Background
8Ausgrid is an electricity retailer. Redbank is an electricity generator. Redbank generates electricity at a plant near Warkworth in the Hunter Valley.
9Receivers were appointed to Redbank on 5 October 2013.
10Ausgrid and Redbank are the current parties to a "Power Purchase and Hedge Agreement" ("the Agreement") originally made on 28 March 1996.
11The Agreement is an electricity hedging agreement. Under the National Electricity Market, electricity is sold by generators into a pool and purchased by retailers from the pool. The price at which electricity is sold into and purchased from the pool is determined by the Australian Energy Market Operator as a spot price for electricity, based on assessments of supply and demand every five minutes which is averaged on a half hourly basis to produce a half hour spot price. Retailers then pay the spot price and generators are paid the spot price.
12To guard against fluctuations in the spot price, retailers commonly enter into hedge agreements with generators to set a fixed price for electricity. The Agreement is one such agreement.
13The hedging arrangements under the Agreement are set out in cl 2. In summary, so far as is relevant to the present proceeding:
(a)one party is obliged to make "difference payments" to the other calculated by reference to a "Contract Amount" of electricity which Redbank must generate each year. If the spot price is higher than the hedge price, Redbank must pay the difference to Ausgrid. If the spot price is lower than the hedge price, Ausgrid must pay the difference to Redbank (cl 2.4);
(b)Redbank must meet an annual target relating to the quantity of electricity generated (cl 2.8.2);
(c)at the end of each Contract Year (which is the same as the calendar year), a calculation must be performed to determine whether Redbank has met its annual generation target (cl 2.8.2(b)); and
(d)if Redbank fails to meet its annual generation target, Ausgrid is entitled to reduce the Contract Amount for the following year (cl 2.8.2(b)(ii)).
14The Agreement is "out of the money" at the moment in that the currently prevailing spot price is well below the hedge price. Accordingly, at all material times, the party obliged to make "difference payments" is Ausgrid.
15The material referred to in the preceding four paragraphs is taken from the submissions of Mr Williams, who appeared for Ausgrid, and is common ground.
16An integer in the calculation of the "Contract Amount", and thus the amount payable by Ausgrid to Redbank, is the "Test Hour Settlement Period". That period, relevantly, excludes any periods during which there is a "Force Majeure" event.
17Force Majeure is defined in the Agreement as follows:
"Force Majeure means an event or circumstance or combination of events or circumstances beyond the reasonable control of the Party claiming Force Majeure including, but not limited to, acts of God, strikes (including lockouts, industrial and/or labour disputes and/or difficulties with bans, blockages or picketing) which are not directed solely toward the Facility, sudden action of the elements and actions of a Government Body that conflict with the terms of this Agreement, including but not limited to the inability of a Party to obtain a necessary permit or authorisation from a Government Body. Mechanical, electrical or equipment breakdown or failure that causes full or partial curtailment of Energy Output of the Facility shall not be declared a Force Majeure event unless caused by or arising out of an event that is itself a Force Majeure event. Failure to obtain the necessary water, fuel supplies or other consumables necessary for the operation of the Facility due to the wilful or negligent action or inaction of Generator shall not be deemed to be a Force Majeure."
18Clause 8 of the Agreement deals with the consequences of Force Majeure:
"If a Party because of Force Majeure is rendered wholly or partly unable to perform its obligations under this Agreement, that Party shall be excused from whatever performance is affected by the Force Majeure to the extent so affected provided that:
...
(iii) The non-performing Party uses reasonable efforts (best endeavours in the case of mechanical, electrical or equipment breakdown or failure) to remedy its inability to perform...".
19So far as is relevant, the definition thus has the effect that a Force Majeure event is one:
(a)which is beyond Redbank's reasonable control;
(b)but not a "mechanical, electrical or equipment breakdown or failure that causes full or partial curtailment of Energy Output" ("the Exclusion");
(c)unless such a breakdown was itself caused by an event beyond Redbank's reasonable control ("the Exception to the Exclusion").
20On 29 January 2013, a sustained energy "outage" occurred at Redbank's Warkworth plant ("the Outage"). The Outage continued until 23 March 2012.
21In correspondence, Redbank:
(a)has asserted that the Outage was a Force Majeure event;
(b)accepted that the Outage was caused by events which satisfied the Exclusion (that is, that it was caused by a "mechanical, electrical or equipment breakdown");
(c)but asserted, without elaboration, that such breakdown was caused by events beyond its control, and thus within the Exception to the Exclusion.
22Ausgrid has disputed Redbank's contention that the Outage amounted to a Force Majeure event. Ausgrid has, unsuccessfully, sought from Redbank particulars, and documents relating to its contention that the Force Majeure was caused by events beyond its control.
23The structure of the Agreement is such that, despite this dispute, Ausgrid has been obliged, for the calendar year 2013, to make payments to Redbank as if the Outage was a Force Majeure event.
24Clause 15 of the Agreement makes provision, to which I shall return, for the resolution of disputes by arbitration. I was, however, informed that the Agreement makes no provision, in terms, for the repayment of amounts overpaid pending resolution of such disputes.
25Ausgrid's position is that, in the events that have happened, despite the provisions of cl 15, it is now free to commence proceedings in this Court to seek declaratory relief as to whether there has been a Force Majeure event and, if successful in that regard, to seek restitution of the amounts it contends it has overpaid.
26What Ausgrid contends that it has been "unable to assess" is "the validity of Redbank's assertion that the Outage was caused by an incident beyond the reasonable control of Redbank" (to adopt the wording of a Notice of Dispute Ausgrid sent to Redbank on 6 March 2013).
27Redbank resists Ausgrid's claim on three bases.