sec.105WLiability of public utility provider to pay additional expenses incurred by local government
Start here
Get a plain-English read of sec.105W
Turn the raw legal text into a practical explanation grounded in Transport Infrastructure Act 1994.
### sec.105W Liability of public utility provider to pay additional expenses incurred by local government
This section applies if a local government incurs additional expense in carrying out local government tollway infrastructure works on local government tollway corridor land because a public utility provider—
did not give within a reasonable time information asked for by the local government as mentioned in section 105S (2) ; or
in giving information as mentioned in section 105S (2) to the local government, did not define in enough detail the location of public utility plant; or
did something mentioned in section 105N (1) in relation to public utility plant other than under the local government’s requirements under this division.
Unless the local government otherwise agrees, the public utility provider is liable to pay the local government the additional expense.
s 105W ins 2005 No. 67 s 32
(sec.105W-ssec.1) This section applies if a local government incurs additional expense in carrying out local government tollway infrastructure works on local government tollway corridor land because a public utility provider— did not give within a reasonable time information asked for by the local government as mentioned in section 105S (2) ; or in giving information as mentioned in section 105S (2) to the local government, did not define in enough detail the location of public utility plant; or did something mentioned in section 105N (1) in relation to public utility plant other than under the local government’s requirements under this division.
(sec.105W-ssec.2) Unless the local government otherwise agrees, the public utility provider is liable to pay the local government the additional expense.
- (a) did not give within a reasonable time information asked for by the local government as mentioned in section 105S (2) ; or
- (b) in giving information as mentioned in section 105S (2) to the local government, did not define in enough detail the location of public utility plant; or
- (c) did something mentioned in section 105N (1) in relation to public utility plant other than under the local government’s requirements under this division.