### sec.1285 Unfinished process provided by water plan for release of particular unallocated water
This section applies if—
immediately before the commencement, a water plan provided to any extent for a process for the release of unallocated water held as a general reserve under the water plan; and
the process started before the commencement but has not ended.
The process continues to apply in relation to the release of the unallocated water, as if the Mineral, Water and Other Legislation Amendment Act 2018 had not been enacted.
s 1285 ins 2018 No. 24 s 280
(sec.1285-ssec.1) This section applies if— immediately before the commencement, a water plan provided to any extent for a process for the release of unallocated water held as a general reserve under the water plan; and the process started before the commencement but has not ended.
(sec.1285-ssec.2) The process continues to apply in relation to the release of the unallocated water, as if the Mineral, Water and Other Legislation Amendment Act 2018 had not been enacted.
- (a) immediately before the commencement, a water plan provided to any extent for a process for the release of unallocated water held as a general reserve under the water plan; and
- (b) the process started before the commencement but has not ended.