One penalty: section 76(3)
21 Section 76(3) provides:
'If conduct constitutes a contravention of two or more provisions of Part IV, a proceeding may be instituted under this Act against a person in relation to the contravention of any one or more of the provisions but a person is not liable to more than one pecuniary penalty under this section in respect of the same conduct.'
The CEPU contends, and the ACCC disputes, that this provision applies.
22 The CEPU submitted that the conduct that made it an accessory to Edison's contravention of s 45E was the same conduct as that which made it an accessory to Edison's contravention of s 45EA. Consequently, the CEPU submitted that it is only exposed to a single penalty which is not to exceed $750,000.
23 The CEPU also advanced a number of alternative submissions. First, it submitted that its conduct should be viewed as a single course of conduct, attracting one penalty only, even if it were possible to draw some distinction between the conduct that was relevant to s 45E and that which was relevant to s 45EA. In support of this submission, the CEPU relied upon Advance Bank at 41,164 per Gummow J; ABB Transmission at 179-180 [38] and Australian Competition and Consumer Commission v Rural Press Ltd (2001) ATPR 41-833 ('Rural Press') at 43,290 [16]-[17]. Further or alternatively, the CEPU submitted that if this approach could not be adopted, its conduct in relation to the two contraventions was so interconnected that, by the application of the totality principle, the Court ought to arrive at a penalty of the same magnitude as if it were dealing with a single contravention: see Rural Press at 43,290 [19] and TNT at 40,169.
24 In all the circumstances, the CEPU submitted that the Court should impose a single penalty of $20,000 in relation to its involvement in Edison's contraventions of ss 45E and 45EA.
25 The ACCC submitted that one penalty should be imposed in respect of both contraventions, but that the quantum of that penalty should be determined on the footing that there were two contraventions attracting two penalties. Thus, the ACCC submitted that the Court should impose a penalty in the range of $210,000 to $250,000, representing approximately one-sixth of the maximum possible penalty of $1.5 million.
26 The first question, therefore, is whether the CEPU's conduct attracts a single penalty that is limited to a maximum of $750,000.
27 The courts have adopted a practical and commonsense approach where a single transaction or course of conduct results in multiple contraventions. Even where s 76(3) does not strictly apply, but the contravener's conduct amounts to one episode or one course of conduct, the courts will apply the totality principle, sometimes producing outcomes that are not very different from those that would have resulted from the application of s 76(3).
28 In Trade Practices Commission v Allied Mills Industries Pty Ltd (No 4) (1981) 37 ALR 256 ('Allied Mills') at 258, Sheppard J was required to assess penalties in relation to price fixing contraventions of s 45 of the TPA. His Honour said that where more than one breach of s 45 is alleged and admitted, it would not be appropriate to impose substantive penalties for each breach because each arises out of the one transaction, namely, the arrangement or understanding alleged in the amended statement of claim. In taking this course, Sheppard J followed the approach adopted by Kitto J in imposing penalties for breaches of the Customs Act 1901 (Cth) in L Vogel & Son Pty Ltd v Anderson (Minister for Customs) (1968) 120 CLR 157 at 164-165. Sheppard J's approach was followed in TNT at 40,169. These cases involved applications of the totality principle rather than s 76(3).
29 The same observation can be made concerning Advance Bank, upon which the CEPU relied. In that case, Gummow J was required to assess penalties in relation to five misleading advertisements published over a two week period. His Honour referred with approval to the following remarks by Lockhart J in Trade Practices Commission v Bata Shoe Company of Australia Pty Ltd (No 2) (1980) 44 FLR 149 at 176:
'Guidance is given in the field of sentencing for criminal offences by the well-known principle that where several offences are heard together and arise out of the same transaction it is a sound working rule that the sentences imposed for those offences should be made concurrent; it is inappropriate to sentence consecutively when the offences were all really involved in the same episode…
I accept that the contraventions arose out of the one course or pattern of conduct. Although it is necessary to look at each contravention separately, nevertheless consideration must be given to the facts common to each contravention.'
30 The decision of Mansfield J in Rural Press illustrates the proposition that s 76(3) and the totality principle can produce similar results. His Honour said at 43,290 [19]:
'The ACCC is correct in stressing that, as I have found, the conduct of the respondents involved two contraventions of s 45 of the Act, namely the making of an arrangement and separately carrying it into effect. In a practical sense, I consider that the conduct that constituted the first of those contraventions was "part and parcel" of the conduct that constituted the second of those contraventions: see for example J McPhee & Son (Australia) Pty Ltd v Australian Competition and Consumer Commission (2000) ATPR ¶41-758; (2000) 172 ALR 532 ("McPhee"), per Black CJ, Lee and Goldberg JJ at ATPR 40,923; FCR 583 [182]. However, although the conduct constituting the contraventions of s 46 was also closely allied to that conduct, in my view the contraventions of s 46 are separate and could be dealt with separately. For the reasons proposed by the ACCC, and accepted by the respondents, I will however impose one penalty upon each respondent for the contraventions of the Act by that particular respondent, or in which that particular respondent was involved. In this matter, the level of pecuniary penalty which I impose would not alter whether the s 45 and s 46 contraventions had to be treated as part and parcel of the one set of conduct by reason of s 76(3) or were capable of being treated as separate contraventions.'
31 In McPhee at 583 [181]-[183], the Full Court considered the imposition of penalties for making and giving effect to an arrangement or understanding in contravention of s 45. The Court concluded that s 76(3) applied because the conduct which constituted the second contravention of giving effect to the arrangement was part and parcel of the conduct which constituted the first contravention of making the arrangement:
'The case presented to his Honour did not distinguish the conduct of McPhee involving the formation of the proscribed arrangement or understanding from the conduct of McPhee said to constitute giving effect to such arrangement or understanding. According to the Commission's case, the delivery by Mr Webb to Mr Jolly of McPhee's rates was an integral part of the conduct that constituted the contravention of s 45 in making, or arriving at, an understanding or arrangement. That same act was also relied upon by the Commission as the act which constituted the further contravention by McPhee of giving effect to the arrangement or understanding.
If the disclosure by McPhee to DFE of the rates charged by McPhee to ACI Florapak could be said to be an act giving effect to an arrangement or understanding already made or arrived at, it was not conduct distinguishable from the conduct of McPhee which constituted the making of such an arrangement or understanding. Pursuant to s 76(3) of the Act, if conduct constitutes a contravention of two or more provisions of Pt IV, a proceeding may be instituted in respect of each contravention but a person is not liable to more than one pecuniary penalty in respect of the same conduct. This was not a case involving repeated conduct concerning discrete events occurring at different times and involving disparate parties: Trade Practices Commission v Simpson Pope Ltd (1980) 30 ALR 544; 47 FLR 334 at 336 per Franki J.
We therefore accept the submission that his Honour erred in imposing separate penalties in respect of the ACI Florapak conduct. The conduct which constituted the second contravention was part and parcel of the conduct which constituted the first contravention and s 76(3) prescribed that only one penalty could be imposed.'
32 The Full Court added at 584 [185] that, if s 76(3) did not apply, the totality principle should have been applied because of the interlocking nature of the conduct involved in the two contraventions:
'If it could be said that the conduct relevant to the two contraventions was not the same conduct for the purpose of s 76(3), we would be of the opinion that his Honour's discretion in calculating the appropriate penalty to be imposed miscarried, in that his Honour failed to have regard to the interlocking nature of the conduct involved in the two contraventions and to the need to set a total penalty appropriate in the circumstances. On the particular facts of this case, it was not appropriate to impose a substantive penalty for each breach of the Act arising as they did out of the one transaction. The appropriate course was to set a penalty for the conduct imposed in respect of one breach and to take the other breach into account: Trade Practices Commission v Allied Mills Industries Pty Ltd (1981) 37 ALR 256; 60 FLR 1 per Sheppard J at FLR 40; Trade Practices Commission v TNT Australia Pty Ltd, above, at 40,169; McDonald v R (1994) 48 FCR 555; 120 ALR 629. For the reasons we have set out above, we consider that the appropriate total of penalty would have been a sum of $500,000.'
The penalty of $500,000 was the same figure that the Full Court considered to be the appropriate penalty on the footing that s 76(3) did apply.
33 I dealt with the CEPU's accessorial liability at [219]-[222] of my principal judgment. In relation to s 45E, I said that the evidence established that the CEPU made demands which instigated, induced and procured Edison to make both the broader arrangement and the heads of agreement, and that the same evidence established that the CEPU aided and abetted, and was knowingly concerned in, the making of a contract, arrangement or understanding between Edison and the CEPU. In relation to s 45EA, I concluded as follows at [222]:
'I have found that Edison gave effect to the contract, arrangement or understanding by excluding DJN from performing work as an electrical contractor at Loy Yang B. In pursuance of the arrangement, the CEPU signed the Simon Engineering site agreement. Further, in its discussions with Edison in August 2001, the CEPU incited, induced, counselled and procured Edison's exclusion of electrical contractors who did not have a certified agreement with the CEPU from performing work at Loy Yang B. I am satisfied that the CEPU thereby counselled, procured and induced Edison's contravention of s 45EA.'
34 The ACCC submitted that the CEPU's conduct in relation to s 45EA was not identical to its conduct in relation to s 45E. In oral submissions, senior counsel for the ACCC accepted that there was a very substantial overlap in the conduct by which the CEPU aided, abetted, counselled, procured and induced the making of an arrangement in contravention of s 45E(3), and the conduct by which it incited, induced and procured Edison to give effect to the offending provision of that arrangement. Indeed, senior counsel for the ACCC accepted that there was a continuum of conduct on the CEPU's part that was closely related and which, in practical terms, could be regarded as a single course of conduct. Nevertheless, the ACCC submitted that there was a critical difference between the conduct relevant to the s 45E contravention and that relevant to the s 45EA contravention in that, after the making of the arrangement, the CEPU took steps to perform its part of the bargain and thereby induced and procured Edison to give effect to the offending provision. Those steps comprised the CEPU's execution of the Simon Engineering MOU on 15 August 2001 and its execution of the Simon Engineering site agreement on 23 August 2001. According to the ACCC, those events post-dated the making of the arrangement and were relevant only to Edison's contravention of s 45EA.
35 One difficulty with this submission is that Edison gave effect to the provision of the arrangement on 13 August 2001 when its employee, Buckley, advised Nabulsi of DJN that DJN's services would no longer be utilised by Edison because Edison had been asked by the CEPU not to engage the services of electrical contractors that did not have an EBA with the CEPU: at [66] of my principal judgment. Further, Pearson and Buckley informed the team leaders of Edison's maintenance staff on 16 August 2001 that Edison had entered into, or was entering into, an arrangement with the CEPU whereby it would only be using electrical contractors who had a certified agreement with the CEPU: at [69] of my principal judgment. Thus, Edison changed its practices in relation to the engagement of electrical contractors from 13 or 16 August 2001. Edison did not revert to its pre-August 2001 practices until late in 2003 after receiving correspondence from the ACCC: see my principal judgment at [94].
36 There was no evidence that Edison had any knowledge of the CEPU's execution of the Simon Engineering MOU on 15 August. Nor was there any evidence that Edison gave effect to the offending provision of its arrangement with the CEPU because it knew that the CEPU had taken steps to implement its part of the bargain. Rather, the evidence indicates that Edison gave effect to the provision of its arrangement with the CEPU that it would not engage the services of electrical contractors that did not have an EBA with the CEPU because that was what the CEPU had demanded on 9 August 2001 and that was what was required by Edison's arrangement with the CEPU.
37 Another difficulty with the ACCC's submission is that, as in McPhee, the ACCC conducted the trial without attempting to draw any distinction between the conduct on the part of the CEPU that was relevant to its involvement in Edison's contravention of s 45E(3) and that which was relevant to Edison's contravention of s 45EA. Quite the contrary; the ACCC relied on the same conduct for its contention that the CEPU was involved in both contraventions. This is confirmed by paras 41 and 42 of the ACCC's amended statement of claim. At trial, senior counsel for the ACCC expressly submitted that the ACCC relied on the same conduct by the CEPU over a relatively short period of time between 9 August and 23 August 2001 in connection with both contraventions.
38 The ACCC's submission fails to take into account the full ambit of my findings concerning the contract, arrangement or understanding between Edison and the CEPU. In my principal judgment, I found that prior to 23 August 2001 Edison and the CEPU made or entered into an arrangement that included a provision that Edison would not engage electrical contractors to perform work at Loy Yang B unless they have a certified agreement with the CEPU prior to commencing work at the site: at [142]. However, I also found that the heads of agreement was entered into on 23 August 2001 in accordance with, and was controlled by, this broader arrangement: at [142] and [173]. Even if the heads of agreement were the only relevant arrangement between Edison and the CEPU, I concluded that cl 4.1 of the heads of agreement constituted a provision that was included in the heads of agreement for a purpose which infringed s 45E(3): at [192]. When I turned to consider the CEPU's liability as an accessory to Edison's contraventions of ss 45E and 45EA, I pointed out that the evidence established that the CEPU made demands which instigated, induced and procured Edison to make both the broader arrangement and the heads of agreement: at [220]. In these circumstances, the implementation steps which the CEPU took on 15 and 23 August 2001 can be regarded as actions by which the CEPU induced, counselled or procured Edison to sign the heads of agreement, which relevantly formed part of the contravening arrangement. Put another way, there is no reason to conclude that the implementation steps which the CEPU took on 15 and 23 August 2001 are relevant only to the contravention of s 45EA and not to the contravention of s 45E(3). In my opinion, they are relevant to both, given the findings I have made concerning the heads of agreement and the relationship between the heads of agreement and the broader arrangement that Edison and the CEPU made some days earlier.
39 For the sake of completeness, I note that the ACCC advanced a different argument in its written submissions on penalty, but it did not pursue that argument in its oral submissions. Shortly stated, the argument was that the CEPU's conduct in relation to s 45EA included its failure to prevent the continuation of Edison's new practice between August 2001 and November 2003. The ACCC did not advance this argument at the principal hearing and, assuming it was not abandoned during the penalty hearing, it is now too late to raise it. At all relevant times, the ACCC's case was that the CEPU was involved in Edison's contravention of s 45EA because the CEPU had counselled, procured or induced Edison to give effect to the offending provision by means of the demands which the CEPU made to Edison in the period leading up to Edison's execution of the heads of agreement on 23 August 2001. At the principal hearing, senior counsel for the ACCC submitted that the ACCC could not point to anything that the CEPU did after the making of the arrangement on or about 23 August that made it an accessory to Edison's contravention of s 45EA. The ACCC did not mount a case that the CEPU policed or sought to enforce the arrangement after it was entered into in August 2001. The ACCC did not ask any questions of Burns or Sutherland or any other witness to the effect that the CEPU had taken any steps to enforce the arrangement after it was entered into in August 2001.
40 This is not a case where different actions were taken by the CEPU at different times and in relation to dealings with different persons or entities. In such a case, the most that could be said was that the conduct on each occasion was of a similar character: see Trade Practices Commission v Simpson Pope Ltd (1980) 30 ALR 544 at 548 per Franki J. On the findings I have made, the CEPU's conduct was part and parcel of one transaction or episode that took place over the period between 9 August and 23 August 2001.
41 In my opinion, the conduct on the part of the CEPU that made it an accessory to Edison's contravention of s 45E(3) is the same conduct that made it an accessory to Edison's contravention of s 45EA. Accordingly, s 76(3) applies. The consequence is that the CEPU is not liable to more than one pecuniary penalty under s 76(1) in respect of its conduct, and the maximum amount of that penalty is $750,000.
42 If the CEPU's conduct that is relevant to Edison's contravention of s 45EA can be distinguished from its conduct in relation to the s 45E(3) contravention, with the consequence that s 76(3) does not apply, I consider that the approach described in Allied Mills, Advance Bank and in McPhee at 584 [185] should be applied in the circumstances of this case. In substance, the CEPU engaged in a single course of conduct that was related and interlocking and which involved it in both contraventions. To my mind, it would be artificial to distinguish between the conduct that is relevant to the making of the arrangement and that which is relevant to Edison's giving effect to the arrangement. The CEPU's conduct in relation to the two contraventions is so interconnected that the appropriate course is to apply the totality principle to set a penalty for the CEPU's accessorial conduct in respect of one breach and to take the CEPU's involvement in the other breach into account. Adopting that approach, I have concluded that the appropriate penalty would not differ from that which I would impose on the basis that s 76(3) applies.