### sec.1003B Condamine and Balonne Resource Operations Plan amended
On the commencement of this section, the CB ROP is amended by including the deferred aspect in the CB ROP.
Subsection (1) applies despite any other provision of this Act.
The CB ROP as amended under subsection (1) is the resource operations plan for the Water Resource (Condamine and Balonne) Plan 2004 .
This section does not affect the power of—
the chief executive to further amend the CB ROP; or
the Governor in Council to approve a further amendment of the CB ROP; or
the chief executive to prepare, or the Governor in Council to approve, a resource operations plan to replace the CB ROP as amended from time to time, including under subsection (1) ; or
the Governor in Council to repeal the CB ROP as amended from time to time, including under subsection (1) .
In this section—
CB ROP means the Condamine and Balonne Resource Operations Plan approved by the Governor in Council on 11 December 2008.
deferred aspect means the provisions for the CB ROP included in the document called ‘Condamine and Balonne resource operations plan amendment incorporating the Lower Balonne area’ approved by the chief executive on 5 March 2010.
On the commencement of this section, the document is available for inspection at the department’s office at 41 George Street, Brisbane and on the department’s website.
s 1003B ins 2010 No. 12 s 243
(sec.1003B-ssec.1) On the commencement of this section, the CB ROP is amended by including the deferred aspect in the CB ROP.
(sec.1003B-ssec.2) Subsection (1) applies despite any other provision of this Act.
(sec.1003B-ssec.3) The CB ROP as amended under subsection (1) is the resource operations plan for the Water Resource (Condamine and Balonne) Plan 2004 .
(sec.1003B-ssec.4) This section does not affect the power of— the chief executive to further amend the CB ROP; or the Governor in Council to approve a further amendment of the CB ROP; or the chief executive to prepare, or the Governor in Council to approve, a resource operations plan to replace the CB ROP as amended from time to time, including under subsection (1) ; or the Governor in Council to repeal the CB ROP as amended from time to time, including under subsection (1) .
(sec.1003B-ssec.5) In this section— CB ROP means the Condamine and Balonne Resource Operations Plan approved by the Governor in Council on 11 December 2008. deferred aspect means the provisions for the CB ROP included in the document called ‘Condamine and Balonne resource operations plan amendment incorporating the Lower Balonne area’ approved by the chief executive on 5 March 2010. On the commencement of this section, the document is available for inspection at the department’s office at 41 George Street, Brisbane and on the department’s website.
- (a) the chief executive to further amend the CB ROP; or
- (b) the Governor in Council to approve a further amendment of the CB ROP; or
- (c) the chief executive to prepare, or the Governor in Council to approve, a resource operations plan to replace the CB ROP as amended from time to time, including under subsection (1) ; or
- (d) the Governor in Council to repeal the CB ROP as amended from time to time, including under subsection (1) .