2) to monitor the levels of the bulk earthworks during the performance of the contract; and
(3) to survey the works as executed.
235Mr Weinberger relied also on what the experts had agreed. I set out paras 60 and 61 of the joint report:
60 AS and BS agree that BH agreed to supervise the earthworks contractor in accordance with its letter dated 14 September 2006 and subsequent email chain on 19 September 2006, and our reading of other documents.
61 GM considers that this is a matter of fact and does not consider he has sufficient facts to provide an opinion.
236I do not regard the opinion expressed by Messrs Shirley and Staniland as carrying any persuasive weight. The obligations that BH undertook are to be found in the contract that it made. What that contract requires is a matter of construction. That is a question for the court.
237I accept that if the contract, on its proper construction, provided that BH was to supervise (among other things) Coffey's performance of its obligations as geotechnical consultant, then the views of the experts as to what a reasonable project manager, in the position of BH, should have done to satisfy that obligation might have some probative value. But that is not the topic the subject of the opinion expressed by Messrs Shirley and Staniland at para 60 of the joint report.
238Notwithstanding what I have just said, Mr Barclay accepted that BH was required to supervise the work as executed (T194.4-.6):
Q. It was your express role under the retainer agreement to supervise the work as executed, correct?
A. Yes.
239I take this concession to mean that Mr Barclay accepted that BH, as part of its project management and contract supervision roles, was to supervise the various contractors, including Robson as bulk earthworks contractor and Coffey as contractor to provide geotechnical services. If that is the proper understanding of this concession, then it does seem to me to reflect the proper construction of the relevant requirements of the contract between Transition and BH.
240Transition engaged Coffey to provide, among other things, level 1 supervision (strictly speaking, "services") in respect of the earthworks. I have set out at [29] above the content of that obligation, as it appears from the relevant Australian Standard.
241Mr Barclay gave evidence as to his understanding of Coffey's obligations in respect of level 1 services (T176.46-177.17):
Q. It was at least by this point in time, that is 7 March 2007, that Mr McCool had instructed you to arrange for Coffeys to provide level 1 -
A. Yes.
Q. - supervision?
A. Yes.
Q. At that time did you know what level 1 supervision entailed?
A. Yes.
Q. What was your understanding as of 7 March 2007 was level 1 supervision entailed?
A. It entailed an officer from or an employee from Coffeys being on site for the receipt of any material for the site and for the spread and compaction of all material over the site.
Q. Without interruption, that is 9 to 5 or 10 to 7, whatever the case may be, full time on site?
A. Yes.
Q. Whilst material was being delivered to the site?
A. Yes.
242Mr Barclay then gave evidence as to what he understood his obligations to be, in respect of ensuring that Coffey would provide level 1 services (T178.4-.49):
Q. Did you ever suggest to Coffey in May 2007 that it provide something less than level 1 supervision?
A. No.
Q. Can I ask you to turn please to tab 17 of BM-1. Do you see that?
A. 17, yes.
Q. I direct your attention to the third paragraph commencing "secondly"?
A. Yes.
Q. You instructed Coffeys to drop in on the site twice a day rather than provide level 1 supervision at least at that point in time, correct?
A. I'd have to look at my advice that this was responding to.
Q. You didn't respond to this email, did you?
A. That is the April response to me. I relied on Coffey's -
Q. I understand you are eager to say that, but what I am suggesting to you is that at least in May 2007 you instructed Coffeys to drop in on the site twice daily. Do you agree with that or do you disagree?
A. I didn't instruct that, no.
Q. To the extent that Coffeys were retained to provide reports and services in connection with this project you or your firm were the interface or go-between between Transition and Coffey, correct?
A. Between Transition - yes.
Q. So, if Coffeys were instructed to provide level 1 supervision, that instruction would have come from you?
A. Yes - no, actually. It came from Mr McCool.
Q. Notwithstanding that, Mr McCool instructed you on numerous occasions to arrange for level 1 supervision?
A. Yes.
Q. That was at least your role to ensure level 1 supervision was being carried out?
A. It was my role to make arrangements to ensure that happened.
Q. Once the arrangements were made to ensure that it was being carried out -
A. Not if you are suggesting I needed to be on site full time, that is not the case.
Q. To do what was reasonably necessary to ensure that level 1 supervision was being carried out in a competent manner?
A. Yes.
243Mr Barclay said that, on days when material was not being delivered to site, and when no regrading works were being carried out, he thought it was in order for Coffey to "[drop] in on the site twice a day" (T179.23-.41). However, when fill was being delivered and spread and compacted, he agreed that Coffey was required to be on site for the whole of that process (T179.38-.46).
244Mr Barclay was asked to identify, by reference to his diaries, days when he went to the Fern Bay site. His response (having had some opportunity to undertake this task, over the short adjournment) was less than satisfactory: he identified pages where the site had been referred to, none of which recorded any observations made on a site inspection.
245I took the view that Mr Barclay should not be required to use adjournments for the purpose of satisfying Mr Weinberger's hunger for information. The diaries were available to Mr Weinberger. It was open to him to tender them, and make such point as he wished (either in cross-examination or in submissions, or in both) by reason of what was or was not shown in them. He did not do so.
246Section 6.9 of the FCPQS provided for the "Design Consultant" to undertake a process of audit and review:
6.9 Auditing and Review by the Design Consultant
The purpose of the auditing and review process is to give an independent appraisal of the performance of the backfilling operation and therefore the attainment of suitably reinstated land. The auditing process incorporates all activities associated with solicitation, inspection and material acceptance, as well as contaminated material management and employee training.
247At an earlier point in the FCPQS, BH was identified as the "Design Consultant".
248Mr Barclay was cross-examined about para 6.9. At first, he appeared to suggest that it did not apply - or apply "completely" - to BH. However, when his attention was drawn to the definition of "Design Consultant", he accepted that it did.
249Mr Barclay maintained that BH did perform its obligations under para 6.9. I set out the whole of this passage of his evidence (T192.1-194.2):
Q. All right. Can I ask you please to turn to page 397--
A. (Witness complied.)
Q. --and draw your attention to paragraph 6.9. Can you read that to yourself please?
A. (Witness complied.)
Q. Don't worry about the next page. That identifies - paragraph 6.9 identifies your role in relation to the fill, does it not?
A. I can't see this saying in it that I am the auditor--
Q. "Auditing and review by a design consultant", is that not Bannister & Hunter?
A. Not completely, no.
Q. Can you turn to page 386 please. You will see that Bannister & Hunter are clearly identified in the second bullet point as the design consultant. Do you see that?
A. Yes.
Q. Did you read this document at or about the time you received it?
A. Yes.
Q. Do you now accept that paragraph 6.9 is referable to Bannister & Hunter?
A. Yes.
Q. And Bannister & Hunter were required to conduct an auditing and review process, do you agree?
A. Yes.
Q. To provide an independent appraisal of the performance of the back filling operation?
A. I can't accept responsibility for--
Q. I didn't ask you about responsibility, I said to give an independent appraisal of the performance of the back filling operation?
A. A general overview, yes.
Q. And, therefore, the attainment of suitably reinstated land, correct?
A. Yes.
Q. And the auditing process incorporated all activities associated with solicitation, inspection and material acceptance. Do you see that?
A. I am sorry, I am not sure where you are - yes.
Q. Now, insofar as solicitation is concerned, that meant working out where the fill came from, correct?
A. Correct.
Q. Quotes for the placement of the fill, correct?
A. Quotes for the placement of the fill - I don't see that in here.
Q. And it involved assessing whether the fill that was introduced to the site was appropriate or not, agree?
A. Assessing the reports provided by the geotechnical.
Q. And assessing what you observed on site?
A. Yes.
Q. Because you did not need to attend the site weekly to read reports which Coffeys may have provided you with. Correct?
A. Correct.
Q. And insofar as inspection and material acceptance is concerned, that involved undertaking inspections of the site during the course of fill delivery?
A. Yes.
Q. And the placement of the fill at the site?
A. Yes.
Q. And would you accept that you did not conduct this project consistently with paragraph 6.9?
A. We carried out those roles.
Q. Well, a few moments ago I think your position was that 6.9 did not apply to you. Do you recall saying that?
A. Yes.
Q. And then I took you to the definition of design
WINDSOR: I object to that question, your Honour. That is not quite the answer that my learned friend got in response to the question. I don't say anything more. I don't ask the witness to leave.
WEINBERGER: I will withdraw the question.
Q. Did you give evidence to the effect, about five minutes ago, that 6.9 did not apply to Bannister & Hunter?
A. I
Q. "Yes" or "no"?
A. I can't I can't tell you the answer to that, sorry. I recall saying I did not think we were the auditors.
Q. Thank you. What I want to suggest to you just one more time is that Bannister & Hunter did not discharge its obligations consistently with 6.9 of the FCPQS. I am not suggesting there was any conspiracy or that it was deliberate. I am suggesting to you that for whatever reason Bannister & Hunter did not discharge its obligations in 6.9 in a competent manner on this job?
A. Well, I don't accept that with the exception of employee training.
250Mr Barclay was not re-examined on this topic: specifically, on the rather Delphic exception in his last answer.
251Mr Windsor submitted, and I accept, that Coffey bore the responsibility for ensuring that the specifications for the supply and compaction of fill were complied with. It appears to be common ground that those specifications emerge from a number of places, including AS3798 and the FCPQS, and perhaps other documents prepared by Coffey.
252Mr Windsor submitted, further, that whatever might be the obligations BH had undertaken in respect of project management and contract supervision, they could not extend to being on site all day every day to ensure that Coffey was doing what it had contracted to do. BH was not to be the guarantor of Coffey's performance of its obligations.
253Further, Mr Windsor laid stress on the FCPQS, which required Coffey, among other things:
To monitor processes affecting the quality of the compacted fill and test and verify conformance with specified requirements.
254In conclusion, Mr Windsor submitted:
In all the circumstances it could not be said that BH had a contractual responsibility to [Transition], to undertake work which was to be performed by Coffey's and/or bulk earthworks contractors.
255The last submission misses the point. However, the previous submissions that I have recorded are correct, so far as they go.
256The last submission misses the point, because it is not Transition's case that BH was required to do the work that Coffey, or for that matter Robson, was contractually obliged to do. Transition's case, on this aspect of the claim, is that BH was required to supervise Coffey's performance of its obligations: to take reasonable steps to ensure that Coffey did what it had contracted to do, and provided the services that it had contracted to provide.
257It may be accepted that BH's obligations of project management and contract supervision did not require it to procure a geotechnical consultant to check what Coffey had supposedly tested and validated. Nor did it require BH itself (assuming it had the ability to do so) to undertake such tests. But in my view, it did require that someone from BH should go to the Fern Bay site regularly, and not infrequently, to observe for himself or herself what was being done.
258Accepting, as the evidence suggests, that the deliveries of fill were intermittent (because of supply problems), nonetheless BH should have made site visits regularly, and again not infrequently, when fill was being delivered, spread and compacted. Among other things, BH would ascertain thereby that a Coffey representative was on the site, and was supervising the importation, spreading and compaction of fill.
259Mr Windsor submitted that BH understood (correctly) that Coffey was required to supply reports at the conclusion of the earthworks, including the validation report and the regrading report. However, those reports, of necessity, would deal with the situation at the conclusion of the works. They would (purport to) show that the works had (or had not) been carried out in accordance with the specifications. The preparation of them would assume that Coffey had been on site, and performed such tests, as might be necessary to justify the conclusions expressed.
260I do not think that the obligation of project management and contract supervision, in respect of services to be provided on a daily basis by a consultant, is satisfied simply by receiving a report from the consultant, at the end of the works, stating what had been done. If that were correct, the consultant would become in effect the project manager and supervisor of its own obligations.
261The view that I have just expressed is supported by the agreement of the experts, as to how the obligation of project management and contract supervision might be performed, in respect of the importation and placement of fill. Their agreement relates not to the content of the duty but to how a reasonable project manager, in the position of BH, might perform it. Thus, I do not consider my reliance on what the experts say as inconsistent with what I have said at [236] above.
262At paras 74 and 75 of the joint report, the experts state:
74. We agree that a reasonably competent person in the position of BH would have inspected the importation of fill to the Fern Bay site.
75. We agree that the inspection interval should have been approximately weekly while fill was being imported or placed.
263To my mind, the most compelling evidence as to the adequacy of such supervision as BH performed comes from observations made by Mr Shirley as to the presence of oversized rocks on the site.
264The FCPQS specified that the capping layer should not contain "particles" larger than 100mm in size. An attempt was made in the course of Mr Barclay's cross-examination to suggest that this applied to the VENM layer also. That is not the proper construction of the FCPQS.
265However, it appeared to be common ground that the maximum particle size in the VENM layer (which should have been placed and compacted in layers) was two-thirds of the thickness of the layer before compaction.
266It was assumed that the VENM would be placed in layers 300mm thick and compacted (the FCPQS suggests 250mm, but nothing turns on this). On that basis, the maximum particle size would be 200mm.
267Mr Shirley's evidence, which is based on observations that he made on a site visit and is confirmed by photographs, is that the fill did not comply with either the Coffey specification or AS3798 (para 58 of his first report). He gave a number of reasons. One was that "[t]here were many large rocks and boulders within the fill material". He said that their size was such that the layers would have to have been about 1.3 metres thick for the particles to comply with the "2/3" requirement. He noted that a layer thickness of that size would not comply with Coffey's specification for placement in 300mm layers.
268Further, when test pits were dug at Mr Shirley's direction, there was in his view no evidence that the fill had in fact been placed in layers. If this were so, it points to another breach of the specification (including the relevant requirements of AS3798).
269Mr Shirley's summary of results obtained from test pits included the observation that "[t]he fill materials are also a heterogeneous mix of clayey sands, sandy clays, silty clays, cobbles, and boulders/large rocks up to 900mm in size". He commented in particular on the presence of "appreciable boulders" in what was in effect the VENM layer.
270Mr Shirley addressed this topic in his oral evidence. He said, of present relevance (T271.32-272.15):
When I undertook investigations at the site the first thing I did, of course, was to walk over the site. There's an awful lot of boulders you can see all over the surface.
HIS HONOUR: What do you mean by "boulders" in this context?
WITNESS SHIRLEY: Things up to 900 millimetres in dimension. That would be the maximum dimension. They may only be 5 to 600 millimetres thick. But an awful lot of big boulders. A lot of - a preponderance probably at 600 millimetre dimension. They are over the surface of the fill, you can clearly see, and I've presented those photographs in my report. And along the western boundary some of the boulders are very much larger than that. They're well over a metre, metre and a half. I presume that they were, as it were, raked out during the course of the fill placement.
So we then excavated a number of test pits during the course of our inspections. During the excavation of these test pits we found a number of these large boulders. In terms of percentage terms, I have a difficulty in assessing the percentage of the total quantity in respect of the amount. It might be 20 per cent of the fill was this, it might be 15 per cent, but I didn't do an accurate figure. All I saw was an awful lot of them in a lot of the test pits. There were more in some places than in others. So in some places there appeared to be a lot of them; in other places it didn't appear as many. I think it is important that whilst there's a lot of big boulders, there was a large preponderance of boulders around the 4 to 600 millimetre dimension.
The other thing is when I excavated these test pits there was no evidence of any layering in the fill. When the fill has been placed and compacted one of the things that you really notice is it seems this sort of - you can see the layers where they have rolled and compacted the surface. You could expect in a fill like this the fill to be placed in layers, I don't know, 3 to 400 millimetres thick, maximum 500. Three to 400 with large equipment. And you would see layers of where those layers were because they would be tested by the individual consultants.
271I should note that Mr Shirley had an additional criticism of the VENM layer: namely that, to be fit for Transition's intended use, the maximum particle size should be no greater than 100mm. To the extent that this is a problem, it does not appear to be one for which BH has any responsibility. Coffey prepared the specifications for the fill. If those specifications were inadequate, that is a matter between Transition and Coffey.
272To the extent that Mr Shirley's observations of large (or "appreciable") boulders were based on observations made in his test pits, it could not be suggested that BH was required to dig and inspect test pits. Nonetheless, I think, if BH had undertaken regular site visits and inspections while the earthworks were being imported, placed and compacted, it would have detected the presence of oversized material. Mr Shirley's evidence of the extent of oversized material throughout the VENM layer renders that conclusion irresistible.
273Further, to the extent that Mr Shirley refers to oversized material on or visible on the surface of the site, that again is something that would have been detected by regular inspection.
274Indeed, Mr Barclay agreed that when he did go to site, he did observe large rocks spread over the site. That was from as early as September 2007 through to the end of BH's retainer (T199.26-200.1):
Q. I want to suggest to you that there are a number of large rocks and boulders on site?
A. Yes.
Q. And that you have observed other material which does not comply with the specifications?
A. That is not the case.
Q. You have seen photographs contained in the exhibit to Mr McCool's affidavit and annexed to Mr Shirley's report which suggests that, correct?
A. I have seen the photos.
Q. When you went to site during these various site visits you observed a number of large rocks spread over the site, didn't you?
A. Yes.
Q. And you observed that from as early as about September 2007, didn't you?
A. 2007, yes, that would be I think right.
Q. And notwithstanding the fact that you observed rocks, or when I say "rocks" I mean boulders, do you accept that?
A. Yes.
Q. From as early as September 2007 they remained on site at the time your retainer came to an end, didn't they?
A. Yes.
275Mr Barclay said, further, that all the boulders were on the surface of the site - at most, "buried at surface level so they can be just pulled out" (T200.16-.21).
276Mr Barclay seemed not to accept that there were boulders below the surface. But it appeared that he had no personal knowledge, and was relying on Coffey's validation report (T200.23-.34).
277Somewhat surprisingly, in view of his concessions as to the presence of boulders on site throughout (in effect) the performance of the stage 1 works, Mr Barclay would not accept that the logical inference that he had failed to take adequate steps to ensure that rocks and boulders were removed (T200.3-.7).
278I find that position difficult to understand. Mr Barclay understood that particle sizes should not exceed 200mm. He agreed that, over virtually the whole of the stage 1 works, he had seen "large rocks" or "boulders". That must have suggested to him that Robson was importing and placing fill that was noncompliant because it included oversized particles. If the particles were observed on the surface, all over the site, it could not be safe to assume that similar particles were not buried and compacted in the VENM layer. More importantly, however, the continued presence of such particles on site does suggest a failure of supervision on the part of BH.
279As I have indicated, Mr Shirley's evidence confirms that oversized particles were contained within the compacted VENM layer.
280Perhaps not surprisingly, the experts agreed that competent inspection should have indicated the presence of oversized particles, and thus that the fill did not comply (in this respect at least) with the specification. There was some disagreement as to the size of particles that should have been observed, but nothing turns on this.
281The evidence of the experts - in particular, the evidence of Mr Shirley, including his photographs - leads inevitably to the conclusion that the fill did not comply with the specification because of the extent of oversized particles (more accurately, large rocks or boulders) within it.
282Mr Barclay accepted a number of relevant propositions:
(1) if there were oversized material onsite, within the VENM layer, it would create difficulty with the installation of services if not removed or broken down (T188.8-.22);
(2) level 1 supervision (I interpolate, properly performed) would detect and require the removal of oversized particles that had not been broken down in the compaction process (T189.7-.10);
(3) Mr McCool was "anxious" to ensure that Coffey would provide level 1 services, and that Mr Barclay would ensure that Coffey did so (T188.24-.38);
(4) by attending the site, Mr Barclay could ascertain if Coffey were undertaking level 1 inspection (T188.43-.45):
(5) he was required, in the course of his site inspections, to look for oversized particles (T189.14-.16); and
(6) if, on inspection, he observed oversized material (or non-complying material) he would at the least draw it to Coffey's attention, seek an explanation and instruct that non-compliant material should not be taken onto the site (T189.23-.49). I set out this last passage:
Q. I am sorry, it was a lengthy question. Assuming you observed boulders or material which did not comply with the specifications in terms of particle size, it was your role to liaise with Robsons and Coffeys in relation to that. Do you agree with that proposition?
A. No.
Q. So is it your position that you were entitled to observe boulders and other non-complying material and just do nothing about it?
A. No.
Q. Do you accept that a reasonable project manager in your position would have contacted Coffeys and at the very least drawn it to Coffey's attention and required an explanation?
A. Yes.
Q. And likewise would have drawn to Robson's attention and taken steps to ensure that further non-complying material was not brought onto the site?
A. I was relying on Coffeys.
Q. You might have been but it was your role in those circumstances to contact Robsons who are issuing progress claims for hundreds of thousands of dollars to make sure that they cease bringing onto the site non-complying material. Do you agree?
A. Yes.
Q. And those are steps which you should have taken, correct?
A. Yes.
283Mr Barclay did say that he took steps of the kind just referred to (T190.1-.5). If he did, those steps were, on the evidence that Mr Shirley gives and his photographs confirm, singularly unsuccessful.
284In my view, BH failed to perform in any satisfactory or reasonable way its obligation to supervise the bulk earthworks, including in this both the performance by Robson of its contract with Transition and the performance by Coffey of its contract with Transition. If BH had attended site at least weekly, during the importation, spreading and compaction of fill (as the experts suggested, and I conclude, was reasonable), it must have observed that oversized particles were being imported and compacted into the fill. The prevalence of oversized particles, both within and on top of the fill (as Mr Shirley reports and as his photograph show) leaves no other conclusion open.
285If BH had attended, and had observed, oversized particles then, as Mr Barclay accepted, it should have contacted Coffey, sought an explanation, and directed that non-compliant fill not be brought to the site. There is no evidence of BH's taking any of those steps.
286There seem to me to be two possible (and possibly cumulative) explanations of the situation that emerged, and of the extent of non-compliance reported by Mr Shirley.
287The first is that BH did not inspect with anything like the regularity required to ensure that the contracts that it was being paid to supervise were in fact being performed, so far as routine inspection could detect, properly.
288The second is that, to the extent that there were inspections, they were performed with insufficient care, and thus ineffective to detect the non-compliance that appears to permeate this aspect of the works.
289I find that the proper performance of regular (weekly or otherwise) and careful inspections would have detected the presence of fill that was non-compliant because it was oversized. On Mr Shirely's estimate, some 15% to 20% of fill that was non-compliant. It should be noted that Mr Shirley's observations and estimate apply only to oversized particles that had not themselves been broken down in the process of compaction. No doubt, some were, so that the percentage of non-compliance observable before compaction is likely to have been higher.
290I add that even if Mr Shirley's percentage figures overstate the extent of the problem, the whole of the evidence (including the photographs) makes it clear that the site was riddled with obviously oversized particles (or rocks, or boulders).
291I accept, as Mr Windsor submitted, that BH was not required to do the job that Coffey was retained to do and paid to do. But BH was required to take reasonable steps to satisfy itself that Coffey was indeed doing the job that it had been retained to do and paid to do. If BH took any steps - and I am not prepared to find that it did - they must have been utterly inadequate. There is no other available explanation for the extent of non-compliance apparent on the evidence as a whole.
292Thus, I conclude, BH did breach its contractual obligation of contract supervision, in respect of the bulk earthworks.