### sec.345 Obligation to complete later failure impact assessment
This section applies if—
the owner of a dam is given a referable dam notice for the dam and, before the effective day for the notice, the owner does not give the chief executive a failure impact assessment for the dam; or
a dam has been failure impact assessed under this part, including under subsection (2) .
The owner must—
if subsection (1) (a) applies—ensure a failure impact assessment of the dam is completed and given to the chief executive within the period stated in the referable dam notice under section 342A (2) (d) ; or
otherwise—ensure another failure impact assessment of the dam is completed and given to the chief executive within the period stated in the notice given to the owner under section 350 .
Maximum penalty—1,665 penalty units.
This provision is an executive liability provision—see section 487 .
s 345 amd 2010 No. 20 s 151 ; 2013 No. 51 s 229 sch 1
sub 2017 No. 11 s 10
(sec.345-ssec.1) This section applies if— the owner of a dam is given a referable dam notice for the dam and, before the effective day for the notice, the owner does not give the chief executive a failure impact assessment for the dam; or a dam has been failure impact assessed under this part, including under subsection (2) .
(sec.345-ssec.2) The owner must— if subsection (1) (a) applies—ensure a failure impact assessment of the dam is completed and given to the chief executive within the period stated in the referable dam notice under section 342A (2) (d) ; or otherwise—ensure another failure impact assessment of the dam is completed and given to the chief executive within the period stated in the notice given to the owner under section 350 . Maximum penalty—1,665 penalty units. This provision is an executive liability provision—see section 487 .
- (a) the owner of a dam is given a referable dam notice for the dam and, before the effective day for the notice, the owner does not give the chief executive a failure impact assessment for the dam; or
- (b) a dam has been failure impact assessed under this part, including under subsection (2) .
- (a) if subsection (1) (a) applies—ensure a failure impact assessment of the dam is completed and given to the chief executive within the period stated in the referable dam notice under section 342A (2) (d) ; or
- (b) otherwise—ensure another failure impact assessment of the dam is completed and given to the chief executive within the period stated in the notice given to the owner under section 350 .