[This headnote is not to be read as part of the judgment]
DSF Constructions Pty Ltd (DSF Constructions) was engaged by Ceerose Pty Ltd (Ceerose), the principal contractor of a building refurbishment project, to manufacture and install steel works, including a steel skylight structure. On 13 April 2013, a worker contracted to Ceerose by a labour hire company was fatally injured when the skylight structure fell on him. Before work had commenced that day, DSF Constructions had discussed the necessary exclusion zones required during the lifting operations of the skylight with Ceerose and Coopers Cranes, which had been engaged by Ceerose to undertake all lifting operations. Ceerose directed the workers not to work in the vicinity of the cranes while the lifting operations were in progress. Later that day, following the installation of the skylight structure and after DSF Constructions had been advised that Coopers Cranes were finished for the day, Coopers Cranes recommenced lifting operations. Workers were allowed to return and work in the exclusion zone under the lifting operations. The skylight structure, which had not been secured, fell when it was struck by a crane.
DSF Constructions was charged with and pleaded guilty to an offence under the Work Health and Safety Act 2011 (NSW) for failing to comply with its health and safety duty, thereby exposing workers to a risk of death or serious injury. The primary judge imposed a fine of $225,000, after allowing a discount of 25 per cent for DSF Constructions' early guilty plea. His Honour found that the offence fell in the mid-range of objective seriousness.
The issues on appeal were:
- Whether the primary judge failed to have regard to the maximum penalty of $1,500,000 and to the fact that this was a significant increase from the maximum penalty prescribed under the previous legislative scheme (Ground 1);
- Whether the primary judge erred in his assessment of the objective seriousness of the offence (Ground 2);
- Whether the penalty imposed was manifestly inadequate (Ground 3); and
- Whether, in any event, the Court should exercise its residual discretion not to intervene (Ground 4).
The Court held, dismissing the appeal:
In relation to Ground 1
Per Beazley P (Fullerton and McCallum JJ agreeing)
(i) Although the primary judge did not refer to the maximum penalty or to the fact that the penalty had been substantially increased, it could not be said that his Honour failed to have regard to these considerations: [61]-[66].
In relation to Ground 2
Per Beazley P and McCallum J
(ii) The primary judge's finding that the offending conduct was in the mid-range of objective seriousness did not disclose an appealable error: [75]-[83]; [127]-[132].
Mulato v R [2006] NSWCCA 282; Muldrock v The Queen (2011) 244 CLR 120; [2011] HCA 89; Nash v Silver City Drilling (NSW) Pty Ltd [2017] NSWCCA 96 considered.
R v KB [2011] NSWCCA 190; Bulga Underground Operations Pty Ltd v Nash (2016) 93 NSWLR 338; [2016] NSWCCA 37; Unity Pty Ltd v SafeWork NSW [2018] NSWCCA 266 referred to.
Per Fullerton J (dissenting)
(iii) The objective seriousness of the offending conduct was significantly greater than that found by the primary judge, having regard to the state of knowledge of DSF Constructions' director of the further lifting operations: [116]-[119].
In relation to Ground 3
Per Beazley P (McCallum J agreeing)
(iv) The penalty imposed was not manifestly inadequate, having regard to, inter alia, the size and scope of DSF Constructions' operation and the fact that DSF Constructions showed genuine remorse, assisted the authorities in the investigation and immediately implemented appropriate work safety procedures: [87]-[93].
Capral Aluminium Ltd v WorkCover Authority of New South Wales (2000) 49 NSWLR 610; [2000] NSWIRComm 71; Barbaro v The Queen (2014) 253 CLR 58; [2014] HCA 2; Nash v Silver City Drilling (NSW) Pty Ltd [2017] NSWCCA 96; Unity Pty Ltd v SafeWork NSW [2018] NSWCCA 266 considered.
Per Fullerton J (dissenting)
(v) Having regard to the totality of the circumstances, the fine imposed on DSF Constructions was unreasonable and plainly unjust: [120]-[121].
In relation to Ground 4
Per Beazley P (McCallum J agreeing)
(vi) If contrary to the opinion of the majority the sentencing judge erred, the Court would have exercised its residual discretion not to intervene, having regard to the Attorney General's unwarranted and largely unexplained delay in prosecuting the appeal: [94]-[111].
R v Hallocoglu (1990) 29 NSWLR 67; R v Pham (1991) 55 A Crim R 128 considered.
Per Fullerton J (dissenting)
(vii) The Court should refuse to exercise its residual discretion, having regard to the significance of the error in the primary judge's assessment of objective seriousness and the magnitude of the inadequacy of the penalty: [122]-[123].