### sec.41 Notice for entry to land under s 40
Before the Coordinator-General or a person authorised under section 40 enters someone else’s land, the Coordinator-General or the person must—
give at least 7 days written notice of the entry to the land’s owner or occupier; or
obtain the written agreement of the land’s owner or occupier to the entry.
The Coordinator-General or person need not comply with subsection (1) for—
urgent remedial action on the railway; or
maintenance on a road.
However, if urgent remedial action is required, the Coordinator-General or person must give the land’s owner or occupier as much oral notice as is practicable.
(sec.41-ssec.1) Before the Coordinator-General or a person authorised under section 40 enters someone else’s land, the Coordinator-General or the person must— give at least 7 days written notice of the entry to the land’s owner or occupier; or obtain the written agreement of the land’s owner or occupier to the entry.
(sec.41-ssec.2) The Coordinator-General or person need not comply with subsection (1) for— urgent remedial action on the railway; or maintenance on a road.
(sec.41-ssec.3) However, if urgent remedial action is required, the Coordinator-General or person must give the land’s owner or occupier as much oral notice as is practicable.
- (a) give at least 7 days written notice of the entry to the land’s owner or occupier; or
- (b) obtain the written agreement of the land’s owner or occupier to the entry.
- (a) urgent remedial action on the railway; or
- (b) maintenance on a road.