### sec.642 Transitional period for existing CSG recycled water schemes
Section 196 does not apply in relation to an existing CSG recycled water scheme until the day after the transitional period for the scheme ends.
The transitional period for an existing CSG recycled water scheme starts on the commencement and ends on the day provided for under subsections (3) to (5).
If the relevant CSG environmental authority for an existing CSG recycled water scheme is prescribed for section 641, the transitional period for the scheme ends on the day the regulation prescribing the authority commences.
The transitional period for an existing CSG recycled water scheme ends on the day that is 4 months after the commencement if, by that day—
the recycled water provider has not applied for—
approval of a recycled water management plan for the scheme; or
an exclusion decision for the scheme or part of the scheme; and
the relevant CSG environmental authority for the scheme has not been prescribed for section 641.
If subsections (3) and (4) do not apply to an existing CSG recycled water scheme, the transitional period for the scheme ends on the earlier of the following days—
the day that is 15 months after the commencement;
the day a recycled water management plan is approved for the scheme or an exclusion decision is made for the scheme or part of the scheme.
s 642 ins 2010 No. 53 s 236
(sec.642-ssec.1) Section 196 does not apply in relation to an existing CSG recycled water scheme until the day after the transitional period for the scheme ends.
(sec.642-ssec.2) The transitional period for an existing CSG recycled water scheme starts on the commencement and ends on the day provided for under subsections (3) to (5).
(sec.642-ssec.3) If the relevant CSG environmental authority for an existing CSG recycled water scheme is prescribed for section 641, the transitional period for the scheme ends on the day the regulation prescribing the authority commences.
(sec.642-ssec.4) The transitional period for an existing CSG recycled water scheme ends on the day that is 4 months after the commencement if, by that day— the recycled water provider has not applied for— approval of a recycled water management plan for the scheme; or an exclusion decision for the scheme or part of the scheme; and the relevant CSG environmental authority for the scheme has not been prescribed for section 641.
(sec.642-ssec.5) If subsections (3) and (4) do not apply to an existing CSG recycled water scheme, the transitional period for the scheme ends on the earlier of the following days— the day that is 15 months after the commencement; the day a recycled water management plan is approved for the scheme or an exclusion decision is made for the scheme or part of the scheme.
- (a) the recycled water provider has not applied for— (i) approval of a recycled water management plan for the scheme; or (ii) an exclusion decision for the scheme or part of the scheme; and
- (i) approval of a recycled water management plan for the scheme; or
- (ii) an exclusion decision for the scheme or part of the scheme; and
- (b) the relevant CSG environmental authority for the scheme has not been prescribed for section 641.
- (i) approval of a recycled water management plan for the scheme; or
- (ii) an exclusion decision for the scheme or part of the scheme; and
- (a) the day that is 15 months after the commencement;
- (b) the day a recycled water management plan is approved for the scheme or an exclusion decision is made for the scheme or part of the scheme.