REASONS FOR JUDGMENT
Introduction
1 Chemeq Limited (Chemeq) is a public company included in the official list of market for securities operated by the Australian Stock Exchange (ASX). It owns intellectual property associated with an acrolein-based polymeric antimicrobial developed as an alternative to antibiotics for the prevention and control of intestinal bacteria diseases in intensively reared livestock (the Chemeq Product). The technology underlying the Chemeq Product has other possible applications including inorganic sunscreens, preservatives in cosmetics and human pharmaceuticals.
2 On 22 December 2004 the Australian Securities and Investments Commission (ASIC) commenced proceedings in this Court against Chemeq. ASIC sought declarations and penalties against the company because it had contravened the Corporations Act 2001 (Cth) (the Act) by failing to disclose to the ASX information material to the price of its shares.
3 Following various interlocutory steps and discussions between ASIC and Chemeq, the number of contraventions alleged was reduced to two. The first of these concerned what might broadly be called cost overruns in the construction of a facility for the manufacture of Chemeq's product at Rockingham. A figure of $25 million known to the market increased between February 2003 and April 2004 to $35 million, then $45 million, then $50 million without market disclosure.
4 The Second Contravention related to the effect of a patent obtained in the United States relating to a process for formulating the Chemeq product. The patent had no commercial significance, a fact which was not disclosed to the market in a material trading period between 6 and 7 October 2004.
5 Chemeq has admitted these contraventions of the Act. ASIC and Chemeq both submitted that penalties of $150,000 for the First Contravention and $350,000 for the Second Contravention are appropriate. The maximum penalty for which the law provides increased between the time of the first and second contraventions from $200,000 to $1 million. So although the First Contravention was the more serious of the two, the penalty proposed is lower because the maximum penalty applicable is significantly lower.
6 For the reasons that follow I am satisfied that it is within the power of the Court to make declarations that the contraventions alleged did occur. On the Statement of Agreed Facts submitted by the parties, those contraventions are established. I am also satisfied, having regard to the relevant sentencing principles, that the penalties proposed are appropriate and will make orders accordingly. Chemeq will also have to pay ASIC's costs of the proceedings agreed at $170,000.
The cost overruns in the construction of the Rockingham facility
7 On 30 April 2002 Chemeq informed the ASX, in a media release, that it had begun construction of a commercial production facility at East Rockingham. After announcing the raising of $5 million at $2 per ordinary share in placements to institutional and other sophisticated investors it added:
Additionally, Chemeq also announces that it has begun construction of its commercial-scale production facilities in Western Australia, budgeted to cost $25 million over a period of approximately 12 months. The facility, located 40 km south of Perth at East Rockingham, is being built and financed in stages. The plant, on an 8-hectare site, will produce all requirements to 2006/7 and is being built to internationally approved US Food and Drug Administration (FDA) Standards.'
8 Dr Graham Melrose, then Chairman and Chief Executive Officer of Chemeq, was quoted as saying that the first commercial stage of the plant was due to be commissioned in the first quarter of 2003 with immediate sales to Asian countries planned. Sales world wide would follow. The Chemeq product was one of those which it was said would be manufactured at the proposed facility.
9 On 2 August 2002 Chemeq made a announcement to the ASX to the effect that it had raised approximately $8 million. It said:
'Combined with earlier placements to other institutions and sophisticated investors, Chemeq has raised approximately $15.5 million this year.'
Each new share had carried with it one free option exercisable at $2.30 before 31 January 2003. The company expressed its optimism that the additional $8 million in options would be substantially taken up. The release then stated:
'The funds raised will be used for the construction of Chemeq's $25 million manufacturing facilities, which are being built and financed in stages.'
A release, on 9 August 2002, announced the raising of an additional $2.6 million from institutions and sophisticated investors, bringing the company's total capital raising for the year to $18 million.
10 On 16 December 2002 in a further media release Chemeq referred to the manufacturing facility and said:
'. The eight-hectare site for the manufacturing facility has been granted all regulatory approvals for plant construction of total output 250 tonnes per annum.
. Currently, Chemeq is constructing infrastructure for 250 tonnes per annum output, including offices, laboratories, amenities, warehousing and formulation areas.
. At this stage of construction, flooring, concrete slabs including hydraulic and electrical services in the entire offices, laboratories, amenities, warehousing and formulation areas have been completed; except for the formulation areas, all walls have been completed and roofing structures begun.'
. Construction is to FDA standards for veterinary manufacture. FDA regulations limit scale-up rate to 10-fold expansions between successive plants; on this basis, Chemeq is currently constructing a 20 tonne per annum process output - with 200 tonne per annum planned to immediately follow. This additional manufacturing capacity will be majorly funded by cashflows from the 20 tonnes per annum facility.'
11 On 4 February 2003, Chemeq announced the raising of a further $10.6 million from option holders, bringing its total capital raising for the preceding 12 months to $28.6 million. It said:
'The funds will be used for the construction of Chemeq's $25 million manufacturing facility, which is due for completion towards the end of first-half of 2003. The manufacturing facility is being built on an 8-hectare site, to internationally approved US Food and Drug Administration (FDA) standards.'
Initial output from the manufacturing facility would be sold in South Africa and New Zealand where Chemeq had regulatory approvals. Australia, Asia and other international markets were to follow. The potential global market was estimated to be worth AUS$10 billion.
12 A meeting of the directors of Chemeq was held on 10 February 2003. The minutes of that meeting record a discussion about Chemeq's relationship with Transfield, the contractor building the East Rockingham facility. The minutes recorded, inter alia:
'Transfield are projecting a cost of $38m; Chemeq believes it will be $36m.'
13 In a further media release and announcement to the ASX on 4 April 2003 Chemeq announced that it was upgrading and expanding its 20 tonne per annum manufacturing facility, currently under construction, for production of its veterinary drug. Included in the announcement were the statements that:
'1. The design of the manufacturing facility has been expanded and up-graded so that production will continue, uninterrupted during periods of maintenance and cleaning;
2. The warehousing and formulation areas of the manufacturing facility have been increased, so as to accommodate future productive capacities of 750 tonnes per annum;
3. Construction, already designed to FDA standards for veterinary pharmaceuticals - has now been up-graded for potential manufacture of human pharmaceuticals.'
Chemeq announced that it had executed a new construction contract for its facility with John Holland Pty Ltd with no change in operational staff at the construction site - those staff having been transferred to John Holland. The anticipated schedules for the facility were:
'. "Lock-up" in stages, beginning end April 2003;
. Occupancy, in stages, beginning end July 2003;
. Commissioning, during August to October 2003 (saleable product is anticipated during this period).'
14 On 20 May 2003 a further announcement was made by way of a status report on the construction of the manufacturing facilities. The infrastructure in the facilities had been upgraded to accommodate future productive increases of the 20 tonnes per annum process plant to 750 tonnes per annum.
15 On 25 June 2003 Chemeq announced that it had raised '… $25 million to fund upgrades and expansion of its manufacturing facilities'. The money came from a placement of new ordinary shares at $5.35 to institutions and sophisticated investors. It was to be partly used for previously announced upgrades and expansion of Chemeq's 20 tonne per annum manufacturing plant then under construction as follows:
'1. Expansion and upgrade, so that production would continue, uninterrupted during periods of maintenance and cleaning;
2. Expanded warehousing and formulation areas of the manufacturing facilities, to accommodate future productive capacities of 750 tonnes per annum;
3. Upgrade from Food and Drug Administration (FDA) standards for veterinary pharmaceuticals to manufacturer of human pharmaceuticals.'
Chemeq also said:
'The funds will also be used to expedite the construction of an additional 200 tonne per annum plant as soon as possible, following the completion of the 20 tonne per annum plant within the facilities, due for commencement of commissioning in October 2003.'
16 At some time prior to a meeting of the Board of Chemeq held on 25 August 2003, members of the Board were provided with a document entitled 'Chemeq Rockingham Production Facility Report for July 2003'. On page 2 of this document there appeared a statement that the forecast final cost of the facility was $45,561,000 of which $22,561,000 had been expended. The report stated:
'There has been an increase in forecast final cost of $2.6M even after allowing a reduction in contingency by $750k.'
17 On 11 September 2003 Chemeq made a further media release and announcement to the ASX. It reported that occupancy of infrastructure areas within the company's manufacturing facility had taken place and that validating and pre-commissioning of facilities had commenced on schedule. The announcement had continued:
'Costs of the manufacturing facility, originally budgeted at AUD$25 million for the 20 tonne per annum plant, will be increased, commensurately with the planned upgrade to US Food and Drug Administration (FDA) standards and expansion of the facility to accommodate next stage development, as previously announced on 4 April 2003 and 25 June 2003.
Additional costs are expected to be in the order of AUD$10 million and will not be fixed until after the current, competitive tender processes for supply of equipment for the manufacturing facility are completed.
Currently, Chemeq has AUD$26 million in cash.'
It is agreed that by 30 September 2003 Chemeq's management was aware that the anticipated construction cost of the East Rockingham facility was likely to be in the order of $50 million.
18 On 5 November 2003 Chemeq told the ASX that it had exercised a right to purchase the land upon which its manufacturing facility was constructed for AUD$2 million. Construction of all the infrastructure to accommodate a production rate equivalent to 750 tonnes of active ingredient per annum was complete. This infrastructure would support and formulate 20 tonnes per annum of active ingredient from manufacturing plant 1 and 200 tonnes per annum from manufacturing plant 2.
19 On 12 December 2003 Chemeq announced that it had raised $20 million from its share purchase plan. It stated:
'The funds will be used firstly, as working capital to finance production and inventory from Chemeq's first manufacturing facilities; secondly, to support the immediate planning and then first stages of construction of Chemeq's second manufacturing facility.'
It is common ground that by December 2003 Chemeq's Board of Directors and its management knew that the anticipated construction cost of the Rockingham facility was likely to exceed $50 million.
20 Chemeq's half year report for the half year ended 31 December 2003, submitted to the ASX, disclosed that the book value of its property, plant and equipment was $37.3 million and its total assets were approximately $72 million. It identified its prime activity during the half year as the ongoing construction of its manufacturing facility. Its loss to 31 December 2003 of AUD$4.169m represented a direct investment into supporting the construction activities and building the company's '… unique future as an Australian manufacturer and seller of its own patented, synthetic pharmaceutical drugs'.
21 In a quarterly cashflow report for the quarter ended 31 March 2004 published to the ASX on 30 April 2004, Chemeq stated that in the quarter ended 31 March 2004 it had made cash payments to the order of $13 million for the acquisition of physical non-current assets.
Factual background relating to non-disclosure of patent information
22 On 16 February 2000 Chemeq made an application under the Patent Cooperation Treaty (PCT) to the Patents Office of IP Australia which identified the United States as one country in respect of which it sought to obtain intellectual property protection for an invention which was a particular method of formulating the Chemeq Product.
23 Patents protecting the Chemeq Product comprise seven families. The PCT application was within one of those families and related to a specific method of improving the efficacy of the Product and its antimicrobial function by preparing it in certain alcohols through a series of steps involving particular temperatures and times. The PCT application was filed with the United States Patent and Trade Marks Office on 8 November 2001. The term of patent protection in the United States, as provided in s 154 of Title 35 of the US Code, is 20 years from the date of filing the application for the grant of a patent.
24 On 10 December 2003 Chemeq made an announcement in the media and to the ASX in relation to its patent approvals. The announcement stated, inter alia:
'Pharmaceutical company Chemeq Ltd … today announced that it has received approval of patents for its antimicrobials in USA, Europe, Australia, Eurasia and China.
This family of approved patents include claims protecting all aspects of Chemeq's technology under patent law. This gives Chemeq additional monopolies in manufacture and marketing of their antimicrobials. The claims include:
- New synthetic molecules
- Methods of synthesis of these molecules
3. Compositions derived from the formulation of these synthesised new molecules
4. Market uses of these compositions.
"Importantly, these patents confirm Chemeq's key monopolies in the manufacture and marketing of our unique polymeric antimicrobial for use in pig and poultry markets, globally" said Dr Graham Melrose, Chairman and Chief Executive Officer, Chemeq Ltd.'
After referring to the 'key US patent' Chemeq's statement quoted its Chairman Dr Melrose as follows:
'"Incorporating today's announcement, Chemeq will now have approximately 60 approved patents and 150 patents pending. The approval processes on all patents pending are progressing satisfactorily and if approved, would give additional monopolies considerably beyond 2020. These processes which generally take in the order of six years in many countries are well progressed by Chemeq. In the meantime national and international patent applications protect our position during the examination processes."'
25 On 27 August 2004 Chemeq lodged a prospectus with the ASX for non-renouncable rights offer to raise $20.3 million. At par 3.7 of the prospectus it was stated:
'Patented intellectual property and other applications
Chemeq has been granted patents in more than 80 countries including the USA, and countries within Europe and Asia. Chemeq has more than 175 patents pending which, if granted, will take potential manufacturing and marketing monopolies beyond the year 2020. Chemeq's key patents are comprehensive and cover molecules, syntheses, compositions and uses. All intellectual property is 100% owned by Chemeq.'
26 On 28 September 2004 Chemeq was told by its patent attorneys that the patent seeking protection for the process of formulation in respect of which Chemeq had filed its PCT application on 8 November 2001 was to be granted by the United States Patent and Trade Marks Office on 12 October 2004. The term of the patent was to be 20 years from 16 February 2000.
27 On 6 October 2004 Chemeq issued 8,478,155 fully paid ordinary shares under its non-renouncable rights offer which closed on 27 September 2004. The number of its fully paid ordinary shares on issue thereby increased to 101,737,865. On the same day, Chemeq made an ASX media release under the headline 'PATENT GIVES PROTECTION TO 2020 AND DISTRIBUTION BEGINS'. The release opened with the statement that Chemeq:
'. [H]as been granted an additional US patent (previously pending only), which extends the company's exclusive protection in manufacture and marketing of its veterinary products in this country, to the year 2020.'
The announcement went on:
'Granting of this patent means that no other party may manufacture or market Chemeq's CHEMEQ polymeric antimicrobials in the large US market. Already, Chemeq has been given expedited review status for the approval process of its drug (for pigs) in the US market.
Chemeq's technologies are protected by granted patents in 80 countries, plus approximately 175 patents pending. The safety and efficacy of Chemeq's technologies have been established over several years, in registered independent international laboratories and successful R & D and commercial field trials in a number of countries.'
There followed under the heading 'Distributed Sales Order' reference to a small additional sale in South Africa of product manufactured in Chemeq's APVMA approved pilot facility.
28 On 7 October the West Australian newspaper published an article including statements attributed to Chemeq that:
'"[T]he issue of the US patent was a major milestone in Chemeq's bid to sell its polymeric anti-microbial, which is described as a replacement for the use of human antibiotics as growth promoters in pork and poultry production into the lucrative US market" and "[I]t's a most important patent … In a nutshell, to have these exclusive rights in the most important market is obviously a very big achievement and an important milestone."' (sic)
29 At the time of the announcement and the report in the newspaper the relevant US patent was known to Chemeq's management not to be material to Chemeq's commercial position in relation to the whole of its intellectual property portfolio. This was because: