QLDIn ForceAct
Waste Reduction and Recycling Act 2011
sec.173ZBShow cause notice
Start here
Get a plain-English read of sec.173ZB
Turn the raw legal text into a practical explanation grounded in Waste Reduction and Recycling Act 2011.
### sec.173ZB Show cause notice
This section applies if the chief executive proposes to—
amend an approval (the proposed action ); or
suspend or cancel an approval (also the proposed action ).
The chief executive must give a notice (a show cause notice ) about the proposed action to the holder of the approval.
The show cause notice must state the following—
the proposed action;
if the proposed action is an amendment—the proposed amendment;
if the proposed action is suspension—the proposed period of the suspension;
the grounds for the proposed action;
the facts and circumstances that form the basis for the grounds;
that the holder may, within a stated period (the show cause period ), make a written submission to the chief executive about why the proposed action should not be taken.
The show cause period must end at least 28 days after the holder of the approval is given the show cause notice.
s 173ZB ins 2014 No. 59 s 167
sub 2017 No. 31 ss 23 – 24
(sec.173ZB-ssec.1) This section applies if the chief executive proposes to— amend an approval (the proposed action ); or suspend or cancel an approval (also the proposed action ).
(sec.173ZB-ssec.2) The chief executive must give a notice (a show cause notice ) about the proposed action to the holder of the approval.
(sec.173ZB-ssec.3) The show cause notice must state the following— the proposed action; if the proposed action is an amendment—the proposed amendment; if the proposed action is suspension—the proposed period of the suspension; the grounds for the proposed action; the facts and circumstances that form the basis for the grounds; that the holder may, within a stated period (the show cause period ), make a written submission to the chief executive about why the proposed action should not be taken.
(sec.173ZB-ssec.4) The show cause period must end at least 28 days after the holder of the approval is given the show cause notice.
- (a) amend an approval (the proposed action ); or
- (b) suspend or cancel an approval (also the proposed action ).
- (a) the proposed action;
- (b) if the proposed action is an amendment—the proposed amendment;
- (c) if the proposed action is suspension—the proposed period of the suspension;
- (d) the grounds for the proposed action;
- (e) the facts and circumstances that form the basis for the grounds;
- (f) that the holder may, within a stated period (the show cause period ), make a written submission to the chief executive about why the proposed action should not be taken.