55045/01 ABIGROUP CONTRACTORS PTY LIMITED v
SYDNEY CATCHMENT AUTHORITY
JUDGMENT
1 HIS HONOUR: The plaintiff (Abigroup) contracted with the Sydney Water Corporation (Sydney Water) to construct an auxiliary spillway for the Warragamba Dam. The contract was a lump sum contract under which Abigroup bore the risk that more work than allowed for in its tender might be required, including by reason of latent conditions. In one critical respect - excavating to solid rock in a particular area and refilling with cement stabilised fill - the quantities were substantially greater than expected. Abigroup said that it had been induced to enter into the contract by misleading or deceptive conduct on the part of Sydney Water. It sued to recover what it said was its loss. The proceedings were referred to a referee for enquiry and report. The referee found, in substance, that there had been no misleading or deceptive conduct; that Abigroup had not shown that it relied on what it said was the misleading or deceptive conduct; that Abigroup had not shown that it had sustained loss; and that, in any event, Abigroup was estopped from pursuing this claim. Following the various hearings to which I refer in the next section of these reasons, the referee's findings have been overturned and Abigroup has been held to be entitled to damages to be assessed. These reasons deal with the assessment of those damages.
Procedural history
2 The defendant (the Authority) is the statutory successor to Sydney Water. It sought an order that the relevant findings in the report be adopted. Abigroup sought orders that those findings be rejected, and that alternative findings, in its favour, be made in their place. Nicholas J heard the competing notices of motion in February 2003. He gave judgment on 23 July 2003, ordering that the report be adopted: [2003] NSWSC 634.
3 Abigroup appealed. The Court of Appeal (speaking through Beazley JA, with Ipp and Tobias JJA agreeing) allowed the appeal, and set aside the orders made by Nicholas J. They remitted the notices of motion for rehearing: [2004] NSWCA 270; see also [2004] NSWCA 459, where their Honours varied the orders initially made.
4 I heard the remitted notices of motion from 23 to 26 May 2005, and gave judgment on 11 July 2005 ([2005] NSWSC 662). I concluded in substance that Sydney Water had engaged in misleading or deceptive conduct in circumstances to which it will be necessary to return; that Abigroup had relied on that misleading or deceptive conduct in submitting its tender and entering into the contract; and that Abigroup was not estopped from pursuing a claim in respect of that misleading or deceptive conduct. Each of those conclusions were inconsistent with findings by the referee, which findings I rejected accordingly. I concluded further that Abigroup had not proved that it suffered any loss, and on that basis ordered that the report otherwise be adopted.
5 Abigroup appealed again, and the Authority cross-appealed. The Court of Appeal (constituted and speaking as before) allowed the appeal and dismissed the cross-appeal: [2006] NSWCA 282 (the third Court of Appeal decision). Their Honours concluded that there should be a judgment in favour of Abigroup "on the basis of a discrete loss in respect of portion of the contract, being the costs incurred in carrying out the additional rock excavation" (para [150]), entered verdict and judgment for Abigroup for damages to be assessed (order 4) and, in the events that have happened, remitted to this Court for determination the amount of those damages and certain other, presently irrelevant, matters (order 5).
Factual background
6 The contract required Abigroup to design and construct, in accordance with a "Concept Design", an additional spillway at Warragamba Dam. As part of that work (and as indicated in the Concept Design), Abigroup was required to excavate to rock in a part of the site known as "Folly Creek" or "the embankment", and refill to a specified level with cement stabilised fill. Levels inferred from the Concept Design Drawings suggested that about 24,300 cubic metres were required to be excavated and replaced in this area. In fact, because the rock level was very much lower than that inferred from the Concept Design Drawings, some 204,518 cubic metres were required to be excavated and filled: an excess, over what was allowed, of some 180,218 cubic metres.
7 I interpose to note that, in the third Court of Appeal decision, Beazley JA stated different quantities at para [19]. The parties are agreed that the correct quantities are as I have just stated them, and as they were stated in para [5] of my first judgment.
8 The material provided to Abigroup and other potential tenderers included the results of geological and technical investigations carried out for Sydney Water by the Department of Public Works and Services (Public Works). The inferred underlying level of rock in the Folly Creek area was deduced from the results of a test borehole known as Borehole 609. That borehole did not give a true indication of the depth of fill, presumably because the drill struck a rock "floater".
9 The relevant part of Folly Creek had been filled during the original construction of the Warragamba Dam. Water was taken through an intake on the upstream side of the embankment and carried through a drainage pipe beneath the embankment to an outlet some considerable distance downstream of the embankment. All of that was disclosed in the material provided to tenderers. However, in two places where that work was referred to, the Concept Design Report stated that "no plans are available of the embankment or of the [or any] outlet pipe."
10 In fact, Sydney Water had in its possession a plan known in these proceedings as "the 1951 cross section". That plan purported to show the original surface of and the extent of excavation and fill on the left bank of Folly Creek, and the location of the outlet pipe. Abigroup's case, accepted by the referee and me and not challenged in the Court of Appeal, was that a competent engineer could deduce that the "Original Surface" shown on the 1951 cross-section (over which, according to that document, fill had been placed and battered) was substantially lower than the rock level inferred from Borehole 609.
11 Even assuming the accuracy of the 1951 cross-section, the level of rock would have been somewhat lower than the "original surface" depicted, because that original surface would have been comprised of soil and other loose material. However, experience demonstrated that the actual rock level was very much lower than that which might have been inferred from the 1951 cross-section.
12 Because the contract between Abigroup and Sydney Water required Abigroup to assume all risks, Sydney Water took the stance that Abigroup was not entitled to be paid for the approximately 180,000 cubic metres of additional excavation and fill, over and above what had been assumed for the purposes of the tender based on the Concept Design Drawings. (It was not suggested that Abigroup's assumption of 24,300 cubic metres based on those drawings was in any way underestimated.)
13 Abigroup's case at all times has been that it would not have tendered, or entered into the contract, on the terms that it did had it been aware at material times of the existence of and information contained in (and that could be inferred from) the 1951 cross-section. Its case is that it is entitled to be paid the whole of the additional cost incurred by it, over and above that allowed in its tender, by reason of the additional excavation and fill.
The three scenarios
14 Each party retained experts, who prepared reports, conferred and gave evidence before the referee. Relevantly, Abigroup called Mr Blunden and the Authority called Mr Meredith. Before the referee, those gentlemen produced a schedule which became, and has been known as, exhibit "AK". Mr Blunden calculated this aspect of Abigroup's loss by assessing "the actual costs incurred by Abigroup in performing [the] additional work". He derived a rate per square metre by quantifying the total costs incurred by Abigroup for excavation and fill, and dividing those costs by the number of additional cubic metres of excavation and fill. Mr Meredith assessed the claim "on the basis of extrapolating from Abigroup's tender a cubic metre rate for the works claimed." Significantly, Mr Meredith said "that if the approach to be adopted by the referee is that which [Mr] Blunden uses, then he [Mr Meredith] accepts the rate calculated by [Mr] Blunden."
15 By the time the matter came to me on the first occasion, Messrs Blunden and Meredith had refined their agreement. They produced a revised version of exhibit AK. In (as they called it and I shall call it) revised exhibit AK, they postulated three "scenarios". Scenario 1 was described as one that "assumes the Abigroup quantities and rates." Scenario 2 was described as one that "assumes the Abigroup quantities and the SCA rates". Scenario 3 was described as one that "assumes the SCA quantities and rates."
16 The agreed total for scenario 1 was $7,499,930. For scenario 2, it was $5,936,730. For scenario 3, it was $3,967,408.
17 The "Abigroup quantities and rates" that are the subject of scenario 1 are respectively: