4 There was no issue before me that, notwithstanding the statutory requirement to conduct its proceedings in an informal manner, the Tribunal is under a legal obligation to act fairly, to comply with the rules of natural justice and to give each party a reasonable opportunity to call evidence relevant to the issues before it and to examine, cross-examine or re-examine witnesses and to make submissions.[1] Furthermore, when, as here, the parties were not represented, there is a special burden upon the Tribunal to ensure that these obligations are complied with.[2] It was accepted, too, that an appeal will succeed on such a ground only where it is demonstrated that a denial of procedural fairness by the Tribunal could have caused a real injustice to the appellant by affecting the outcome of the proceeding.[3]
The Factual Background
5 The directions given by the Tribunal on 12 February 2004 included orders that by certain specified dates Mr Stevens and the builder file and serve points of claim or points of defence together with a copy of every document that he or it intended to use to establish his claim or its defence and file and serve any expert reports and outlines of evidence for each of the witnesses to be called at the hearing. On 14 April 2004 further directions were given by the Tribunal which, in part, amended the times for the exchange of expert reports and witness outlines.
6 The proprietors filed their points of claim on 9 March 2004 in which they claimed the sum of $31,690.40 as the cost of the rectification work. A schedule to the points of claim contained particulars of the defective work by way of an unpriced list comprising 28 items ("the Particulars List"). In its points of defence, filed on 25 May 2004, the builder denied all allegations and then set out its response to each of the 28 items in the Particulars List.
7 Mr Stevens filed and served outlines of evidence for both his wife and himself, but no expert reports. The builder filed and served outlines of evidence for its director, Dominic Ambrogio, and its construction supervisor, Peter Mills, and expert reports by Charles Lee and Thomas Brown. Mr Lee, a registered builder, a building consultant since 1991 and a claims inspector and inspections administrator with the Housing Guarantee Fund Ltd for 16 years, had prepared a report in which he had considered and dealt with each of the 28 items in the Particulars List. Mr Lee concluded that only eight of the 28 items required further work to be carried out by the builder at a cost which he estimated to total $613.75. Mr Brown's report related to the finish of the plaster work which he said was satisfactory.
8 At the hearing before the Tribunal neither party was legally represented. Mr Stevens, who is a panel beater by trade and in July 2004 was employed as a truck driver, represented himself and his wife. The builder was represented by Mr Ambrogio. It appears from the transcript of the hearing before the Tribunal that Mr Stevens failed to understand the need to call expert evidence to prove the cost of rectification. When this was explained to Mr Stevens he produced a quotation prepared by a builder, Gary Barber, showing an itemised cost of rectification work. At the suggestion of the Tribunal Mr Stevens called Mr Barber on the second day of the hearing to give evidence by telephone.
9 As it happened, the quotation handed to the Tribunal on the first day of hearing was not the correct document. Mr Stevens rectified this error at the start of the second day of the hearing by replacing it with another quotation dated 16 February 2004 which contained a list of 22 items of rectification work at a cost totalling $31,690.40 ("the Barber Rectification List"). Not only did the 22 items in the Barber Rectification List not accord with the 28 items in the Particulars List, it also contained an extra six items from the quotation "tendered" the previous day. Whilst the extra six items were relatively minor, totalling only $739.23, this change of position during the course of the hearing only aggravated what was already a quite unfair situation for the builder. Mr Ambrogio's complaint after lunch on the first day when he was cross-examining Mr Stevens that he had not had "time to analyse" the first Barber quotation, had been simply brushed aside by the Tribunal: