63 As to the second item (b), "Tax Invoice of 15/09/2009 $79,997.75", this assessment was founded upon the Claimant's tax invoice dated 15 September 2009. The tax invoice dated 15 September 2009 claimed the sum of $114,282.50 plus GST in the sum of $11,428.25, a total of $125,710.75. The schedule attached to the invoice, which was entitled "PROGRESS STATEMENT", identified the work performed and the amount claimed in relation to each item of that work, which totalled $114,282.50. However, the Adjudicator noted that the Trade Summary, which provided an assessment only up to 26 August 2009 did not include all of the work claimed to have been undertaken by Aircon up to the date of the invoice, namely 15 September 2009. Accordingly, the Adjudicator set about the task of valuing the work carried out during this period. The Adjudicator found that the work claimed in the invoice was in fact completed as submitted by the Claimant. He then proceeded to calculate the value of the work undertaken between 26 August 2009 to 15 September 2009. He did this by calculating the amount on a pro rata basis using the available work days in the period 14 August 2009 to 15 September 2009, and excluding those days covered by the Trade Summary. Taking the total amount claimed in the invoice dated 15 September 2009, $125,710.75, and finding that there were 22 work days, of which 8 were covered by the Trade Summary (leaving 14 days unaccounted for in the Trade Summary), the Adjudicator calculated that the Claimant was entitled to be paid $79,997.75 ($125,710.75 ÷ 22 X 14). In undertaking this reasoning, the Adjudicator accepted the Claimant's progress statement which summarised the work claimed to have been done by it which comprised the 15 September 2009 invoice, and accepted the value of that work as assessed by the Claimant as stated in its progress statement, where the 8 items of claimed work claimed to have been undertaken were valued by Aircon at $114,282.50.